5900 N WINNETKA AVE 91367
Certificate Information: 5900 N WINNETKA AVE 91367
- Application / Permit
- 18014-20000-05850
- Plan Check / Job No.
- B18VN17714
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE 40 X 52' SINGLE FAMILY DWELLING; ADD 80'-6" x 48' NEW SINGLE FAMILY DWELLING WITH BASEMENT AND ATTACHED GARAGE TO BE ATTACHED TO EXISTING GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 5/3/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/22/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/12/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 10/25/2018 | SELLA BENYAMIN |
| Corrections Issued | 10/31/2018 | SELLA BENYAMIN |
| Quality Review Completed | 11/1/2018 | STEVEN KIM |
| Building Plans Picked Up | 11/7/2018 | APPLICANT |
| Green Plans Picked Up | 11/7/2018 | APPLICANT |
| Plan Check Approved | 5/1/2019 | SELLA BENYAMIN |
| Issued | 5/3/2019 | LADBS |
| CofO in Progress | 7/31/2023 | JON MCHUGH |
| Permit Finaled | 8/22/2023 | JOHN JANSON |
| CofO Issued | 8/22/2023 | JOHN JANSON |
| Permit Finaled | 8/22/2023 | JOHN JANSON |
Permit Application Clearance Information
| Green Code | Cleared | 1/16/2019 | DAVID MATSON |
| Low Impact Development | Cleared | 1/22/2019 | MARTIN FRAGOSO |
| Address approval | Cleared | 2/5/2019 | APEKSHYA BAJRACHARYA |
| Eng Process Fee Ord 176,300 | Cleared | 2/5/2019 | APEKSHYA BAJRACHARYA |
| Roof/Waste drainage to street | Cleared | 2/5/2019 | APEKSHYA BAJRACHARYA |
| Hydrant and Access approval | Cleared | 2/7/2019 | GILBERT URREA |
| GPI Written Notices | Cleared | 5/1/2019 | SELLA BENYAMIN |
| Grading Pre-Inspection | Cleared | 5/1/2019 | SELLA BENYAMIN |
| Sewer availability | Cleared | 5/2/2019 | JOHN LIN |
| Hold | Cleared | 1/6/2020 | LOURDES RAMIRO |
Contact Information
| Contractor | Caribe Construction Inc; Lic. No.: 878090-B | 521 PARISH PLACE BURBANK, CA 91506 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/9/2020 | Partial Approval | STEVEN BACK |
| Deputy Reinf. Concrete | 1/13/2020 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 4/29/2020 | Partial Approval | STEVEN BACK |
| Footing/Foundation/Slab | 5/14/2020 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 5/14/2020 | Partial Approval | STEVEN BACK |
| Footing/Foundation/Slab | 6/9/2020 | Partial Approval | STEVEN BACK |
| Deputy Steel/Welding | 8/4/2020 | Partial Approval | STEVEN BACK |
| Deputy Drilled-In Anchors | 8/21/2020 | Partial Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2020 | Partial Approval | STEVEN BACK |
| Deputy Wood Construction | 8/27/2020 | Partial Approval | STEVEN BACK |
| Deputy Steel/Welding | 10/19/2020 | Partial Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 1/12/2021 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2021 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Rough | 9/21/2021 | Not Ready for Inspection | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2021 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 9/21/2021 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Rough | 11/29/2021 | Partial Approval | SEAN HAUPT |
| HVAC-Rough | 11/29/2021 | Partial Approval | SEAN HAUPT |
| PLUMBING-Rough | 11/29/2021 | Partial Approval | SEAN HAUPT |
| BUILDING-Rough-Frame | 12/8/2021 | Approved | SEAN HAUPT |
