16707 W LOS ALIMOS ST 91344
Certificate Information: 16707 W LOS ALIMOS ST 91344
- Application / Permit
- 18014-20000-06402
- Plan Check / Job No.
- B18VN19328
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR INT/EXT REMODEL WITH ONE, TWO STORY ADDN & 2ND FLR ADDITION OVER EX 1-STORY SFD TO CREATE 2-STORY SFD. SEE COMMENTS.
- Permit Issued
- Issued on 12/29/2020
- Issuing Office
- Current Status
- CofO Issued on 7/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/7/2018 | APPLICANT |
| Green Plans Picked Up | 12/6/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 12/13/2018 | HAYATO TSUCHIYA |
| Corrections Issued | 12/27/2018 | HAYATO TSUCHIYA |
| Quality Review Completed | 12/31/2018 | ABDUL CHEGENI |
| Building Plans Picked Up | 2/8/2019 | APPLICANT |
| Applicant returned to address corrections | 4/22/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 9/15/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 9/22/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 9/23/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 9/25/2020 | HAYATO TSUCHIYA |
| Plan Check Approved | 11/24/2020 | HAYATO TSUCHIYA |
| Issued | 12/29/2020 | APPLICANT |
| CofO in Progress | 7/15/2024 | JAVIER RAMOS JR |
| Permit Finaled | 7/23/2024 | RUBEN SALAS |
| CofO Issued | 7/23/2024 | RUBEN SALAS |
| Permit Finaled | 7/23/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/25/2019 | LEE GUILBEAUX |
| Sewer availability | Cleared | 11/25/2019 | LEE GUILBEAUX |
| Green Code | Cleared | 12/10/2019 | DAVID MATSON |
| Low Impact Development | Cleared | 2/18/2020 | IDA MEISAMI-FARD |
| Roof/Waste drainage to street | Cleared | 2/18/2020 | JUAN ASHTON |
Contact Information
| Architect | Honles,, Guillermo; Lic. No.: C24928 | 9825 SHADOW ISLAND DRIVE SHADOW HILLS, CA 91040 |
| Contractor | P B Construction Co Inc; Lic. No.: 370868-B | 1475 NORTH MICHIGAN AVENUE PASADENA, CA 91104 |
| Engineer | Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 | 2160 PARNELL WY ALTADENA, CA 91001 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/5/2021 | Partial Approval | MARK JOHNSON |
| BUILDING-Rough-Frame | 4/20/2021 | Not Ready for Inspection | MARK JOHNSON |
| Footing/Foundation/Slab | 4/20/2021 | Approved | MARK JOHNSON |
| Green Building Rough | 4/20/2021 | Not Ready for Inspection | MARK JOHNSON |
| Light Gage Steel Frame | 4/20/2021 | Approved | MARK JOHNSON |
| PLUMBING-Rough | 4/20/2021 | Partial Approval | MARK JOHNSON |
| Structural Steel Frame | 4/20/2021 | Partial Approval | MARK JOHNSON |
| HVAC-Rough | 4/27/2021 | Not Ready for Inspection | MARK JOHNSON |
| PLUMBING-Rough | 4/27/2021 | Partial Approval | MARK JOHNSON |
| BUILDING-Rough-Frame | 5/21/2021 | Partial Approval | MARK JOHNSON |
| Green Building Rough | 5/21/2021 | Not Ready for Inspection | MARK JOHNSON |
| PLUMBING-Rough | 7/12/2021 | Partial Approval | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 7/12/2021 | SGSOV Not Ready | JOHN HAYES |
| Sewer | 7/12/2021 | Not Ready for Inspection | JOHN HAYES |
| Wood Frame | 8/20/2021 | Conditional Approval | MARK JOHNSON |
| BUILDING-Rough-Frame | 9/16/2021 | Corrections Issued | MARK JOHNSON |
| ELECTRICAL-Rough | 9/16/2021 | Not Ready for Inspection | MARK JOHNSON |
| Green Building Rough | 9/16/2021 | Not Ready for Inspection | MARK JOHNSON |
| HVAC-Rough | 9/16/2021 | Not Ready for Inspection | MARK JOHNSON |
| BUILDING-Rough-Frame | 9/29/2021 | Approved | MARK JOHNSON |
| ELECTRICAL-Rough | 9/29/2021 | Approved | MARK JOHNSON |
| Green Building Rough | 9/29/2021 | Approved | MARK JOHNSON |
| Interior/Exterior Lathing | 9/29/2021 | Approved | MARK JOHNSON |
| PLUMBING-Rough | 9/29/2021 | Approved | MARK JOHNSON |
| Insulation | 10/21/2021 | Approved | MARK JOHNSON |
| Shower Pan | 10/21/2021 | Approved | MARK JOHNSON |
| Drywall Nailing | 11/10/2021 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Drywall Nailing | 11/17/2021 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 2/2/2022 | Approved | JESUS RODRIGUEZ |
| Pre-Inspection | 7/20/2022 | Approved | JAVIER RAMOS JR |
| Pre-Inspection | 10/19/2022 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Final | 2/14/2024 | Approved | JAVIER RAMOS JR |
| Final | 2/14/2024 | Corrections Issued | JAVIER RAMOS JR |
| HVAC-Final | 2/14/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 2/14/2024 | Approved | JAVIER RAMOS JR |
| Service/Power Release | 2/14/2024 | Corrections Issued | JAVIER RAMOS JR |
| Smoke Detectors | 2/14/2024 | Approved | JAVIER RAMOS JR |
| Final | 6/3/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| Green Building Final | 6/3/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 6/3/2024 | SGSOV Approved | JAVIER RAMOS JR |
| Final | 7/15/2024 | OK to Issue CofO | JAVIER RAMOS JR |
| Green Building Final | 7/15/2024 | Approved | JAVIER RAMOS JR |
| Service/Power Release | 7/15/2024 | Approved | JAVIER RAMOS JR |