4120 W CROMWELL AVE 90027

Certificate Information: 4120 W CROMWELL AVE 90027

Application / Permit
18014-20000-06285
Plan Check / Job No.
B18VN19006
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND REMODEL TO EX. DWELLING. ADD 2-CAR GARAGE AND REMODEL KITCHEN, BATHROOMS, AND BEDROOMS. REMOVE PORTION OF COVERED PATIO AND ADD ATTACHED TRELLIS. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 4/17/2019
Issuing Office
Valley
Current Status
CofO Issued on 4/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/2/2018 APPLICANT
Green Plans Picked Up 11/14/2018 APPLICANT
Assigned to Plan Check Engineer 11/15/2018 JEFFREY TANGONAN
Corrections Issued 11/19/2018 JEFFREY TANGONAN
Quality Review Completed 11/21/2018 ABDUL CHEGENI
Building Plans Picked Up 11/28/2018 APPLICANT
Applicant returned to address corrections 1/14/2019 JEFFREY TANGONAN
Plan Check Approved 4/17/2019 JEFFREY TANGONAN
Issued 4/17/2019 LADBS
CofO in Progress 4/15/2024 ENRIQUE MIRELES
Permit Finaled 4/18/2024 DEROLD HAUFF
CofO Issued 4/18/2024 DEROLD HAUFF
Permit Finaled 4/18/2024 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 11/30/2018 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 11/30/2018 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 11/30/2018 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 11/30/2018 HISASHI KOBAYAKAWA
Sewer availability Cleared 11/30/2018 HISASHI KOBAYAKAWA
ZI Cleared 11/30/2018 TREVOR MARTIN
Encroachment in public way Cleared 12/4/2018 STEVE MELGAR
Permit Cleared 12/4/2018 STEVE MELGAR
Construction near power lines Cleared 1/10/2019 WALTER RAMIREZ
Trees in Parkway Cleared 1/11/2019 JOHN KIM
GPI Written Notices Cleared 1/14/2019 JEFFREY TANGONAN
Grading Pre-Inspection Cleared 1/14/2019 JEFFREY TANGONAN
Green Code Cleared 3/18/2019 PARISA ZAHABI
Low Impact Development Cleared 4/11/2019 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 4/11/2019 JOHN LIN

Contact Information

Architect Manion,, Richard M; Lic. No.: C26957 11400 WEST OLYMPIC BLVD SUITE 410      LOS ANGELES, CA 90025
Contractor Intension Construction Inc; Lic. No.: 956850-B 1378 CARMONA AVE      LOS ANGELES, CA 90019
Engineer Miller,, Karen Lynn; Lic. No.: GE2257 6634 VALJEAN AVE      VAN NUYS, CA 91406
Engineer White,, William Michael; Lic. No.: C62111 19619 MATHILDE LN      SAUGUS, CA 91350
Geologist Van, Meter, James L.; Lic. No.: EG2031 6634 VALJEAN AVE      VAN NUYS, CA 91406

