4712 N CONCHITA WAY 91356
Certificate Information: 4712 N CONCHITA WAY 91356
- Application / Permit
- 18014-20000-06114
- Plan Check / Job No.
- B18VN18459
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE ENTIRE SFD EXCEPT 21LF & 22LF OF (E) GARAGE WALLS & FOOTING TO REMAIN AND BUILD 2-STORY SFD W/ ATTACHED GARAGE & BASEMENT (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 4/10/2021
- Issuing Office
- Current Status
- CofO Issued on 8/30/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/25/2018 | APPLICANT |
| Green Plans Picked Up | 11/28/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 11/29/2018 | NILOOFAR MEHRAIN |
| Corrections Issued | 12/13/2018 | NILOOFAR MEHRAIN |
| Quality Review Completed | 12/14/2018 | CHON CHIO KUO |
| Building Plans Picked Up | 12/14/2018 | APPLICANT |
| Applicant returned to address corrections | 4/29/2019 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 5/15/2019 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 6/4/2019 | NILOOFAR MEHRAIN |
| Plan Check Approved | 11/20/2020 | NILOOFAR MEHRAIN |
| Issued | 4/10/2021 | APPLICANT |
| CofO in Progress | 8/1/2023 | SEAN HAUPT |
| Permit Finaled | 8/30/2023 | JOHN JANSON |
| CofO Issued | 8/30/2023 | JOHN JANSON |
| Permit Finaled | 8/30/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 1/10/2019 | CELINA MORENO |
| Permit | Cleared | 1/10/2019 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 2/8/2019 | APEKSHYA BAJRACHARYA |
| BHO/Hillside ordinance | Cleared | 2/8/2019 | APEKSHYA BAJRACHARYA |
| BHO/Hillside ordinance | Cleared | 2/8/2019 | APEKSHYA BAJRACHARYA |
| Eng Process Fee Ord 176,300 | Cleared | 2/8/2019 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 2/8/2019 | APEKSHYA BAJRACHARYA |
| Hydrant and Access approval | Cleared | 2/19/2019 | GILBERT URREA |
| Green Code | Cleared | 3/6/2019 | PARISA ZAHABI |
| Trees in Parkway | Cleared | 4/10/2019 | ADRIAN SANCHEZ |
| Excavation more than 5-ft deep | Cleared | 4/29/2019 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 4/29/2019 | NILOOFAR MEHRAIN |
| Grading Pre-Inspection | Cleared | 4/29/2019 | NILOOFAR MEHRAIN |
| Low Impact Development | Cleared | 7/13/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 7/16/2020 | ADRIAN CASTRO |
| Haul Route | Cleared | 11/20/2020 | NILOOFAR MEHRAIN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/29/2021 | Corrections Issued | DAVID SCANTLIN |
| Pre-Inspection | 5/19/2021 | Partial Inspection | DAVID SANDOVAL |
| Deputy Reinf. Concrete | 7/9/2021 | No Access for Inspection | MICHAEL PELHAM |
| Piling/Pier/Caisson | 9/13/2021 | Partial Approval | DAVID SANDOVAL |
| Deputy Reinf. Concrete | 9/21/2021 | Approved | DAVID SANDOVAL |
| Piling/Pier/Caisson | 9/21/2021 | Approved | DAVID SANDOVAL |
| Deputy Other (see comments) | 9/27/2021 | Partial Approval | DAVID SANDOVAL |
| Piling/Pier/Caisson | 9/27/2021 | Partial Approval | DAVID SANDOVAL |
| Piling/Pier/Caisson | 9/29/2021 | Partial Approval | DAVID SANDOVAL |
| Deputy Reinf. Concrete | 9/30/2021 | Partial Approval | DAVID SANDOVAL |
| Piling/Pier/Caisson | 9/30/2021 | Partial Approval | DAVID SANDOVAL |
| Deputy Reinf. Concrete | 10/1/2021 | Conditional Approval | DAVID SANDOVAL |
| Piling/Pier/Caisson | 10/6/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Deputy Reinf. Concrete | 10/8/2021 | Conditional Approval | DAVID SANDOVAL |
| Piling/Pier/Caisson | 10/8/2021 | Partial Approval | DAVID SANDOVAL |
| Piling/Pier/Caisson | 10/13/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Piling/Pier/Caisson | 10/15/2021 | Partial Approval | DAVID SANDOVAL |
| Deputy Reinf. Concrete | 10/18/2021 | Conditional Approval | DAVID SANDOVAL |
| Piling/Pier/Caisson | 10/18/2021 | Partial Approval | DAVID SANDOVAL |
| Piling/Pier/Caisson | 10/21/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Piling/Pier/Caisson | 10/25/2021 | Partial Approval | DAVID SANDOVAL |
| Deputy Reinf. Concrete | 10/28/2021 | Conditional Approval | DAVID SANDOVAL |
| Piling/Pier/Caisson | 10/28/2021 | Approved | DAVID SANDOVAL |
| Deputy Reinf. Concrete | 12/10/2021 | Conditional Approval | DAVID SANDOVAL |
| Footing/Foundation/Slab | 12/10/2021 | Partial Approval | DAVID SANDOVAL |
| Deputy Reinf. Concrete | 2/24/2022 | Approved | DAVID SANDOVAL |
| Footing/Foundation/Slab | 2/24/2022 | Partial Approval | DAVID SANDOVAL |
| Pre-Inspection | 2/24/2022 | Partial Inspection | JAVIER RAMOS JR |
