4120 W CROMWELL AVE 90027
Certificate Information: 4120 W CROMWELL AVE 90027
- Application / Permit
- 18014-20000-06285
- Plan Check / Job No.
- B18VN19006
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND REMODEL TO EX. DWELLING. ADD 2-CAR GARAGE AND REMODEL KITCHEN, BATHROOMS, AND BEDROOMS. REMOVE PORTION OF COVERED PATIO AND ADD ATTACHED TRELLIS. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 4/17/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/2/2018 | APPLICANT |
| Green Plans Picked Up | 11/14/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 11/15/2018 | JEFFREY TANGONAN |
| Corrections Issued | 11/19/2018 | JEFFREY TANGONAN |
| Quality Review Completed | 11/21/2018 | ABDUL CHEGENI |
| Building Plans Picked Up | 11/28/2018 | APPLICANT |
| Applicant returned to address corrections | 1/14/2019 | JEFFREY TANGONAN |
| Plan Check Approved | 4/17/2019 | JEFFREY TANGONAN |
| Issued | 4/17/2019 | LADBS |
| CofO in Progress | 4/15/2024 | ENRIQUE MIRELES |
| Permit Finaled | 4/18/2024 | DEROLD HAUFF |
| CofO Issued | 4/18/2024 | DEROLD HAUFF |
| Permit Finaled | 4/18/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 11/30/2018 | HISASHI KOBAYAKAWA |
| BHO/Hillside ordinance | Cleared | 11/30/2018 | HISASHI KOBAYAKAWA |
| BHO/Hillside ordinance | Cleared | 11/30/2018 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 11/30/2018 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 11/30/2018 | HISASHI KOBAYAKAWA |
| ZI | Cleared | 11/30/2018 | TREVOR MARTIN |
| Encroachment in public way | Cleared | 12/4/2018 | STEVE MELGAR |
| Permit | Cleared | 12/4/2018 | STEVE MELGAR |
| Construction near power lines | Cleared | 1/10/2019 | WALTER RAMIREZ |
| Trees in Parkway | Cleared | 1/11/2019 | JOHN KIM |
| GPI Written Notices | Cleared | 1/14/2019 | JEFFREY TANGONAN |
| Grading Pre-Inspection | Cleared | 1/14/2019 | JEFFREY TANGONAN |
| Green Code | Cleared | 3/18/2019 | PARISA ZAHABI |
| Low Impact Development | Cleared | 4/11/2019 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 4/11/2019 | JOHN LIN |
Contact Information
| Architect | Manion,, Richard M; Lic. No.: C26957 | 11400 WEST OLYMPIC BLVD SUITE 410 LOS ANGELES, CA 90025 |
| Contractor | Intension Construction Inc; Lic. No.: 956850-B | 1378 CARMONA AVE LOS ANGELES, CA 90019 |
| Engineer | Miller,, Karen Lynn; Lic. No.: GE2257 | 6634 VALJEAN AVE VAN NUYS, CA 91406 |
| Engineer | White,, William Michael; Lic. No.: C62111 | 19619 MATHILDE LN SAUGUS, CA 91350 |
| Geologist | Van, Meter, James L.; Lic. No.: EG2031 | 6634 VALJEAN AVE VAN NUYS, CA 91406 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/23/2019 | Not Ready for Inspection | BRAD BESCOS |
| Excavation/Setback/Form/Re-Bar | 7/31/2019 | Partial Approval | BRAD BESCOS |
| Deputy Reinf. Concrete | 8/1/2019 | Approved | BRAD BESCOS |
| Excavation/Setback/Form/Re-Bar | 8/22/2019 | Partial Approval | BRAD BESCOS |
| Footing/Foundation/Slab | 8/22/2019 | Partial Approval | BRAD BESCOS |
| Excavation/Setback/Form/Re-Bar | 9/10/2019 | Partial Approval | BRAD BESCOS |
| Deputy Reinf. Concrete | 9/11/2019 | Approved | BRAD BESCOS |
| Excavation/Setback/Form/Re-Bar | 9/23/2019 | Partial Approval | BRAD BESCOS |
| Deputy Reinf. Concrete | 9/24/2019 | Approved | BRAD BESCOS |
| Excavation/Setback/Form/Re-Bar | 10/2/2019 | Partial Approval | BRAD BESCOS |
| Deputy Reinf. Concrete | 10/4/2019 | No Access for Inspection | BRAD BESCOS |
| Excavation/Setback/Form/Re-Bar | 10/18/2019 | Partial Approval | BRAD BESCOS |
| Deputy Reinf. Concrete | 10/22/2019 | No Access for Inspection | BRAD BESCOS |
| Excavation/Setback/Form/Re-Bar | 11/7/2019 | Partial Approval | BRAD BESCOS |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2019 | Partial Approval | ARTHUR SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 4/8/2020 | Partial Approval | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 4/29/2020 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 6/3/2020 | Partial Approval | JOSEPH MCGARRY |
