Footing/Foundation/Slab
|
4/29/2019
|
Partial Approval
|
ANTHONY MCDOWALL
|
|
Excavation/Setback/Form/Re-Bar
|
5/31/2019
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
5/31/2019
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
6/3/2019
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
6/13/2019
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
6/24/2019
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
7/2/2019
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
7/17/2019
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
7/17/2019
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
7/22/2019
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Green Building Rough
|
7/22/2019
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Verify Sprinkler Sign Off
|
7/22/2019
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
7/25/2019
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
7/25/2019
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
7/25/2019
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
8/5/2019
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Deputy Drilled-In Anchors
|
9/20/2019
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
9/20/2019
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
9/25/2019
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Green Building Rough
|
9/25/2019
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Verify Sprinkler Sign Off
|
9/25/2019
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Deputy Drilled-In Anchors
|
9/27/2019
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Wood Construction
|
9/27/2019
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
9/30/2019
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Green Building Rough
|
9/30/2019
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Verify Sprinkler Sign Off
|
9/30/2019
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Footing/Foundation/Slab
|
10/1/2019
|
Not Ready for Inspection
|
MATT KELLERMAN
|
|
Excavation/Setback/Form/Re-Bar
|
10/2/2019
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
10/24/2019
|
Partial Approval
|
MATT KELLERMAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/14/2019
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Masonry Wall/Backfill
|
11/25/2019
|
Partial Inspection
|
ANTHONY MCDOWALL
|
|
Deputy Shotcrete
|
12/10/2019
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
12/10/2019
|
Partial Approval
|
ROBERT SHELLY
|
|
Deputy Shotcrete
|
12/11/2019
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Shotcrete
|
12/11/2019
|
Conditional Approval
|
ROBERT SHELLY
|
|
Footing/Foundation/Slab
|
1/13/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
1/27/2020
|
Partial Approval
|
MATT KELLERMAN
|
|
Excavation/Setback/Form/Re-Bar
|
2/10/2020
|
Partial Approval
|
MATT KELLERMAN
|
|
PLUMBING-Rough
|
2/27/2020
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
3/18/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Underground Mechanical
|
3/18/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
4/3/2020
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
4/14/2020
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
4/22/2020
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Underground Mechanical
|
4/22/2020
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
4/24/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
7/2/2020
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
7/2/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Wood Frame
|
7/2/2020
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
7/8/2020
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Wood Frame
|
7/8/2020
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/14/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Green Building Rough
|
7/14/2020
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Verify Sprinkler Sign Off
|
7/14/2020
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/5/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
8/27/2020
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Wood Frame
|
8/27/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Pre-Inspection
|
8/28/2020
|
Partial Inspection
|
MICHAEL PELHAM
|
|
Special/Order Compliance
|
8/28/2020
|
Approved
|
MATTHEW NUCKOLLS
|
|
PLUMBING-Rough
|
9/3/2020
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
9/8/2020
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
10/7/2020
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
10/13/2020
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Underground Mechanical
|
10/28/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Shower Pan
|
11/4/2020
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
11/10/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Shower Pan
|
11/10/2020
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Verify Sprinkler Sign Off
|
11/10/2020
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
11/20/2020
|
Approved
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
11/25/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
11/25/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Special/Order Compliance
|
11/28/2020
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
12/1/2020
|
No Access for Inspection
|
CHRISTOPHER WILSON
|
|
HVAC-Rough
|
12/1/2020
|
No Access for Inspection
|
CHRISTOPHER WILSON
|
|
Shower Pan
|
12/1/2020
|
No Access for Inspection
|
CHRISTOPHER WILSON
|
|
HVAC-Rough
|
12/2/2020
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Underground Mechanical
|
12/2/2020
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Verify Sprinkler Sign Off
|
12/3/2020
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
HVAC-Rough
|
12/7/2020
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
12/8/2020
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
12/17/2020
|
Not Ready for Inspection
|
THOMAS FINNILA
|
|
HVAC-Rough
|
12/17/2020
|
Not Ready for Inspection
|
THOMAS FINNILA
|
|
Wood Frame
|
12/17/2020
|
Not Ready for Inspection
|
THOMAS FINNILA
|
|
ELECTRICAL-Rough
|
12/18/2020
|
Not Ready for Inspection
|
GERMAN RODRIGUEZ MENDOZA
|
|
HVAC-Rough
|
12/18/2020
|
Not Ready for Inspection
|
GERMAN RODRIGUEZ MENDOZA
|
|
Insulation
|
12/18/2020
|
Not Ready for Inspection
|
GERMAN RODRIGUEZ MENDOZA
|
|
Shower Pan
|
12/18/2020
|
