5900 N WINNETKA AVE 91367

Certificate Information: 5900 N WINNETKA AVE 91367

Application / Permit
18014-20000-05850
Plan Check / Job No.
B18VN17714
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE 40 X 52' SINGLE FAMILY DWELLING; ADD 80'-6" x 48' NEW SINGLE FAMILY DWELLING WITH BASEMENT AND ATTACHED GARAGE TO BE ATTACHED TO EXISTING GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 5/3/2019
Issuing Office
Valley
Current Status
CofO Issued on 8/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/12/2018 APPLICANT
Assigned to Plan Check Engineer 10/25/2018 SELLA BENYAMIN
Corrections Issued 10/31/2018 SELLA BENYAMIN
Quality Review Completed 11/1/2018 STEVEN KIM
Building Plans Picked Up 11/7/2018 APPLICANT
Green Plans Picked Up 11/7/2018 APPLICANT
Plan Check Approved 5/1/2019 SELLA BENYAMIN
Issued 5/3/2019 LADBS
CofO in Progress 7/31/2023 JON MCHUGH
Permit Finaled 8/22/2023 JOHN JANSON
CofO Issued 8/22/2023 JOHN JANSON
Permit Finaled 8/22/2023 JOHN JANSON

Permit Application Clearance Information

Green Code Cleared 1/16/2019 DAVID MATSON
Low Impact Development Cleared 1/22/2019 MARTIN FRAGOSO
Address approval Cleared 2/5/2019 APEKSHYA BAJRACHARYA
Eng Process Fee Ord 176,300 Cleared 2/5/2019 APEKSHYA BAJRACHARYA
Roof/Waste drainage to street Cleared 2/5/2019 APEKSHYA BAJRACHARYA
Hydrant and Access approval Cleared 2/7/2019 GILBERT URREA
GPI Written Notices Cleared 5/1/2019 SELLA BENYAMIN
Grading Pre-Inspection Cleared 5/1/2019 SELLA BENYAMIN
Sewer availability Cleared 5/2/2019 JOHN LIN
Hold Cleared 1/6/2020 LOURDES RAMIRO

Contact Information

Contractor Caribe Construction Inc; Lic. No.: 878090-B 521 PARISH PLACE      BURBANK, CA 91506

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/9/2020 Partial Approval STEVEN BACK
Deputy Reinf. Concrete 1/13/2020 Partial Approval STEVEN BACK
PLUMBING-Rough 4/29/2020 Partial Approval STEVEN BACK
Footing/Foundation/Slab 5/14/2020 Partial Approval STEVEN BACK
PLUMBING-Rough 5/14/2020 Partial Approval STEVEN BACK
Footing/Foundation/Slab 6/9/2020 Partial Approval STEVEN BACK
Deputy Steel/Welding 8/4/2020 Partial Approval STEVEN BACK
Deputy Drilled-In Anchors 8/21/2020 Partial Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 8/26/2020 Partial Approval STEVEN BACK
Deputy Wood Construction 8/27/2020 Partial Approval STEVEN BACK
Deputy Steel/Welding 10/19/2020 Partial Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 1/12/2021 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 3/22/2021 Corrections Issued STEVEN BACK
ELECTRICAL-Rough 9/21/2021 Not Ready for Inspection STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 9/21/2021 Corrections Issued STEVEN BACK
PLUMBING-Rough 9/21/2021 Corrections Issued STEVEN BACK
ELECTRICAL-Rough 11/29/2021 Partial Approval SEAN HAUPT
HVAC-Rough 11/29/2021 Partial Approval SEAN HAUPT
PLUMBING-Rough 11/29/2021 Partial Approval SEAN HAUPT
BUILDING-Rough-Frame 12/8/2021 Approved SEAN HAUPT
Deputy Wood Construction 12/8/2021 Conditional Approval JUSTIN HAWLEY
ELECTRICAL-Rough 12/8/2021 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 12/8/2021 Approved SEAN HAUPT
Green Building Rough 12/8/2021 Partial Approval SEAN HAUPT
HVAC-Rough 12/8/2021 Not Ready for Inspection SEAN HAUPT
PLUMBING-Rough 12/8/2021 Approved SEAN HAUPT
Rough-Elec/Plmb/HVAC 12/8/2021 Not Ready for Inspection SEAN HAUPT
Wood Frame 12/8/2021 Partial Approval SEAN HAUPT
Green Building Rough 12/27/2021 Approved STEVEN BACK
HVAC-Rough 12/27/2021 Not Ready for Inspection STEVEN BACK
Interior/Exterior Lathing 12/27/2021 Partial Approval STEVEN BACK
HVAC-Rough 1/4/2022 Approved SEAN HAUPT
Insulation 1/24/2022 Approved SEAN HAUPT
Drywall Nailing 2/9/2022 Partial Approval JUSTIN HAWLEY
Drywall Nailing 2/16/2022 Approved KRISTEN CAUSEY
Shower Pan 2/16/2022 Approved KRISTEN CAUSEY
Drywall Nailing 3/23/2022 Approved MORRIS JACKSON
Interior/Exterior Lathing 3/23/2022 Approved MORRIS JACKSON
Sewer 4/28/2022 Corrections Issued SEAN HAUPT
Sewer 5/2/2022 Corrections Issued SEAN HAUPT
Underground Mechanical 5/4/2022 Approved SEAN HAUPT
ELECTRICAL-Final 6/23/2022 Not Ready for Inspection SEAN HAUPT
Final 6/23/2022 Not Ready for Inspection SEAN HAUPT
Footing/Foundation/Slab 6/23/2022 Not Ready for Inspection SEAN HAUPT
Green Building Final 6/23/2022 Not Ready for Inspection SEAN HAUPT
HVAC-Final 6/23/2022 Not Ready for Inspection SEAN HAUPT
MERV13>=Final 6/23/2022 Not Ready for Inspection SEAN HAUPT
PLUMBING-Final 6/23/2022 Not Ready for Inspection SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 6/23/2022 SGSOV Not Ready SEAN HAUPT
Smoke Detectors 6/23/2022 Not Ready for Inspection SEAN HAUPT
Structural Steel Frame 6/23/2022 Approved SEAN HAUPT
Excavation/Setback/Form/Re-Bar 7/11/2022 Not Ready for Inspection ROBERT GOLD
Masonry Wall/Backfill 7/11/2022 Corrections Issued ROBERT GOLD
Final 10/7/2022 Corrections Issued SEAN HAUPT
Footing/Foundation/Slab 10/7/2022 Not Ready for Inspection SEAN HAUPT
Green Building Final 10/7/2022 Not Ready for Inspection SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 10/7/2022 SGSOV Not Ready SEAN HAUPT
Smoke Detectors 10/7/2022 Not Ready for Inspection SEAN HAUPT
Special/Order Compliance 11/2/2022 Corrections Issued SEAN HAUPT
ELECTRICAL-Final 12/30/2022 Approved SEAN HAUPT
Final 12/30/2022 Corrections Issued SEAN HAUPT
Footing/Foundation/Slab 12/30/2022 Approved SEAN WIRCH
Green Building Final 12/30/2022 Approved SEAN HAUPT
HVAC-Final 12/30/2022 Approved SEAN HAUPT
PLUMBING-Final 12/30/2022 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 12/30/2022 SGSOV Approved SEAN HAUPT
Service/Power Release 12/30/2022 Approved SEAN HAUPT
Smoke Detectors 12/30/2022 Approved SEAN HAUPT
Final 7/31/2023 OK to Issue CofO JON MCHUGH