| Deputy Reinf. Concrete | 6/5/2020 | Partial Approval | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 6/12/2020 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 6/18/2020 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 7/23/2020 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Rough | 10/2/2020 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 10/30/2020 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 11/6/2020 | Partial Approval | DONALD CRICHLOW |
| Floor/Roof Diaphrgm/Shear Wall | 11/10/2020 | Partial Approval | JOSEPH MCGARRY |
| HVAC-Rough | 11/13/2020 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 11/13/2020 | Partial Approval | JOSEPH MCGARRY |
| Deputy Wood Construction | 11/16/2020 | No Access for Inspection | ELMER BLAND |
| ELECTRICAL-Rough | 11/30/2020 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 11/30/2020 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 12/11/2020 | Partial Approval | JOSEPH MCGARRY |
| Deputy Wood Construction | 12/11/2020 | No Access for Inspection | ELMER BLAND |
| ELECTRICAL-Rough | 12/11/2020 | Partial Approval | JOSEPH MCGARRY |
| Green Building Rough | 12/11/2020 | Partial Approval | JOSEPH MCGARRY |
| Insulation | 12/29/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| Insulation | 1/26/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Underground Mechanical | 1/26/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Shower Pan | 2/10/2021 | Partial Approval | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 2/18/2021 | Partial Approval | JOSEPH MCGARRY |
| HVAC-Rough | 2/24/2021 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 3/8/2021 | Partial Approval | HAMIK HARTOUNIAN |
| HVAC-Rough | 3/12/2021 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 3/12/2021 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 3/19/2021 | Approved | JOSEPH MCGARRY |
| Shower Pan | 3/19/2021 | Partial Approval | JOSEPH MCGARRY |
| Shower Pan | 3/30/2021 | Approved | JOSEPH MCGARRY |
| Deck | 4/14/2021 | Partial Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 4/22/2021 | Partial Approval | JOSEPH MCGARRY |
| Deck | 4/22/2021 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 4/22/2021 | Approved | JOSEPH MCGARRY |
| Insulation | 4/22/2021 | Partial Approval | JOSEPH MCGARRY |
| Special/Order Compliance | 5/17/2021 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 6/2/2021 | Partial Approval | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 6/11/2021 | Partial Approval | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 7/16/2021 | Approved | CHARLES BOGHOSKHAN |
| BUILDING-Rough-Frame | 3/30/2022 | Conditional Approval | JOSEPH MCGARRY |
| Green Building Rough | 3/30/2022 | Approved | JOSEPH MCGARRY |
| Deputy Wood Construction | 4/7/2022 | Approved | ARTHUR SARGSYAN |
| Insulation | 4/7/2022 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Final | 12/19/2022 | Not Ready for Inspection | JEFFREY MEAD |
| Service/Power Release | 12/19/2022 | Not Ready for Inspection | JEFFREY MEAD |
| Service/Power Release | 1/20/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Final | 2/8/2023 | Corrections Issued | JEFFREY MEAD |
| ELECTRICAL-Final | 3/6/2023 | Not Ready for Inspection | JEFFREY MEAD |
| ELECTRICAL-Final | 3/9/2023 | Approved | JOSEPH MCGARRY |
| Gas Test | 3/9/2023 | Approved | JOSEPH MCGARRY |
| PLUMBING-Final | 3/9/2023 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 6/16/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Final | 6/16/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 6/16/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Final | 6/16/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 6/16/2023 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Service/Power Release | 6/16/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Smoke Detectors | 6/16/2023 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 6/26/2023 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 6/26/2023 | Approved | JOSEPH MCGARRY |
| Final | 6/26/2023 | Corrections Issued | JOSEPH MCGARRY |
| Green Building Final | 6/26/2023 | Approved | JOSEPH MCGARRY |
| HVAC-Final | 6/26/2023 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 6/26/2023 | SGSOV Approved | JOSEPH MCGARRY |
| Final | 2/27/2024 | Corrections Issued | ENRIQUE MIRELES |
| Final | 4/12/2024 | OK to Issue CofO | ENRIQUE MIRELES |