| Deputy Reinf. Concrete | 3/3/2022 | Approved | DAVID SANDOVAL |
| Deputy Other (see comments) | 5/20/2022 | Approved | DAVID SANDOVAL |
| Deputy Reinf. Concrete | 5/20/2022 | Approved | DAVID SANDOVAL |
| Footing/Foundation/Slab | 5/20/2022 | Partial Approval | DAVID SANDOVAL |
| Deputy Reinf. Concrete | 5/24/2022 | Approved | DAVID SANDOVAL |
| PLUMBING-Rough | 6/21/2022 | Partial Approval | DAVID SANDOVAL |
| Footing/Foundation/Slab | 7/15/2022 | No Access for Inspection | VINCENT HANLEY |
| Pool Piping | 7/15/2022 | No Access for Inspection | VINCENT HANLEY |
| Deputy Reinf. Concrete | 7/26/2022 | Approved | DAVID SANDOVAL |
| Deputy Steel/Welding | 7/26/2022 | Approved | DAVID SANDOVAL |
| Footing/Foundation/Slab | 7/26/2022 | Partial Approval | DAVID SANDOVAL |
| Deputy Reinf. Concrete | 7/27/2022 | Conditional Approval | DAVID SANDOVAL |
| Masonry Wall/Backfill | 8/8/2022 | Partial Approval | DAVID SANDOVAL |
| Excavation/Setback/Form/Re-Bar | 8/16/2022 | Partial Approval | DAVID SANDOVAL |
| Footing/Foundation/Slab | 8/16/2022 | Partial Approval | DAVID SANDOVAL |
| Deputy Reinf. Concrete | 8/19/2022 | Conditional Approval | DAVID SANDOVAL |
| Deputy Steel/Welding | 8/30/2022 | No Access for Inspection | DAVID SANDOVAL |
| Deputy Steel/Welding | 8/31/2022 | Conditional Approval | DAVID SANDOVAL |
| Deputy Other (see comments) | 9/26/2022 | Conditional Approval | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2022 | Partial Approval | DAVID SANDOVAL |
| Footing/Foundation/Slab | 9/27/2022 | Partial Approval | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2022 | Partial Approval | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2022 | Partial Inspection | DAVID SANDOVAL |
| Footing/Foundation/Slab | 11/3/2022 | Partial Approval | DAVID SANDOVAL |
| Deputy Reinf. Concrete | 11/7/2022 | Conditional Approval | DAVID SANDOVAL |
| Deputy Other (see comments) | 11/22/2022 | Conditional Approval | JUSTIN HAWLEY |
| Deputy Reinf. Concrete | 11/22/2022 | Approved | DAVID SANDOVAL |
| Footing/Foundation/Slab | 11/22/2022 | Approved | DAVID SANDOVAL |
| Deputy Reinf. Concrete | 11/23/2022 | Conditional Approval | DAVID SANDOVAL |
| Pre-Inspection | 11/28/2022 | Partial Inspection | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2022 | Partial Approval | DAVID SANDOVAL |
| ELECTRICAL-Rough | 12/27/2022 | Partial Inspection | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2022 | Partial Inspection | DAVID SANDOVAL |
| PLUMBING-Rough | 12/30/2022 | Partial Approval | PETER FOLLING |
| PLUMBING-Rough | 1/18/2023 | Approved | DAVID SANDOVAL |
| Deputy Wood Construction | 1/20/2023 | Conditional Approval | DAVID SANDOVAL |
| HVAC-Rough | 1/20/2023 | Approved | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 1/23/2023 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Rough | 1/23/2023 | Approved | DAVID SANDOVAL |
| Green Building Rough | 1/23/2023 | Not Ready for Inspection | DAVID SANDOVAL |
| Verify Sprinkler Sign Off | 1/23/2023 | Approved | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 2/1/2023 | Approved | JESUS PINEDA |
| Green Building Rough | 2/1/2023 | Approved | JESUS PINEDA |
| Insulation | 2/1/2023 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 2/1/2023 | Partial Approval | JESUS PINEDA |
| Deputy Wood Construction | 2/6/2023 | Approved | DAVID SANDOVAL |
| Deputy Wood Construction | 2/7/2023 | Conditional Approval | DAVID SANDOVAL |
| Shower Pan | 2/8/2023 | Approved | DAVID SANDOVAL |
| Wood Frame | 2/8/2023 | Approved | DAVID SANDOVAL |
| Drywall Nailing | 2/13/2023 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 2/13/2023 | Approved | JESUS PINEDA |
| Special/Order Compliance | 3/10/2023 | Partial Inspection | MORRIS JACKSON |
| Underground Mechanical | 3/10/2023 | Partial Approval | DAVID SANDOVAL |
| ELECTRICAL-Final | 6/27/2023 | Corrections Issued | SEAN HAUPT |
| Final | 6/27/2023 | Corrections Issued | SEAN HAUPT |
| Green Building Final | 6/27/2023 | Not Ready for Inspection | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 6/27/2023 | SGSOV Approved | SEAN HAUPT |
| Smoke Detectors | 6/27/2023 | Approved | SEAN HAUPT |
| Structural Steel Frame | 6/27/2023 | Approved | SEAN HAUPT |
| ELECTRICAL-Final | 6/30/2023 | Approved | SEAN HAUPT |
| Service/Power Release | 6/30/2023 | Approved | SEAN HAUPT |
| Final | 8/1/2023 | OK to Issue CofO | SEAN HAUPT |
| Green Building Final | 8/1/2023 | Approved | SEAN HAUPT |