8520 W HEDGES PL 90069

Certificate Information: 8520 W HEDGES PL 90069

Application / Permit
18014-20000-06139
Plan Check / Job No.
B18VN18549
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Major remodel and proposed addition at basement. Maintain existing wall (14'-1") at west side. NFPA 13D fire sprinklers required
Permit Issued
Issued on 5/8/2020
Issuing Office
Metro
Current Status
CofO Issued on 1/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/26/2018 APPLICANT
Green Plans Picked Up 11/28/2018 APPLICANT
Assigned to Plan Check Engineer 11/29/2018 ALYSSA N NARCISO
Corrections Issued 12/10/2018 ALYSSA N NARCISO
Quality Review Completed 12/17/2018 OMID HEDAYAT
Building Plans Picked Up 12/18/2018 APPLICANT
Applicant returned to address corrections 1/31/2019 ALYSSA N NARCISO
Applicant returned to address corrections 3/1/2019 ALYSSA N NARCISO
Applicant returned to address corrections 5/14/2019 ALYSSA N NARCISO
Applicant returned to address corrections 6/25/2019 ALYSSA N NARCISO
Applicant returned to address corrections 7/10/2019 ALYSSA N NARCISO
Applicant returned to address corrections 12/3/2019 ALYSSA N NARCISO
Applicant returned to address corrections 12/13/2019 ALYSSA N NARCISO
Applicant returned to address corrections 1/8/2020 ALYSSA N NARCISO
Applicant returned to address corrections 1/24/2020 ALYSSA N NARCISO
Applicant returned to address corrections 1/29/2020 ALYSSA N NARCISO
Plan Check Approved 2/12/2020 ALYSSA N NARCISO
Issued 5/8/2020 LADBS
CofO in Progress 12/9/2022 RAUL BARAJAS
CofO Issued 1/4/2023 DEROLD HAUFF
Permit Finaled 1/4/2023 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 5/8/2019 GUILLERMO PETRA
BHO/Hillside ordinance Cleared 5/8/2019 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 5/8/2019 GUILLERMO PETRA
Sewer availability Cleared 5/8/2019 GUILLERMO PETRA
Hydrant and Access approval Cleared 12/12/2019 GEORGE SUCHAND
Green Code Cleared 12/13/2019 DAVID MATSON
Encroachment in public way Cleared 12/27/2019 JAMES KHO
Excavation more than 5-ft deep Cleared 1/8/2020 CALOSHA APPROVED
Low Impact Development Cleared 1/10/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 1/10/2020 JOHN LIN
GPI Written Notices Cleared 1/24/2020 ALYSSA N NARCISO
Grading Pre-Inspection Cleared 1/24/2020 ALYSSA N NARCISO
BHO/Hillside ordinance Cleared 2/7/2020 THAN WIN

Contact Information

Contractor Domaen Build Inc; Lic. No.: 1052085-B 915 S MATEO ST SUITE 205      LOS ANGELES, CA 90021
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316
Engineer De, Leon, Cynthia Aguilar; Lic. No.: C31604 8061 SAN MATEO CIR      BUENA PARK, CA 90620

