16229 W NORDHOFF ST 91343

Certificate Information: 16229 W NORDHOFF ST 91343

Application / Permit
18014-20000-06314
Plan Check / Job No.
B18VN19081
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18' X 22'-6" DETACHED GARAGE AND ADD (10' X 14') TO CREATE A (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER ENGINEERING
Permit Issued
Issued on 8/10/2021
Issuing Office
Valley
Current Status
CofO Issued on 3/25/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/5/2018 APPLICANT
Assigned to Plan Check Engineer 11/5/2018 RAPHAEL ROSAS
Corrections Issued 11/5/2018 RAPHAEL ROSAS
Applicant returned to address corrections 3/22/2021 RAPHAEL ROSAS
Plan Check Approved 6/18/2021 RAPHAEL ROSAS
Building Plans Picked Up 6/22/2021 APPLICANT
Issued 8/10/2021 APPLICANT
CofO in Progress 3/3/2022 RAUL OLAGI
Permit Finaled 3/25/2022 RONALD MYRICK
CofO Issued 3/25/2022 RONALD MYRICK
Permit Finaled 3/25/2022 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 11/8/2018 KAYLA PEJI
Roof/Waste drainage to street Cleared 11/8/2018 KAYLA PEJI
Eng Process Fee Ord 176,300 Cleared 3/26/2021 GUILLERMO PETRA
Sewer availability Cleared 3/26/2021 GUILLERMO PETRA
Grading Pre-Inspection Cleared 3/30/2021 BRIAN MILLER
Construction near power lines Cleared 5/18/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/8/2021 Approved JACK KARGODORIAN
Footing/Foundation/Slab 9/13/2021 Corrections Issued JENNIFER RABUCHIN
Special/Order Compliance 9/13/2021 Corrections Issued JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 9/15/2021 Partial Approval MARK JOHNSON
Footing/Foundation/Slab 9/21/2021 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 10/1/2021 Partial Approval JACK KARGODORIAN
Gas Test 10/1/2021 Partial Approval JACK KARGODORIAN
Underground Mechanical 10/1/2021 Partial Approval JACK KARGODORIAN
BUILDING-Rough-Frame 10/13/2021 Not Ready for Inspection JACK KARGODORIAN
ELECTRICAL-Rough 10/13/2021 Approved JACK KARGODORIAN
Green Building Rough 10/13/2021 Not Ready for Inspection JACK KARGODORIAN
PLUMBING-Rough 10/13/2021 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 10/13/2021 SGSOV Approved JACK KARGODORIAN
Sewer 10/13/2021 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 11/4/2021 Corrections Issued RAUL OLAGI
Green Building Rough 11/4/2021 Corrections Issued RAUL OLAGI
HVAC-Rough 11/4/2021 Approved RAUL OLAGI
BUILDING-Rough-Frame 11/15/2021 Partial Approval RAUL OLAGI
Green Building Rough 11/15/2021 Partial Approval RAUL OLAGI
Interior/Exterior Lathing 11/15/2021 Partial Approval RAUL OLAGI
BUILDING-Rough-Frame 12/2/2021 Approved RAUL OLAGI
Green Building Rough 12/2/2021 Approved RAUL OLAGI
Insulation 12/2/2021 Approved RAUL OLAGI
Interior/Exterior Lathing 12/2/2021 Partial Approval RAUL OLAGI
Drywall Nailing 12/22/2021 Approved ALAN MORELOS
Interior/Exterior Lathing 12/22/2021 Approved ALAN MORELOS
Final 2/11/2022 Not Ready for Inspection RICHARD DOCKUS
Green Building Final 2/11/2022 Approved RICHARD DOCKUS
PLUMBING-Final 2/11/2022 Approved RICHARD DOCKUS
Smoke Detectors 2/11/2022 Approved RICHARD DOCKUS
Final 2/17/2022 Corrections Issued RAUL OLAGI
Final 3/2/2022 OK to Issue CofO RAUL OLAGI