5359 N PENFIELD AVE 91364
Certificate Information: 5359 N PENFIELD AVE 91364
- Application / Permit
- 18014-20000-06400
- Plan Check / Job No.
- B18VN19321
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR INTERIOR REMODEL AND ADD 24'9" X 57'3" (IRREGULAR) TO REAR OF (E) SINGLE STORY DWELLING, AND ADD 22'0" X 27'7" FOR A NEW SECOND FLOOR. FIRE SPRINKLER REQUIRED; NFPA 13D.
- Permit Issued
- Issued on 11/26/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/7/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 11/15/2018 | STANLEY RAAP |
| Corrections Issued | 11/19/2018 | STANLEY RAAP |
| Quality Review Completed | 11/19/2018 | STEVEN KIM |
| Building Plans Picked Up | 11/29/2018 | APPLICANT |
| Green Plans Picked Up | 11/29/2018 | APPLICANT |
| Plan Check Approved | 7/18/2019 | STANLEY RAAP |
| Issued | 11/26/2019 | LADBS |
| CofO in Progress | 9/22/2022 | PETER FOLLING |
| Permit Finaled | 3/7/2023 | DANIEL ORRANTE |
| CofO Issued | 3/7/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/7/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/13/2019 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 6/13/2019 | ADRIAN SANCHEZ |
| Green Code | Cleared | 7/11/2019 | DAVID MATSON |
| Low Impact Development | Cleared | 7/17/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 7/17/2019 | KARAN PATEL |
| GPI Written Notices | Cleared | 7/18/2019 | STANLEY RAAP |
| Grading Pre-Inspection | Cleared | 7/18/2019 | STANLEY RAAP |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cristescu,, Barbu D; Lic. No.: C72038 | 14401 SYLVAN STREET 209 VAN NUYS, CA 91401 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 1/16/2020 | Partial Approval | JOHN JANSON |
| Deputy Drilled-In Anchors | 1/24/2020 | Approved | DONALD SUNSERI |
| Footing/Foundation/Slab | 1/31/2020 | Not Ready for Inspection | JOHN KIDWELL |
| Footing/Foundation/Slab | 2/6/2020 | Partial Approval | DAVID SANDOVAL |
| Footing/Foundation/Slab | 3/2/2020 | Approved | PETER FOLLING |
| BUILDING-Rough-Frame | 4/23/2020 | Partial Approval | RONALD COWAN |
| Green Building Rough | 4/23/2020 | Not Ready for Inspection | RONALD COWAN |
| Pre-Inspection | 6/29/2020 | Partial Inspection | MICHAEL TEMPLE |
| BUILDING-Rough-Frame | 7/20/2020 | Corrections Issued | RONALD COWAN |
| ELECTRICAL-Rough | 7/20/2020 | Approved | RONALD COWAN |
| Green Building Rough | 7/20/2020 | Not Ready for Inspection | RONALD COWAN |
| PLUMBING-Rough | 7/20/2020 | Approved | RONALD COWAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2020 | Approved | RONALD COWAN |
| BUILDING-Rough-Frame | 9/18/2020 | Partial Approval | DONALD SUNSERI |
| Green Building Rough | 9/18/2020 | Not Ready for Inspection | DONALD SUNSERI |
| HVAC-Rough | 9/18/2020 | Approved | DONALD SUNSERI |
| BUILDING-Rough-Frame | 10/6/2020 | Approved | RONALD COWAN |
| Green Building Rough | 10/6/2020 | Approved | RONALD COWAN |
| Insulation | 10/15/2020 | Corrections Issued | PAUL CHOPP |
| Drywall Nailing | 11/18/2020 | Approved | RONALD COWAN |
| Interior/Exterior Lathing | 11/18/2020 | Partial Approval | RONALD COWAN |
| Shower Pan | 11/18/2020 | Approved | RONALD COWAN |
| Interior/Exterior Lathing | 12/23/2020 | Partial Approval | PAUL CHOPP |
| Gas Test | 1/29/2021 | Approved | PAUL CHOPP |
| ELECTRICAL-Final | 9/8/2022 | Not Ready for Inspection | PETER FOLLING |
| Final | 9/8/2022 | Corrections Issued | PETER FOLLING |
| Green Building Final | 9/8/2022 | Approved | PETER FOLLING |
| HVAC-Final | 9/8/2022 | Approved | PETER FOLLING |
| PLUMBING-Final | 9/8/2022 | Approved | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 9/8/2022 | SGSOV Not Ready | PETER FOLLING |
| Smoke Detectors | 9/8/2022 | Approved | PETER FOLLING |
| Final | 9/20/2022 | Partial Approval | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 9/20/2022 | SGSOV Approved | PETER FOLLING |
| Service/Power Release | 9/20/2022 | Approved | PETER FOLLING |
| Final | 9/22/2022 | OK to Issue CofO | PETER FOLLING |