15448 W LEMARSH ST 91345

Certificate Information: 15448 W LEMARSH ST 91345

Application / Permit
18014-20000-06232
Plan Check / Job No.
B18VN18820
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Remove (E) carport and remove 5'-0" x 40'-0" portion of (E) rec room / storage room. 4'-0" x 20'-0" first floor addition and 23'-0" x 20'-6" second floor addition to and convert rec room to accessory dwelling unit per ab 494 and sb 229. Convert storage room into two car garage.
Permit Issued
Issued on 7/31/2019
Issuing Office
Valley
Current Status
CofO Issued on 3/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/31/2018 APPLICANT
Assigned to Plan Check Engineer 11/8/2018 JEROME MAGAT PALMA
Corrections Issued 11/13/2018 JEROME MAGAT PALMA
Quality Review Completed 11/13/2018 ABDUL CHEGENI
Building Plans Picked Up 11/16/2018 APPLICANT
Green Plans Picked Up 11/16/2018 APPLICANT
Plan Check Approved 7/3/2019 JEROME MAGAT PALMA
Issued 7/31/2019 LADBS
CofO in Progress 11/19/2020 JENNIFER RABUCHIN
Permit Finaled 3/22/2022 RONALD MYRICK
CofO Issued 3/22/2022 RONALD MYRICK
Permit Finaled 3/22/2022 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 12/7/2018 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 6/14/2019 MARKOS PEREZ-BRAN
Sewer availability Cleared 6/14/2019 MARKOS PEREZ-BRAN
Low Impact Development Cleared 6/27/2019 ORVAL HERNANDEZ-MARCIAL
Green Code Cleared 6/28/2019 PARISA ZAHABI
Roof/Waste drainage to street Cleared 7/2/2019 APEKSHYA BAJRACHARYA
Construction near power lines Cleared 7/31/2019 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Adams,, Robert Charles; Lic. No.: C21234 22129 BRYANT STREET      CANOGA PARK, CA 91304

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/3/2020 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 2/18/2020 Approved JENNIFER RABUCHIN
PLUMBING-Rough 2/27/2020 Partial Approval JENNIFER RABUCHIN
Underground Mechanical 2/27/2020 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 3/19/2020 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 4/14/2020 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 4/14/2020 Approved JENNIFER RABUCHIN
Green Building Rough 4/14/2020 Not Ready for Inspection JENNIFER RABUCHIN
MERV13>=Rough 4/14/2020 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 4/22/2020 Partial Approval JENNIFER RABUCHIN
HVAC-Rough 4/22/2020 Approved JENNIFER RABUCHIN
PLUMBING-Rough 4/22/2020 Corrections Issued JENNIFER RABUCHIN
Shower Pan 4/22/2020 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 4/27/2020 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 4/27/2020 Partial Approval JENNIFER RABUCHIN
Shower Pan 4/27/2020 Approved JENNIFER RABUCHIN
Insulation 5/11/2020 Approved JENNIFER RABUCHIN
Drywall Nailing 5/19/2020 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Rough 5/19/2020 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 5/19/2020 Partial Approval JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 7/20/2020 Not Ready for Inspection MISAEL ESPARZA
Pre-Inspection 7/20/2020 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 7/20/2020 SGSOV Not Ready MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 7/29/2020 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 7/29/2020 SGSOV Not Ready JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 8/14/2020 Corrections Issued MICHAEL TEMPLE
Excavation/Setback/Form/Re-Bar 8/26/2020 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 9/15/2020 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 9/15/2020 Approved JENNIFER RABUCHIN
Green Building Rough 9/15/2020 Not Ready for Inspection JENNIFER RABUCHIN
MERV13>=Rough 9/15/2020 Approved JENNIFER RABUCHIN
Wood Frame 9/15/2020 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 9/22/2020 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 9/22/2020 Approved JENNIFER RABUCHIN
Service/Power Release 9/22/2020 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 11/18/2020 Approved JENNIFER RABUCHIN
Drywall Nailing 11/18/2020 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 11/18/2020 Approved JENNIFER RABUCHIN
Final 11/18/2020 OK to Issue CofO JENNIFER RABUCHIN
Gas Test 11/18/2020 Approved JENNIFER RABUCHIN
Green Building Final 11/18/2020 Approved JENNIFER RABUCHIN
HVAC-Final 11/18/2020 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 11/18/2020 Approved JENNIFER RABUCHIN
MERV13>=Final 11/18/2020 Approved JENNIFER RABUCHIN
PLUMBING-Final 11/18/2020 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 11/18/2020 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 11/18/2020 Approved JENNIFER RABUCHIN
Smoke Detectors 11/18/2020 Approved JENNIFER RABUCHIN
Special/Order Compliance 3/24/2021 Partial Inspection JENNIFER RABUCHIN