| Deputy Wood Construction | 12/8/2021 | Conditional Approval | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 12/8/2021 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2021 | Approved | SEAN HAUPT |
| Green Building Rough | 12/8/2021 | Partial Approval | SEAN HAUPT |
| HVAC-Rough | 12/8/2021 | Not Ready for Inspection | SEAN HAUPT |
| PLUMBING-Rough | 12/8/2021 | Approved | SEAN HAUPT |
| Rough-Elec/Plmb/HVAC | 12/8/2021 | Not Ready for Inspection | SEAN HAUPT |
| Wood Frame | 12/8/2021 | Partial Approval | SEAN HAUPT |
| Green Building Rough | 12/27/2021 | Approved | STEVEN BACK |
| HVAC-Rough | 12/27/2021 | Not Ready for Inspection | STEVEN BACK |
| Interior/Exterior Lathing | 12/27/2021 | Partial Approval | STEVEN BACK |
| HVAC-Rough | 1/4/2022 | Approved | SEAN HAUPT |
| Insulation | 1/24/2022 | Approved | SEAN HAUPT |
| Drywall Nailing | 2/9/2022 | Partial Approval | JUSTIN HAWLEY |
| Drywall Nailing | 2/16/2022 | Approved | KRISTEN CAUSEY |
| Shower Pan | 2/16/2022 | Approved | KRISTEN CAUSEY |
| Drywall Nailing | 3/23/2022 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 3/23/2022 | Approved | MORRIS JACKSON |
| Sewer | 4/28/2022 | Corrections Issued | SEAN HAUPT |
| Sewer | 5/2/2022 | Corrections Issued | SEAN HAUPT |
| Underground Mechanical | 5/4/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Final | 6/23/2022 | Not Ready for Inspection | SEAN HAUPT |
| Final | 6/23/2022 | Not Ready for Inspection | SEAN HAUPT |
| Footing/Foundation/Slab | 6/23/2022 | Not Ready for Inspection | SEAN HAUPT |
| Green Building Final | 6/23/2022 | Not Ready for Inspection | SEAN HAUPT |
| HVAC-Final | 6/23/2022 | Not Ready for Inspection | SEAN HAUPT |
| MERV13>=Final | 6/23/2022 | Not Ready for Inspection | SEAN HAUPT |
| PLUMBING-Final | 6/23/2022 | Not Ready for Inspection | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 6/23/2022 | SGSOV Not Ready | SEAN HAUPT |
| Smoke Detectors | 6/23/2022 | Not Ready for Inspection | SEAN HAUPT |
| Structural Steel Frame | 6/23/2022 | Approved | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 7/11/2022 | Not Ready for Inspection | ROBERT GOLD |
| Masonry Wall/Backfill | 7/11/2022 | Corrections Issued | ROBERT GOLD |
| Final | 10/7/2022 | Corrections Issued | SEAN HAUPT |
| Footing/Foundation/Slab | 10/7/2022 | Not Ready for Inspection | SEAN HAUPT |
| Green Building Final | 10/7/2022 | Not Ready for Inspection | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 10/7/2022 | SGSOV Not Ready | SEAN HAUPT |
| Smoke Detectors | 10/7/2022 | Not Ready for Inspection | SEAN HAUPT |
| Special/Order Compliance | 11/2/2022 | Corrections Issued | SEAN HAUPT |
| ELECTRICAL-Final | 12/30/2022 | Approved | SEAN HAUPT |
| Final | 12/30/2022 | Corrections Issued | SEAN HAUPT |
| Footing/Foundation/Slab | 12/30/2022 | Approved | SEAN WIRCH |
| Green Building Final | 12/30/2022 | Approved | SEAN HAUPT |
| HVAC-Final | 12/30/2022 | Approved | SEAN HAUPT |
| PLUMBING-Final | 12/30/2022 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 12/30/2022 | SGSOV Approved | SEAN HAUPT |
| Service/Power Release | 12/30/2022 | Approved | SEAN HAUPT |
| Smoke Detectors | 12/30/2022 | Approved | SEAN HAUPT |
| Final | 7/31/2023 | OK to Issue CofO | JON MCHUGH |