13547 W DESMOND ST 91331
Certificate Information: 13547 W DESMOND ST 91331
- Application / Permit
- 18014-20000-06641
- Plan Check / Job No.
- B18VN20010
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (22) Storage Building
- Work Description
- NEW STORAGE BLDG (90'-2"X36'-4"). RE-STRIP PARKING ON LOT
- Permit Issued
- Issued on 6/4/2020
- Issuing Office
- Current Status
- Issued on 6/4/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/19/2018 | APPLICANT |
| Disabled Access Plans Picked Up | 12/18/2018 | APPLICANT |
| Green Plans Picked Up | 12/19/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 12/20/2018 | ALYSSA N NARCISO |
| Corrections Issued | 1/7/2019 | ALYSSA N NARCISO |
| Quality Review Completed | 1/11/2019 | OMID HEDAYAT |
| Applicant returned to address corrections | 9/18/2019 | ALYSSA N NARCISO |
| Applicant returned to address corrections | 12/10/2019 | ALYSSA N NARCISO |
| Applicant returned to address corrections | 2/3/2020 | ALYSSA N NARCISO |
| Plan Check Approved | 4/22/2020 | ALYSSA N NARCISO |
| Issued | 6/4/2020 | APPLICANT |
| Building Plans Picked Up | 6/5/2020 | APPLICANT |
Permit Application Clearance Information
| CPC | Cleared | 2/6/2019 | DAISY BENICIA |
| Eng Process Fee Ord 176,300 | Cleared | 2/6/2019 | APEKSHYA BAJRACHARYA |
| Hydrant and Access approval | Cleared | 2/6/2019 | JOHN DALLAS |
| Permit | Cleared | 2/6/2019 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 2/6/2019 | APEKSHYA BAJRACHARYA |
| ZI | Cleared | 2/11/2019 | ANNA VIDAL |
| DAS Clearance | Cleared | 2/19/2019 | NORLITO MEDRANO |
| Prkng lot landscape/Water mgmt | Cleared | 5/24/2019 | RINA LARA |
| Address approval | Cleared | 9/4/2019 | CELINA MORENO |
| Trees in Parkway | Cleared | 9/4/2019 | ADRIAN SANCHEZ |
| Green Code | Cleared | 10/15/2019 | DAVID MATSON |
| Low Impact Development | Cleared | 3/11/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 3/19/2020 | JOHN LIN |
Contact Information
| Architect | Azarnoush,, Farshad; Lic. No.: C19247 | 13743 VENTURA BLVD # 270 SHERMAN OAKS, CA 91423 |
| Contractor | Owner-Builder | , |
| Engineer | Vasquez,, Luis Fernando; Lic. No.: C56232 | 1551 RANDALL ST GLENDALE, CA 91201 |
Inspector Information
| JOHN KITCKO, (818) 374-1109 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/14/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| METHANE-Barrier | 7/14/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| METHANE-Subgrade | 7/14/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 7/28/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| METHANE-Barrier | 7/28/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| METHANE-Subgrade | 7/28/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 7/30/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| METHANE-Barrier | 7/30/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| METHANE-Subgrade | 7/30/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 8/6/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| METHANE-Barrier | 8/6/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| METHANE-Subgrade | 8/6/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 8/10/2021 | Partial Approval | DANIEL VARNUM |
| METHANE-Barrier | 8/10/2021 | Not Ready for Inspection | DANIEL VARNUM |
| METHANE-Subgrade | 8/10/2021 | Not Ready for Inspection | DANIEL VARNUM |
| Footing/Foundation/Slab | 8/23/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| METHANE-Barrier | 8/23/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| METHANE-Subgrade | 8/23/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| METHANE-Barrier | 9/22/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| METHANE-Subgrade | 9/22/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Masonry Wall/Backfill | 9/22/2021 | Corrections Issued | DANNY RODRIGUEZ |
| METHANE-Barrier | 9/24/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| METHANE-Subgrade | 9/24/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Masonry Wall/Backfill | 9/24/2021 | Partial Approval | DANNY RODRIGUEZ |
| METHANE-Barrier | 10/4/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| METHANE-Subgrade | 10/4/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Masonry Wall/Backfill | 10/4/2021 | Partial Approval | DANNY RODRIGUEZ |
| METHANE-Barrier | 10/7/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| METHANE-Subgrade | 10/7/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Masonry Wall/Backfill | 10/7/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| METHANE-Barrier | 10/13/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| METHANE-Subgrade | 10/13/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Masonry Wall/Backfill | 10/13/2021 | Partial Approval | DANNY RODRIGUEZ |
| METHANE-Barrier | 12/15/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| METHANE-Subgrade | 12/15/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Reinforced Masonry Frame | 12/15/2021 | Corrections Issued | DANNY RODRIGUEZ |
| METHANE-Barrier | 12/28/2021 | Not Ready for Inspection | DANIEL VARNUM |
| METHANE-Subgrade | 12/28/2021 | Not Ready for Inspection | DANIEL VARNUM |
| Masonry Wall/Backfill | 12/28/2021 | Corrections Issued | DANIEL VARNUM |
| METHANE-Barrier | 1/4/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| METHANE-Subgrade | 1/4/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Reinforced Masonry Frame | 1/4/2022 | Partial Approval | DANNY RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2022 | No Access for Inspection | DANNY RODRIGUEZ |
| Green Building Rough | 2/3/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| METHANE-Rough | 2/3/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 2/3/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/8/2022 | No Access for Inspection | DANNY RODRIGUEZ |
| Green Building Rough | 2/8/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| METHANE-Rough | 2/8/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 2/8/2022 | Partial Inspection | DANNY RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2022 | Partial Approval | DANNY RODRIGUEZ |
| Pre-Inspection | 7/21/2022 | Not Ready for Inspection | GREGORY POMISH |
| Footing/Foundation/Slab | 9/12/2022 | Partial Inspection | DANNY RODRIGUEZ |
| METHANE-Barrier | 9/12/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| METHANE-Subgrade | 9/12/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 9/14/2022 | Partial Approval | DANNY RODRIGUEZ |
| Green Building Rough | 10/17/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| METHANE-Rough | 10/17/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 10/17/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Wood Frame | 10/17/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Green Building Rough | 12/9/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| METHANE-Rough | 12/9/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 12/9/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Wood Frame | 12/9/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Special/Order Compliance | 1/17/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Green Building Rough | 2/21/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| METHANE-Rough | 2/21/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 2/21/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Wood Frame | 2/21/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Green Building Rough | 4/3/2023 | Approved | DANNY RODRIGUEZ |
| METHANE-Rough | 4/3/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 4/3/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Wood Frame | 4/3/2023 | Partial Inspection | DANNY RODRIGUEZ |
| Drywall Nailing | 4/13/2023 | Not Ready for Inspection | BRIAN KELLY |
| Drywall Nailing | 4/20/2023 | Partial Approval | DANNY RODRIGUEZ |
| Special/Order Compliance | 11/1/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Special/Order Compliance | 5/20/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Special/Order Compliance | 10/1/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Special/Order Compliance | 2/6/2025 | Partial Inspection | DANNY RODRIGUEZ |