15801 W MOORPARK ST 91436

Certificate Information: 15801 W MOORPARK ST 91436

Application / Permit
18014-20000-06224
Plan Check / Job No.
B18VN18775
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL TO EX. 2 -STORY DWELLING. RELOCATE STAIRS AND ADDITION TO FIRST AND 2ND FLOOR. ADD WASHER/DRYER TO EX. GARAGE. REMODEL ALL KITCHEN, BATHROOMS, AND BEDROOMS. REFRAME BLDG. ALL WORK PER ENGINEERING. <ENTIRE BLDG. SHALL BE FULLY SPRINKLERED>
Permit Issued
Issued on 2/15/2019
Issuing Office
Valley
Current Status
CofO Issued on 8/7/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/30/2018 APPLICANT
Green Plans Picked Up 11/6/2018 APPLICANT
Assigned to Plan Check Engineer 11/8/2018 JEFFREY TANGONAN
Corrections Issued 11/14/2018 JEFFREY TANGONAN
Quality Review Completed 11/21/2018 ABDUL CHEGENI
Building Plans Picked Up 11/21/2018 APPLICANT
Applicant returned to address corrections 1/30/2019 JEFFREY TANGONAN
Plan Check Approved 2/14/2019 JEFFREY TANGONAN
Issued 2/15/2019 LADBS
CofO in Progress 8/6/2020 RONALD COWAN
CofO Issued 8/7/2020 DONALD SUNSERI
Permit Finaled 8/7/2020 DONALD SUNSERI

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/30/2019 LEE GUILBEAUX
Miscellaneous Cleared 1/30/2019 SHEILA GERSHON
Sewer availability Cleared 1/30/2019 LEE GUILBEAUX
Low Impact Development Cleared 2/7/2019 MITESH PATEL
Roof/Waste drainage to street Cleared 2/7/2019 MARKOS PEREZ-BRAN
Green Code Cleared 2/12/2019 DAVID MATSON

Contact Information

Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/9/2019 Approved MICHAEL YOUNG
Footing/Foundation/Slab 4/9/2019 Conditional Approval MICHAEL YOUNG
Deputy Drilled-In Anchors 5/6/2019 Partial Approval MICHAEL YOUNG
PLUMBING-Rough 5/9/2019 Partial Approval MICHAEL YOUNG
BUILDING-Rough-Frame 5/13/2019 Partial Approval SEAN WIRCH
Green Building Rough 5/13/2019 Not Ready for Inspection SEAN WIRCH
PLUMBING-Rough 5/14/2019 Not Ready for Inspection JOHN KIDWELL
BUILDING-Rough-Frame 5/20/2019 No Access for Inspection MICHAEL YOUNG
Green Building Rough 5/20/2019 No Access for Inspection MICHAEL YOUNG
Floor/Roof Diaphrgm/Shear Wall 6/5/2019 Partial Approval JOSEPH SAGEN
Insulation 6/5/2019 Partial Approval JOSEPH SAGEN
Sewer 6/14/2019 Not Ready for Inspection JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 6/26/2019 Partial Approval MICHAEL YOUNG
Floor/Roof Diaphrgm/Shear Wall 10/16/2019 Corrections Issued RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 11/22/2019 Corrections Issued RONALD COWAN
PLUMBING-Rough 1/23/2020 Approved RONALD COWAN
BUILDING-Rough-Frame 2/5/2020 Corrections Issued RONALD COWAN
ELECTRICAL-Rough 2/5/2020 Approved RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 2/5/2020 Not Ready for Inspection RONALD COWAN
Green Building Rough 2/5/2020 Not Ready for Inspection RONALD COWAN
BUILDING-Rough-Frame 3/16/2020 Not Ready for Inspection RONALD COWAN
Green Building Rough 3/16/2020 Corrections Issued RONALD COWAN
BUILDING-Rough-Frame 3/25/2020 Approved RONALD COWAN
Green Building Rough 3/25/2020 Approved RONALD COWAN
Verify Sprinkler Sign Off 3/25/2020 Approved RONALD COWAN
Insulation 4/2/2020 Partial Approval RONALD COWAN
Interior/Exterior Lathing 4/8/2020 Partial Approval RONALD COWAN
Drywall Nailing 4/13/2020 Approved RONALD COWAN
Shower Pan 4/13/2020 Approved RONALD COWAN
Masonry Wall/Backfill 4/21/2020 Not Ready for Inspection RONALD COWAN
Service/Power Release 4/28/2020 Not Ready for Inspection RONALD COWAN
ELECTRICAL-Final 6/4/2020 Approved RONALD COWAN
Gas Test 6/4/2020 Approved RONALD COWAN
Service/Power Release 6/4/2020 Approved RONALD COWAN
Final 7/13/2020 Corrections Issued RONALD COWAN
Footing/Foundation/Slab 7/13/2020 Approved RONALD COWAN
SGSOV-Seismic Gas S/O Valve 7/13/2020 SGSOV Not Ready RONALD COWAN
Smoke Detectors 7/13/2020 Corrections Issued RONALD COWAN
Final 7/31/2020 OK to Issue CofO RONALD COWAN
Green Building Final 7/31/2020 Approved RONALD COWAN
SGSOV-Seismic Gas S/O Valve 7/31/2020 SGSOV Approved RONALD COWAN
Smoke Detectors 7/31/2020 Approved RONALD COWAN