7305 N HILLSVIEW CT 91307

Certificate Information: 7305 N HILLSVIEW CT 91307

Application / Permit
18014-20000-06200
Plan Check / Job No.
B18VN18694
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
7'1-3/4"X11'8-1/2" & 9'4"X30'5" IRREGULAR SHAPED ADDITIONS AND REAR 10'6-3/8"X7'8" PATIO ADDITION WITH DECK ABOVE AND REMODEL TO (E) SFD
Permit Issued
Issued on 7/25/2019
Issuing Office
Valley
Current Status
CofO Issued on 3/16/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/30/2018 APPLICANT
Assigned to Plan Check Engineer 11/8/2018 MARVEL DELACRUZ
Green Plans Picked Up 11/8/2018 APPLICANT
Corrections Issued 11/12/2018 MARVEL DELACRUZ
Quality Review Completed 11/16/2018 OMID HEDAYAT
Building Plans Picked Up 11/19/2018 APPLICANT
Plan Check Approved 1/15/2019 MARVEL DELACRUZ
Issued 7/25/2019 LADBS
CofO in Progress 3/11/2021 DAVID STEPANYAN
Permit Finaled 3/16/2021 JOHN JANSON
CofO Issued 3/16/2021 JOHN JANSON
Permit Finaled 3/16/2021 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/8/2019 JOHN LIN
Roof/Waste drainage to street Cleared 1/8/2019 JOHN LIN
Sewer availability Cleared 1/8/2019 JOHN LIN
Tract Map conditions Cleared 1/8/2019 HERMINIGILDO AGUSTIN
Public Works-Highway Ded. Cleared 1/8/2019 JOHN LIN
Public Works-Open Permits Cleared 1/8/2019 JOHN LIN
Public Works-Sewers Cleared 1/8/2019 JOHN LIN
Grading Pre-Inspection Cleared 1/9/2019 MARVEL DELACRUZ
Green Code Cleared 1/15/2019 PARISA ZAHABI

Contact Information

Architect Nolan,, John Michael; Lic. No.: C21107 116 STAGECOACH ROAD      BELL CANYON, CA 91307
Contractor G N R Building Specialists; Lic. No.: 746376-B 2610 LYNNVIEW STREET      NEWBURY PARK, CA 91320
Engineer Rogers,, Mark Alan; Lic. No.: C42848 1305 LA CULEBRA CIR      CAMARILLO, CA 93012

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/12/2019 Partial Approval PETER FOLLING
Footing/Foundation/Slab 11/12/2019 Partial Approval PETER FOLLING
PLUMBING-Rough 12/24/2019 Partial Approval PETER FOLLING
Footing/Foundation/Slab 1/8/2020 Approved PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 2/12/2020 Not Ready for Inspection PETER FOLLING
HVAC-Rough 4/13/2020 Corrections Issued DAVID STEPANYAN
Shower Pan 4/13/2020 Approved DAVID STEPANYAN
Interior/Exterior Lathing 4/17/2020 Partial Approval DAVID STEPANYAN
Shower Pan 4/17/2020 Approved DAVID STEPANYAN
Insulation 4/22/2020 Partial Approval DAVID STEPANYAN
PLUMBING-Rough 4/22/2020 Corrections Issued DAVID STEPANYAN
ELECTRICAL-Rough 5/4/2020 Approved HENRY KIM
Gas Test 5/4/2020 Not Ready for Inspection HENRY KIM
Interior/Exterior Lathing 5/4/2020 Approved HENRY KIM
PLUMBING-Rough 5/4/2020 Partial Approval HENRY KIM
Gas Test 5/5/2020 Partial Approval DAVID STEPANYAN
Interior/Exterior Lathing 5/5/2020 Approved DAVID STEPANYAN
BUILDING-Rough-Frame 5/11/2020 Corrections Issued DAVID STEPANYAN
HVAC-Rough 5/11/2020 Not Ready for Inspection DAVID STEPANYAN
Insulation 5/11/2020 Partial Approval DAVID STEPANYAN
BUILDING-Rough-Frame 5/19/2020 Partial Approval DAVID STEPANYAN
Green Building Rough 5/19/2020 Not Ready for Inspection DAVID STEPANYAN
HVAC-Rough 5/21/2020 Not Ready for Inspection DAVID STEPANYAN
PLUMBING-Rough 5/21/2020 Approved DAVID STEPANYAN
BUILDING-Rough-Frame 5/22/2020 Partial Approval DAVID STEPANYAN
Green Building Rough 5/22/2020 Approved DAVID STEPANYAN
HVAC-Rough 5/22/2020 Approved DAVID STEPANYAN
BUILDING-Rough-Frame 6/8/2020 Approved DAVID STEPANYAN
Drywall Nailing 6/9/2020 Not Ready for Inspection DAVID STEPANYAN
Gas Test 6/9/2020 Not Ready for Inspection DAVID STEPANYAN
Drywall Nailing 6/10/2020 Approved DAVID STEPANYAN
Gas Test 6/10/2020 Approved DAVID STEPANYAN
ELECTRICAL-Final 8/13/2020 Corrections Issued DAVID STEPANYAN
Gas Test 8/13/2020 Approved DAVID STEPANYAN
HVAC-Final 8/13/2020 Approved DAVID STEPANYAN
ELECTRICAL-Final 8/14/2020 Approved DAVID STEPANYAN
Final 8/14/2020 Not Ready for Inspection DAVID STEPANYAN
Green Building Final 8/14/2020 Not Ready for Inspection DAVID STEPANYAN
HVAC-Final 8/14/2020 Approved DAVID STEPANYAN
PLUMBING-Final 8/14/2020 Not Ready for Inspection DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 8/14/2020 SGSOV Approved DAVID STEPANYAN
Smoke Detectors 8/14/2020 Approved DAVID STEPANYAN
PLUMBING-Final 8/19/2020 Approved DAVID STEPANYAN
Final 3/10/2021 OK to Issue CofO DAVID STEPANYAN
Green Building Final 3/10/2021 Approved DAVID STEPANYAN