8520 W HEDGES PL 90069
Certificate Information: 8520 W HEDGES PL 90069
- Application / Permit
- 18014-20000-06139
- Plan Check / Job No.
- B18VN18549
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Major remodel and proposed addition at basement. Maintain existing wall (14'-1") at west side. NFPA 13D fire sprinklers required
- Permit Issued
- Issued on 5/8/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/26/2018 | APPLICANT |
| Green Plans Picked Up | 11/28/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 11/29/2018 | ALYSSA N NARCISO |
| Corrections Issued | 12/10/2018 | ALYSSA N NARCISO |
| Quality Review Completed | 12/17/2018 | OMID HEDAYAT |
| Building Plans Picked Up | 12/18/2018 | APPLICANT |
| Applicant returned to address corrections | 1/31/2019 | ALYSSA N NARCISO |
| Applicant returned to address corrections | 3/1/2019 | ALYSSA N NARCISO |
| Applicant returned to address corrections | 5/14/2019 | ALYSSA N NARCISO |
| Applicant returned to address corrections | 6/25/2019 | ALYSSA N NARCISO |
| Applicant returned to address corrections | 7/10/2019 | ALYSSA N NARCISO |
| Applicant returned to address corrections | 12/3/2019 | ALYSSA N NARCISO |
| Applicant returned to address corrections | 12/13/2019 | ALYSSA N NARCISO |
| Applicant returned to address corrections | 1/8/2020 | ALYSSA N NARCISO |
| Applicant returned to address corrections | 1/24/2020 | ALYSSA N NARCISO |
| Applicant returned to address corrections | 1/29/2020 | ALYSSA N NARCISO |
| Plan Check Approved | 2/12/2020 | ALYSSA N NARCISO |
| Issued | 5/8/2020 | LADBS |
| CofO in Progress | 12/9/2022 | RAUL BARAJAS |
| CofO Issued | 1/4/2023 | DEROLD HAUFF |
| Permit Finaled | 1/4/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 5/8/2019 | GUILLERMO PETRA |
| BHO/Hillside ordinance | Cleared | 5/8/2019 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 5/8/2019 | GUILLERMO PETRA |
| Sewer availability | Cleared | 5/8/2019 | GUILLERMO PETRA |
| Hydrant and Access approval | Cleared | 12/12/2019 | GEORGE SUCHAND |
| Green Code | Cleared | 12/13/2019 | DAVID MATSON |
| Encroachment in public way | Cleared | 12/27/2019 | JAMES KHO |
| Excavation more than 5-ft deep | Cleared | 1/8/2020 | CALOSHA APPROVED |
| Low Impact Development | Cleared | 1/10/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 1/10/2020 | JOHN LIN |
| GPI Written Notices | Cleared | 1/24/2020 | ALYSSA N NARCISO |
| Grading Pre-Inspection | Cleared | 1/24/2020 | ALYSSA N NARCISO |
| BHO/Hillside ordinance | Cleared | 2/7/2020 | THAN WIN |
Contact Information
| Contractor | Domaen Build Inc; Lic. No.: 1052085-B | 915 S MATEO ST SUITE 205 LOS ANGELES, CA 90021 |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 6/3/2020 | Partial Approval | RAUL BARAJAS |
| Deputy Other (see comments) | 6/5/2020 | Conditional Approval | RAUL BARAJAS |
| Piling/Pier/Caisson | 6/5/2020 | Partial Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 6/11/2020 | Conditional Approval | RAUL BARAJAS |
| Deputy Drilled-In Anchors | 7/9/2020 | Conditional Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 7/20/2020 | Partial Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 7/23/2020 | Approved | RAUL BARAJAS |
| Deputy Drilled-In Anchors | 8/3/2020 | Conditional Approval | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 8/3/2020 | Partial Approval | RAUL BARAJAS |
| PLUMBING-Rough | 8/25/2020 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 12/10/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Deputy Drilled-In Anchors | 12/15/2020 | Conditional Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 12/17/2020 | Partial Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 12/18/2020 | Conditional Approval | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 12/29/2020 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 1/20/2021 | Conditional Approval | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 2/12/2021 | Corrections Issued | RAUL BARAJAS |
