5869 W 74TH ST 90045
Certificate Information: 5869 W 74TH ST 90045
- Application / Permit
- 18014-20000-06495
- Plan Check / Job No.
- B18VN19638
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 20' x 6' ADDITION TO ENLARGE LIVING ROOM; 5' X 20' TRELLIS ADDITION TO FRONT OF DWELLING; 15' X 9'-8" IRREGULAR SHAPED ADDITION TO ENLARGE BEDROOM; 20'-10" X 4'-8" TRELLIS ADDITION TO REAR OF DWELLING; INTEROR REMODEL
- Permit Issued
- Issued on 12/6/2018
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/14/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 11/14/2018 | SELLA BENYAMIN |
| Corrections Issued | 11/15/2018 | SELLA BENYAMIN |
| Building Plans Picked Up | 11/16/2018 | APPLICANT |
| Plan Check Approved | 12/6/2018 | SELLA BENYAMIN |
| Issued | 12/6/2018 | LADBS |
| CofO in Progress | 2/3/2023 | BOBBY KEY |
| Permit Finaled | 2/7/2023 | DANIEL ORRANTE |
| CofO Issued | 2/7/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/7/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/21/2018 | MAHELET GEBEYHU |
| Roof/Waste drainage to street | Cleared | 11/21/2018 | MAHELET GEBEYHU |
| Grading Pre-Inspection | Cleared | 12/3/2018 | TIMOTHY POWELL |
| Hold | Cleared | 1/18/2019 | LOURDES RAMIRO |
Contact Information
| No Data Available. |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/23/2019 | Approved | TIM CHRISTENSEN |
| Underground Mechanical | 2/1/2019 | Approved | TIM CHRISTENSEN |
| BUILDING-Rough-Frame | 3/28/2019 | Not Ready for Inspection | TIM CHRISTENSEN |
| Green Building Rough | 3/28/2019 | Not Ready for Inspection | TIM CHRISTENSEN |
| MERV13>=Rough | 3/28/2019 | Not Ready for Inspection | TIM CHRISTENSEN |
| Rough-Elec/Plmb/HVAC | 3/28/2019 | Not Ready for Inspection | TIM CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2019 | No Access for Inspection | JUAN VALENZUELA |
| Green Building Rough | 4/10/2019 | Not Ready for Inspection | JUAN VALENZUELA |
| MERV13>=Rough | 4/10/2019 | Not Ready for Inspection | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2019 | Conditional Approval | JUAN VALENZUELA |
| Green Building Rough | 4/24/2019 | Not Ready for Inspection | JUAN VALENZUELA |
| MERV13>=Rough | 4/24/2019 | Not Ready for Inspection | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2019 | Approved | CRAIG DAVIS |
| BUILDING-Rough-Frame | 5/30/2019 | Not Ready for Inspection | JUAN VALENZUELA |
| ELECTRICAL-Rough | 5/30/2019 | Corrections Issued | JUAN VALENZUELA |
| Green Building Rough | 5/30/2019 | Not Ready for Inspection | JUAN VALENZUELA |
| HVAC-Rough | 5/30/2019 | Not Ready for Inspection | JUAN VALENZUELA |
| MERV13>=Rough | 5/30/2019 | Not Ready for Inspection | JUAN VALENZUELA |
| PLUMBING-Rough | 5/30/2019 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 6/13/2019 | Partial Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 6/13/2019 | Approved | JUAN VALENZUELA |
| Green Building Rough | 6/13/2019 | Not Ready for Inspection | JUAN VALENZUELA |
| HVAC-Rough | 6/13/2019 | Approved | JUAN VALENZUELA |
| MERV13>=Rough | 6/13/2019 | Not Ready for Inspection | JUAN VALENZUELA |
| Insulation | 7/11/2019 | Not Ready for Inspection | JUAN VALENZUELA |
| Interior/Exterior Lathing | 7/11/2019 | Not Ready for Inspection | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 7/15/2019 | Approved | JUAN VALENZUELA |
| Green Building Rough | 7/15/2019 | Approved | JUAN VALENZUELA |
| Insulation | 7/15/2019 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 7/15/2019 | Approved | JUAN VALENZUELA |
| MERV13>=Rough | 7/15/2019 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 7/30/2019 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 8/12/2019 | Not Ready for Inspection | JUAN VALENZUELA |
| Interior/Exterior Lathing | 8/30/2019 | Approved | KENNETH NAGLE |
| Shower Pan | 8/30/2019 | Approved | KENNETH NAGLE |
| Final | 1/27/2020 | Corrections Issued | DAVID FEILER |
| Green Building Final | 1/27/2020 | Not Ready for Inspection | DAVID FEILER |
| MERV13>=Final | 1/27/2020 | Not Ready for Inspection | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 1/27/2020 | SGSOV Not Ready | DAVID FEILER |
| Smoke Detectors | 1/27/2020 | Approved | DAVID FEILER |
| Final | 12/11/2020 | Corrections Issued | JUAN VALENZUELA |
| Green Building Final | 12/11/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| MERV13>=Final | 12/11/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 12/11/2020 | SGSOV Not Ready | JUAN VALENZUELA |
| Final | 10/25/2022 | Not Ready for Inspection | BOBBY KEY |
| Green Building Final | 10/25/2022 | Not Ready for Inspection | BOBBY KEY |
| MERV13>=Final | 10/25/2022 | Not Ready for Inspection | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 10/25/2022 | SGSOV Approved | BOBBY KEY |
| ELECTRICAL-Final | 1/26/2023 | Approved | BOBBY KEY |
| Final | 1/26/2023 | Corrections Issued | BOBBY KEY |
| Green Building Final | 1/26/2023 | Approved | BOBBY KEY |
| HVAC-Final | 1/26/2023 | Corrections Issued | BOBBY KEY |
| MERV13>=Final | 1/26/2023 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 1/26/2023 | Approved | BOBBY KEY |
| Final | 2/1/2023 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Final | 2/1/2023 | Corrections Issued | BOBBY KEY |
| MERV13>=Final | 2/1/2023 | Approved | BOBBY KEY |
| Final | 2/3/2023 | OK to Issue CofO | BOBBY KEY |
| HVAC-Final | 2/3/2023 | Approved | BOBBY KEY |