2672 N NEWELL ST 90039
Certificate Information: 2672 N NEWELL ST 90039
- Application / Permit
- 18014-20000-06092
- Plan Check / Job No.
- B18VN18393
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED (22'-8" X 23'-3") IRREGULAR SHAPED ADDITION TO (E) SFD FOR (N) MASTER BEDRM/BATH/CLOSET & LAUNDRY ROOM.
- Permit Issued
- Issued on 2/21/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/7/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/24/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 10/24/2018 | HAYATO TSUCHIYA |
| Corrections Issued | 10/24/2018 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 12/6/2018 | RAPHAEL ROSAS |
| Plan Check Approved | 4/26/2019 | NIKTA MOUSAVI |
| Issued | 2/21/2020 | LADBS |
| CofO in Progress | 6/17/2022 | SCOTT FINNILA |
| Permit Finaled | 7/7/2022 | DEROLD HAUFF |
| CofO Issued | 7/7/2022 | DEROLD HAUFF |
| Permit Finaled | 7/7/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/10/2018 | KAYLA PEJI |
| Roof/Waste drainage to street | Cleared | 12/10/2018 | KAYLA PEJI |
| Sewer availability | Cleared | 12/10/2018 | KAYLA PEJI |
| ZI | Cleared | 3/13/2019 | TOM HENRY |
Contact Information
| Contractor | D C L A Design Build Inc; Lic. No.: 1060451-B | 45 S ARROYO PKWY STE 214 PASADENA, CA 91105 |
| Engineer | , ; Lic. No.: C58024 | , |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/9/2020 | Approved | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 11/9/2020 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 12/18/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| Insulation | 12/23/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 11/5/2021 | Approved | KATHRYN BUTTERWORTH |
| HVAC-Rough | 11/5/2021 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 11/5/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 12/1/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| Pre-Inspection | 12/1/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 12/7/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Green Building Rough | 12/7/2021 | Approved | KATHRYN BUTTERWORTH |
| MERV13>=Rough | 12/7/2021 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 12/7/2021 | Approved | KATHRYN BUTTERWORTH |
| Insulation | 12/15/2021 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 12/15/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Drywall Nailing | 1/14/2022 | Approved | THOMAS LOGRASSO |
| Shower Pan | 1/14/2022 | Corrections Issued | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 2/3/2022 | Approved | THOMAS LOGRASSO |
| Shower Pan | 2/3/2022 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 5/19/2022 | SGSOV Not Ready | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 5/24/2022 | Approved | KATHRYN BUTTERWORTH |
| Final | 5/24/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| Green Building Final | 5/24/2022 | Approved | KATHRYN BUTTERWORTH |
| MERV13>=Final | 5/24/2022 | Approved | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 5/24/2022 | SGSOV Approved | KATHRYN BUTTERWORTH |
| Smoke Detectors | 5/24/2022 | Approved | KATHRYN BUTTERWORTH |
| Final | 6/2/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| Final | 6/16/2022 | OK to Issue CofO | KATHRYN BUTTERWORTH |