| Footing/Foundation/Slab | 2/12/2021 | Partial Approval | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 2/25/2021 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 2/25/2021 | Partial Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 3/1/2021 | Conditional Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 3/24/2021 | Partial Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 4/13/2021 | No Access for Inspection | BRAD BESCOS |
| Footing/Foundation/Slab | 5/3/2021 | Partial Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 5/7/2021 | Conditional Approval | RAUL BARAJAS |
| Deputy Steel/Welding | 5/14/2021 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 5/14/2021 | Partial Approval | JOSEPH MCGARRY |
| Underground Mechanical | 5/27/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Underground Mechanical | 6/1/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Underground Mechanical | 6/7/2021 | Approved | RAUL BARAJAS |
| Footing/Foundation/Slab | 6/10/2021 | Approved | RAUL BARAJAS |
| Deputy Steel/Welding | 7/9/2021 | Conditional Approval | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 7/15/2021 | Partial Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2021 | Partial Approval | RAUL BARAJAS |
| Wood Frame | 8/17/2021 | Partial Inspection | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 8/31/2021 | Corrections Issued | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2021 | Partial Approval | RAUL BARAJAS |
| ELECTRICAL-Rough | 10/4/2021 | Approved | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2021 | Conditional Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 10/8/2021 | Approved | RAUL BARAJAS |
| PLUMBING-Rough | 11/3/2021 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 12/30/2021 | No Access for Inspection | RAUL BARAJAS |
| Interior/Exterior Lathing | 1/3/2022 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 3/8/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Green Building Rough | 3/8/2022 | Approved | RAUL BARAJAS |
| HVAC-Rough | 3/8/2022 | Partial Inspection | RAUL BARAJAS |
| Light Gage Steel Frame | 3/8/2022 | Conditional Approval | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 3/8/2022 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 4/4/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Wood Frame | 4/4/2022 | Approved | RAUL BARAJAS |
| Insulation | 4/12/2022 | Approved | RAUL BARAJAS |
| Drywall Nailing | 5/2/2022 | Approved | RAUL BARAJAS |
| Shower Pan | 5/18/2022 | Approved | RAUL BARAJAS |
| Gas Test | 10/5/2022 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 10/5/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Service/Power Release | 10/5/2022 | Corrections Issued | RAUL BARAJAS |
| ELECTRICAL-Final | 10/18/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Gas Test | 10/18/2022 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Final | 10/21/2022 | Partial Inspection | RAUL BARAJAS |
| HVAC-Final | 10/21/2022 | Partial Inspection | RAUL BARAJAS |
| PLUMBING-Final | 10/21/2022 | Partial Approval | RAUL BARAJAS |
| HVAC-Final | 10/27/2022 | Corrections Issued | RAUL BARAJAS |
| ELECTRICAL-Final | 10/28/2022 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Final | 10/28/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Enclosure/Fence | 11/1/2022 | Not Ready for Inspection | RAUL BARAJAS |
| ELECTRICAL-Final | 11/4/2022 | Corrections Issued | RAUL BARAJAS |
| HVAC-Final | 11/4/2022 | Conditional Approval | RAUL BARAJAS |
| PLUMBING-Final | 11/4/2022 | Approved | RAUL BARAJAS |
| ELECTRICAL-Final | 11/16/2022 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 11/29/2022 | Approved | RAUL BARAJAS |
| Final | 11/29/2022 | Corrections Issued | RAUL BARAJAS |
| Green Building Final | 11/29/2022 | Approved | RAUL BARAJAS |
| HVAC-Final | 11/29/2022 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 11/29/2022 | SGSOV Not Ready | RAUL BARAJAS |
| Smoke Detectors | 11/29/2022 | Approved | RAUL BARAJAS |
| Structural Steel Frame | 11/29/2022 | Approved | RAUL BARAJAS |
| Final | 12/2/2022 | Not Ready for Inspection | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 12/2/2022 | SGSOV Not Ready | RAUL BARAJAS |
| Final | 12/9/2022 | OK to Issue CofO | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 12/9/2022 | SGSOV Approved | RAUL BARAJAS |