16630 W CALNEVA DR 91436
Certificate Information: 16630 W CALNEVA DR 91436
- Application / Permit
- 18014-20000-06473
- Plan Check / Job No.
- B18VN19545
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL & 12'1"X6'9; 39'6"X27'2";1'3"X11'2";18'6"X10'2" IRREGULAR SHAPED ADDITIONS TO (E) 2-STORY SFD TO EXPAND SIZE TO 79'2"X46'. NFPA 13D FIRE SPRINKLERS REQ'D
- Permit Issued
- Issued on 3/13/2019
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 6/5/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/13/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 11/20/2018 | MARVEL DELACRUZ |
| Corrections Issued | 11/23/2018 | MARVEL DELACRUZ |
| Green Plans Picked Up | 11/28/2018 | APPLICANT |
| Quality Review Completed | 11/29/2018 | STEVEN KIM |
| Building Plans Picked Up | 11/29/2018 | APPLICANT |
| Applicant returned to address corrections | 1/16/2019 | MARVEL DELACRUZ |
| Plan Check Approved | 2/4/2019 | MARVEL DELACRUZ |
| Issued | 3/13/2019 | LADBS |
| CofO in Progress | 3/23/2021 | RONALD COWAN |
| CofO Issued | 6/5/2021 | MICHAEL SMITH |
| Permit Finaled | 6/5/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 12/5/2018 | KRISTEN LY |
| BHO/Hillside ordinance | Cleared | 12/5/2018 | KRISTEN LY |
| BHO/Hillside ordinance | Cleared | 12/5/2018 | KRISTEN LY |
| Eng Process Fee Ord 176,300 | Cleared | 12/5/2018 | KRISTEN LY |
| Sewer availability | Cleared | 12/5/2018 | KRISTEN LY |
| Distance to fire station | Cleared | 12/10/2018 | ROBERT DUFF |
| Hydrant and Access approval | Cleared | 12/10/2018 | ROBERT DUFF |
| Green Code | Cleared | 1/15/2019 | DAVID MATSON |
| Low Impact Development | Cleared | 1/16/2019 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 1/17/2019 | JOSE CRUZ RODRIGUEZ |
| Specific Plan | Cleared | 1/29/2019 | ALYCIA WITZLING |
Contact Information
| Architect | Farhad,, Farshid; Lic. No.: C19859 | 840 20TH ST. # 13 SANTA MONICA, CA 90403 |
| Contractor | Berjis S Inc; Lic. No.: 809228-B | 1451 PRINCETON STREET # 4 SANTA MONICA, CA 90049 |
| Engineer | Farhad,, Bijan; Lic. No.: S2138 | 532 N GREENCRAIG RD LOS ANGELES, CA 90049 |
| Engineer | Jahanpour-Burke,, Hooshmand; Lic. No.: L8230 | 830 S DURANGO DR STE 100 LAS VEGAS, NV 89145 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/17/2019 | Not Ready for Inspection | MICHAEL YOUNG |
| Deputy Drilled-In Anchors | 6/24/2019 | Partial Approval | MICHAEL YOUNG |
| Footing/Foundation/Slab | 7/2/2019 | Corrections Issued | MICHAEL YOUNG |
| Sewer | 7/2/2019 | Approved | MICHAEL YOUNG |
| Footing/Foundation/Slab | 7/17/2019 | Not Ready for Inspection | MICHAEL YOUNG |
| Footing/Foundation/Slab | 7/19/2019 | Partial Approval | MICHAEL YOUNG |
| Excavation/Setback/Form/Re-Bar | 7/23/2019 | Approved | MICHAEL YOUNG |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2019 | Partial Approval | RONALD COWAN |
| Footing/Foundation/Slab | 9/18/2019 | Partial Approval | RONALD COWAN |
| BUILDING-Rough-Frame | 9/26/2019 | Partial Approval | RONALD COWAN |
| Green Building Rough | 9/26/2019 | Partial Inspection | RONALD COWAN |
| Verify Sprinkler Sign Off | 9/26/2019 | Not Ready for Inspection | RONALD COWAN |
| Special/Order Compliance | 9/30/2019 | Corrections Issued | RONALD COWAN |
| Footing/Foundation/Slab | 11/13/2019 | Partial Approval | RONALD COWAN |
| PLUMBING-Rough | 11/13/2019 | Partial Approval | RONALD COWAN |
| HVAC-Rough | 12/9/2019 | Approved | RONALD COWAN |
| PLUMBING-Rough | 12/9/2019 | Approved | RONALD COWAN |
| ELECTRICAL-Rough | 1/21/2020 | Approved | RONALD COWAN |
| Wood Frame | 1/21/2020 | Corrections Issued | RONALD COWAN |
| Deputy Steel/Welding | 2/3/2020 | Approved | RONALD COWAN |
| BUILDING-Rough-Frame | 3/5/2020 | Approved | RONALD COWAN |
| Green Building Rough | 3/5/2020 | Approved | RONALD COWAN |
| Interior/Exterior Lathing | 3/5/2020 | Partial Approval | RONALD COWAN |
| Verify Sprinkler Sign Off | 3/5/2020 | Approved | RONALD COWAN |
| Insulation | 3/11/2020 | Approved | RONALD COWAN |
| Drywall Nailing | 3/31/2020 | Approved | RONALD COWAN |
| Shower Pan | 4/21/2020 | Approved | RONALD COWAN |
| ELECTRICAL-Final | 12/21/2020 | Corrections Issued | BRENDAN LOONEY |
| PLUMBING-Final | 12/21/2020 | Corrections Issued | BRENDAN LOONEY |
| Smoke Detectors | 12/21/2020 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Final | 1/11/2021 | No Access for Inspection | RONALD COWAN |
| Green Building Final | 1/11/2021 | No Access for Inspection | RONALD COWAN |
| HVAC-Final | 1/11/2021 | No Access for Inspection | RONALD COWAN |
| PLUMBING-Final | 1/11/2021 | No Access for Inspection | RONALD COWAN |
| Smoke Detectors | 1/11/2021 | No Access for Inspection | RONALD COWAN |
| ELECTRICAL-Final | 1/21/2021 | Approved | RONALD COWAN |
| Green Building Final | 1/21/2021 | Approved | RONALD COWAN |
| HVAC-Final | 1/21/2021 | Approved | RONALD COWAN |
| PLUMBING-Final | 1/21/2021 | Approved | RONALD COWAN |
| Smoke Detectors | 1/21/2021 | Approved | RONALD COWAN |
| Final | 3/23/2021 | OK to Issue CofO | RONALD COWAN |
| Footing/Foundation/Slab | 3/23/2021 | Approved | RONALD COWAN |
| SGSOV-Seismic Gas S/O Valve | 3/23/2021 | SGSOV Approved | RONALD COWAN |