Partial Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Special/Order Compliance
|
12/18/2020
|
Corrections Issued
|
GERMAN RODRIGUEZ MENDOZA
|
|
ELECTRICAL-Rough
|
12/23/2020
|
Not Ready for Inspection
|
MATT KELLERMAN
|
|
HVAC-Rough
|
12/23/2020
|
Partial Approval
|
MATT KELLERMAN
|
|
ELECTRICAL-Rough
|
12/30/2020
|
Corrections Issued
|
GERMAN RODRIGUEZ MENDOZA
|
|
ELECTRICAL-Rough
|
12/31/2020
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Shower Pan
|
12/31/2020
|
Approved
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
1/6/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
HVAC-Rough
|
1/6/2021
|
Approved
|
CHRISTOPHER WILSON
|
|
Verify Sprinkler Sign Off
|
1/6/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
1/8/2021
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
1/12/2021
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Verify Sprinkler Sign Off
|
1/12/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Wood Frame
|
1/12/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Interior/Exterior Lathing
|
1/19/2021
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Interior/Exterior Lathing
|
1/25/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Verify Sprinkler Sign Off
|
1/25/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Interior/Exterior Lathing
|
2/16/2021
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
2/23/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
2/23/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Green Building Rough
|
2/23/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Interior/Exterior Lathing
|
2/23/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Rough-Elec/Plmb/HVAC
|
2/23/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Structural Steel Frame
|
2/23/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Verify Sprinkler Sign Off
|
2/23/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Wood Frame
|
2/26/2021
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
3/1/2021
|
Approved
|
CHRISTOPHER WILSON
|
|
Wood Frame
|
3/2/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
3/4/2021
|
Approved
|
CHRISTOPHER WILSON
|
|
Green Building Rough
|
3/4/2021
|
Approved
|
CHRISTOPHER WILSON
|
|
Verify Sprinkler Sign Off
|
3/4/2021
|
Approved
|
CHRISTOPHER WILSON
|
|
Insulation
|
3/8/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Drywall Nailing
|
3/12/2021
|
Not Ready for Inspection
|
GERMAN RODRIGUEZ MENDOZA
|
|
Insulation
|
3/12/2021
|
Partial Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Drywall Nailing
|
3/15/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Drywall Nailing
|
3/17/2021
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
Insulation
|
3/17/2021
|
Corrections Issued
|
ANTHONY MCDOWALL
|
|
Drywall Nailing
|
3/18/2021
|
Partial Approval
|
ANTHONY MCDOWALL
|
|
Insulation
|
3/18/2021
|
Approved
|
ANTHONY MCDOWALL
|
|
Drywall Nailing
|
3/30/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Drywall Nailing
|
4/5/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Interior/Exterior Lathing
|
4/13/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Drywall Nailing
|
4/30/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Interior/Exterior Lathing
|
10/12/2021
|
Approved
|
DANIEL ORRANTE
|
|
Drywall Nailing
|
10/19/2021
|
Approved
|
DEANDRE HOFFMAN
|
|
Gas Test
|
10/21/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Underground Mechanical
|
10/21/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
11/9/2022
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
11/9/2022
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
5/24/2023
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Service/Power Release
|
7/5/2023
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Final
|
7/7/2023
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Service/Power Release
|
7/11/2023
|
Approved
|
CHRISTOPHER WILSON
|
|
Final
|
8/24/2023
|
No Access for Inspection
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
8/24/2023
|
No Access for Inspection
|
CHRISTOPHER WILSON
|
|
Green Building Final
|
8/24/2023
|
No Access for Inspection
|
CHRISTOPHER WILSON
|
|
SGSOV-Seismic Gas S/O Valve
|
8/24/2023
|
SGSOV Not Ready
|
CHRISTOPHER WILSON
|
|
Smoke Detectors
|
8/24/2023
|
No Access for Inspection
|
CHRISTOPHER WILSON
|
|
Structural Steel Frame
|
8/24/2023
|
No Access for Inspection
|
CHRISTOPHER WILSON
|
|
Gas Test
|
10/12/2023
|
No Access for Inspection
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Final
|
10/16/2023
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Verify Sprinkler Sign Off
|
10/16/2023
|
Approved
|
CHRISTOPHER WILSON
|
|
Gas Test
|
10/17/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
PLUMBING-Final
|
10/17/2023
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
PLUMBING-Final
|
11/7/2023
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Special/Order Compliance
|
11/7/2023
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Gas Test
|
11/20/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Gas Test
|
11/21/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Final
|
11/27/2023
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Pre-Inspection
|
11/27/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Final
|
12/1/2023
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
PLUMBING-Final
|
12/1/2023
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Final
|
12/5/2023
|
Approved
|
CHRISTOPHER WILSON
|
|
PLUMBING-Final
|
12/5/2023
|
Approved
|
CHRISTOPHER WILSON
|
|
HVAC-Final
|
12/8/2023
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
HVAC-Final
|
12/11/2023
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
HVAC-Final
|
12/14/2023
|
Approved
|
CHRISTOPHER WILSON
|
|
Gas Test
|
12/22/2023
|
Approved
|
CHRISTOPHER WILSON
|
|
SGSOV-Seismic Gas S/O Valve
|
12/22/2023
|
SGSOV Approved
|
CHRISTOPHER WILSON
|
|
Final
|
12/26/2023
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
12/26/2023
|
Approved
|
CHRISTOPHER WILSON
|
|
Green Building Final
|
12/26/2023
|
Approved
|
CHRISTOPHER WILSON
|
|
Smoke Detectors
|
12/26/2023
|
Approved
|
CHRISTOPHER WILSON
|
|
Structural Steel Frame
|
12/26/2023
|
Approved
|
CHRISTOPHER WILSON
|
|
Final
|
3/7/2024
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Final
|
7/26/2024
|
OK to Issue CofO
|
CHRISTOPHER WILSON
|