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 6/3/2020 Partial Approval RAUL BARAJAS
Deputy Other (see comments) 6/5/2020 Conditional Approval RAUL BARAJAS
Piling/Pier/Caisson 6/5/2020 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 6/11/2020 Conditional Approval RAUL BARAJAS
Deputy Drilled-In Anchors 7/9/2020 Conditional Approval RAUL BARAJAS
Footing/Foundation/Slab 7/20/2020 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 7/23/2020 Approved RAUL BARAJAS
Deputy Drilled-In Anchors 8/3/2020 Conditional Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 8/3/2020 Partial Approval RAUL BARAJAS
PLUMBING-Rough 8/25/2020 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 12/10/2020 Not Ready for Inspection RAUL BARAJAS
Deputy Drilled-In Anchors 12/15/2020 Conditional Approval RAUL BARAJAS
Footing/Foundation/Slab 12/17/2020 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 12/18/2020 Conditional Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 12/29/2020 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 1/20/2021 Conditional Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 2/12/2021 Corrections Issued RAUL BARAJAS
Footing/Foundation/Slab 2/12/2021 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 2/25/2021 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 2/25/2021 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 3/1/2021 Conditional Approval RAUL BARAJAS
Footing/Foundation/Slab 3/24/2021 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 4/13/2021 No Access for Inspection BRAD BESCOS
Footing/Foundation/Slab 5/3/2021 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 5/7/2021 Conditional Approval RAUL BARAJAS
Deputy Steel/Welding 5/14/2021 Partial Approval JOSEPH MCGARRY
Footing/Foundation/Slab 5/14/2021 Partial Approval JOSEPH MCGARRY
Underground Mechanical 5/27/2021 Not Ready for Inspection RAUL BARAJAS
Underground Mechanical 6/1/2021 Not Ready for Inspection RAUL BARAJAS
Underground Mechanical 6/7/2021 Approved RAUL BARAJAS
Footing/Foundation/Slab 6/10/2021 Approved RAUL BARAJAS
Deputy Steel/Welding 7/9/2021 Conditional Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 7/15/2021 Partial Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 7/15/2021 Partial Approval RAUL BARAJAS
Wood Frame 8/17/2021 Partial Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 8/31/2021 Corrections Issued RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 9/3/2021 Partial Approval RAUL BARAJAS
ELECTRICAL-Rough 10/4/2021 Approved RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 10/4/2021 Conditional Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 10/8/2021 Approved RAUL BARAJAS
PLUMBING-Rough 11/3/2021 Approved RAUL BARAJAS
Interior/Exterior Lathing 12/30/2021 No Access for Inspection RAUL BARAJAS
Interior/Exterior Lathing 1/3/2022 Approved RAUL BARAJAS
BUILDING-Rough-Frame 3/8/2022 Not Ready for Inspection RAUL BARAJAS
Green Building Rough 3/8/2022 Approved RAUL BARAJAS
HVAC-Rough 3/8/2022 Partial Inspection RAUL BARAJAS
Light Gage Steel Frame 3/8/2022 Conditional Approval RAUL BARAJAS
Verify Sprinkler Sign Off 3/8/2022 Approved RAUL BARAJAS
Interior/Exterior Lathing 4/4/2022 Not Ready for Inspection RAUL BARAJAS
Wood Frame 4/4/2022 Approved RAUL BARAJAS
Insulation 4/12/2022 Approved RAUL BARAJAS
Drywall Nailing 5/2/2022 Approved RAUL BARAJAS
Shower Pan 5/18/2022 Approved RAUL BARAJAS
Gas Test 10/5/2022 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Rough 10/5/2022 Not Ready for Inspection RAUL BARAJAS
Service/Power Release 10/5/2022 Corrections Issued RAUL BARAJAS
ELECTRICAL-Final 10/18/2022 Not Ready for Inspection BRIAN SULLIVAN
Gas Test 10/18/2022 Approved BRIAN SULLIVAN
ELECTRICAL-Final 10/21/2022 Partial Inspection RAUL BARAJAS
HVAC-Final 10/21/2022 Partial Inspection RAUL BARAJAS
PLUMBING-Final 10/21/2022 Partial Approval RAUL BARAJAS
HVAC-Final 10/27/2022 Corrections Issued RAUL BARAJAS
ELECTRICAL-Final 10/28/2022 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Final 10/28/2022 Not Ready for Inspection RAUL BARAJAS
Enclosure/Fence 11/1/2022 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Final 11/4/2022 Corrections Issued RAUL BARAJAS
HVAC-Final 11/4/2022 Conditional Approval RAUL BARAJAS
PLUMBING-Final 11/4/2022 Approved RAUL BARAJAS
ELECTRICAL-Final 11/16/2022 Approved RAUL BARAJAS
BUILDING-Rough-Frame 11/29/2022 Approved RAUL BARAJAS
Final 11/29/2022 Corrections Issued RAUL BARAJAS
Green Building Final 11/29/2022 Approved RAUL BARAJAS
HVAC-Final 11/29/2022 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 11/29/2022 SGSOV Not Ready RAUL BARAJAS
Smoke Detectors 11/29/2022 Approved RAUL BARAJAS
Structural Steel Frame 11/29/2022 Approved RAUL BARAJAS
Final 12/2/2022 Not Ready for Inspection RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 12/2/2022 SGSOV Not Ready RAUL BARAJAS
Final 12/9/2022 OK to Issue CofO RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 12/9/2022 SGSOV Approved RAUL BARAJAS