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/23/2019 Not Ready for Inspection BRAD BESCOS
Excavation/Setback/Form/Re-Bar 7/31/2019 Partial Approval BRAD BESCOS
Deputy Reinf. Concrete 8/1/2019 Approved BRAD BESCOS
Excavation/Setback/Form/Re-Bar 8/22/2019 Partial Approval BRAD BESCOS
Footing/Foundation/Slab 8/22/2019 Partial Approval BRAD BESCOS
Excavation/Setback/Form/Re-Bar 9/10/2019 Partial Approval BRAD BESCOS
Deputy Reinf. Concrete 9/11/2019 Approved BRAD BESCOS
Excavation/Setback/Form/Re-Bar 9/23/2019 Partial Approval BRAD BESCOS
Deputy Reinf. Concrete 9/24/2019 Approved BRAD BESCOS
Excavation/Setback/Form/Re-Bar 10/2/2019 Partial Approval BRAD BESCOS
Deputy Reinf. Concrete 10/4/2019 No Access for Inspection BRAD BESCOS
Excavation/Setback/Form/Re-Bar 10/18/2019 Partial Approval BRAD BESCOS
Deputy Reinf. Concrete 10/22/2019 No Access for Inspection BRAD BESCOS
Excavation/Setback/Form/Re-Bar 11/7/2019 Partial Approval BRAD BESCOS
Floor/Roof Diaphrgm/Shear Wall 12/19/2019 Partial Approval ARTHUR SARGSYAN
Excavation/Setback/Form/Re-Bar 4/8/2020 Partial Approval JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 4/29/2020 Partial Approval JOSEPH MCGARRY
Footing/Foundation/Slab 6/3/2020 Partial Approval JOSEPH MCGARRY
Deputy Reinf. Concrete 6/5/2020 Partial Approval CHRISTOPHER DELLEFIELD
PLUMBING-Rough 6/12/2020 Partial Approval JOSEPH MCGARRY
Footing/Foundation/Slab 6/18/2020 Partial Approval JOSEPH MCGARRY
Footing/Foundation/Slab 7/23/2020 Approved ARTHUR SARGSYAN
PLUMBING-Rough 10/2/2020 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 10/30/2020 Not Ready for Inspection JOSEPH MCGARRY
Footing/Foundation/Slab 10/30/2020 Partial Approval JOSEPH MCGARRY
PLUMBING-Rough 11/6/2020 Partial Approval DONALD CRICHLOW
Floor/Roof Diaphrgm/Shear Wall 11/10/2020 Partial Approval JOSEPH MCGARRY
HVAC-Rough 11/13/2020 Partial Approval JOSEPH MCGARRY
PLUMBING-Rough 11/13/2020 Partial Approval JOSEPH MCGARRY
Deputy Wood Construction 11/16/2020 No Access for Inspection ELMER BLAND
ELECTRICAL-Rough 11/30/2020 Partial Approval JOSEPH MCGARRY
Footing/Foundation/Slab 11/30/2020 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 12/11/2020 Partial Approval JOSEPH MCGARRY
Deputy Wood Construction 12/11/2020 No Access for Inspection ELMER BLAND
ELECTRICAL-Rough 12/11/2020 Partial Approval JOSEPH MCGARRY
Green Building Rough 12/11/2020 Partial Approval JOSEPH MCGARRY
Insulation 12/29/2020 Not Ready for Inspection JOSEPH MCGARRY
Insulation 1/26/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Underground Mechanical 1/26/2021 Partial Approval HAMIK HARTOUNIAN
Shower Pan 2/10/2021 Partial Approval JOSEPH MCGARRY
Interior/Exterior Lathing 2/18/2021 Partial Approval JOSEPH MCGARRY
HVAC-Rough 2/24/2021 Partial Approval JOSEPH MCGARRY
PLUMBING-Rough 3/8/2021 Partial Approval HAMIK HARTOUNIAN
HVAC-Rough 3/12/2021 Approved JOSEPH MCGARRY
PLUMBING-Rough 3/12/2021 Approved JOSEPH MCGARRY
ELECTRICAL-Rough 3/19/2021 Approved JOSEPH MCGARRY
Shower Pan 3/19/2021 Partial Approval JOSEPH MCGARRY
Shower Pan 3/30/2021 Approved JOSEPH MCGARRY
Deck 4/14/2021 Partial Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 4/22/2021 Partial Approval JOSEPH MCGARRY
Deck 4/22/2021 Approved JOSEPH MCGARRY
Green Building Rough 4/22/2021 Approved JOSEPH MCGARRY
Insulation 4/22/2021 Partial Approval JOSEPH MCGARRY
Special/Order Compliance 5/17/2021 Approved THOMAS LOGRASSO
Drywall Nailing 6/2/2021 Partial Approval JOSEPH MCGARRY
Interior/Exterior Lathing 6/11/2021 Partial Approval JOSEPH MCGARRY
Interior/Exterior Lathing 7/16/2021 Approved CHARLES BOGHOSKHAN
BUILDING-Rough-Frame 3/30/2022 Conditional Approval JOSEPH MCGARRY
Green Building Rough 3/30/2022 Approved JOSEPH MCGARRY
Deputy Wood Construction 4/7/2022 Approved ARTHUR SARGSYAN
Insulation 4/7/2022 Approved ARTHUR SARGSYAN
ELECTRICAL-Final 12/19/2022 Not Ready for Inspection JEFFREY MEAD
Service/Power Release 12/19/2022 Not Ready for Inspection JEFFREY MEAD
Service/Power Release 1/20/2023 Not Ready for Inspection JOSEPH MCGARRY
ELECTRICAL-Final 2/8/2023 Corrections Issued JEFFREY MEAD
ELECTRICAL-Final 3/6/2023 Not Ready for Inspection JEFFREY MEAD
ELECTRICAL-Final 3/9/2023 Approved JOSEPH MCGARRY
Gas Test 3/9/2023 Approved JOSEPH MCGARRY
PLUMBING-Final 3/9/2023 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 6/16/2023 Partial Approval ALIZAH MAYAGOITIA
Final 6/16/2023 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 6/16/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
HVAC-Final 6/16/2023 Corrections Issued ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 6/16/2023 SGSOV Not Ready ALIZAH MAYAGOITIA
Service/Power Release 6/16/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 6/16/2023 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 6/26/2023 Approved JOSEPH MCGARRY
Drywall Nailing 6/26/2023 Approved JOSEPH MCGARRY
Final 6/26/2023 Corrections Issued JOSEPH MCGARRY
Green Building Final 6/26/2023 Approved JOSEPH MCGARRY
HVAC-Final 6/26/2023 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 6/26/2023 SGSOV Approved JOSEPH MCGARRY
Final 2/27/2024 Corrections Issued ENRIQUE MIRELES
Final 4/12/2024 OK to Issue CofO ENRIQUE MIRELES