5234 N SALE AVE 91364
Certificate Information: 5234 N SALE AVE 91364
- Application / Permit
- 18014-20000-05814
- Plan Check / Job No.
- B18VN17578
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel and reframe roof of 2 bedrooms for high ceiling, add <irregular shape> 32'9" x 45'9" to ground floor for (new den, 2 bedrooms expansion, 2 relocated bathrooms, stairwell, hallway) and 45'9" x 32'9" new 2nd floor game room. See comment
- Permit Issued
- Issued on 6/13/2019
- Issuing Office
- Valley
- Current Status
- Issued on 1/31/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/11/2018 | APPLICANT |
| Green Plans Picked Up | 10/24/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 10/25/2018 | ALDOUS CHIC |
| Corrections Issued | 10/29/2018 | ALDOUS CHIC |
| Quality Review Completed | 10/29/2018 | OMID HEDAYAT |
| Building Plans Picked Up | 10/31/2018 | APPLICANT |
| Applicant returned to address corrections | 3/28/2019 | ALDOUS CHIC |
| Applicant returned to address corrections | 4/4/2019 | ALDOUS CHIC |
| Applicant returned to address corrections | 4/25/2019 | ALDOUS CHIC |
| Applicant returned to address corrections | 6/4/2019 | ALDOUS CHIC |
| Plan Check Approved | 6/13/2019 | ALDOUS CHIC |
| Issued | 6/13/2019 | LADBS |
| CofO in Progress | 8/19/2024 | JOHN HAYES |
| CofO in Progress | 11/25/2024 | JOHN JANSON |
| No Progress | 1/31/2025 | SEAN WIRCH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/5/2017 | ALDOUS CHIC |
| GPI Written Notices | Cleared | 10/27/2018 | ALDOUS CHIC |
| BHO/Hillside ordinance | Cleared | 11/5/2018 | KAREN LE |
| BHO/Hillside ordinance | Cleared | 11/5/2018 | KAREN LE |
| BHO/Hillside ordinance | Cleared | 11/5/2018 | KAREN LE |
| Eng Process Fee Ord 176,300 | Cleared | 11/5/2018 | KAREN LE |
| Highway dedication | Cleared | 11/5/2018 | KAREN LE |
| Hydrant and Access approval | Cleared | 11/5/2018 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 11/5/2018 | MATTHEW JIMENEZ |
| Roof/Waste drainage to street | Cleared | 11/5/2018 | KAREN LE |
| Green Code | Cleared | 4/4/2019 | DAVID MATSON |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Graig, Erick Standley; Lic. No.: C87675 | , |
| Engineer | Mohan, B. Upasani; Lic. No.: GE2301 | , |
| Geologist | Kevin, B. Young; Lic. No.: EG2253 | , |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 10/7/2019 | Partial Approval | SEAN WIRCH |
| Footing/Foundation/Slab | 10/16/2019 | Corrections Issued | JOHN KIDWELL |
| Footing/Foundation/Slab | 10/22/2019 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 10/23/2019 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 11/21/2019 | Not Ready for Inspection | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2019 | Partial Approval | SEAN WIRCH |
| MERV13>=Rough | 11/21/2019 | No Access for Inspection | SEAN WIRCH |
| Verify Sprinkler Sign Off | 11/21/2019 | Not Ready for Inspection | SEAN WIRCH |
| BUILDING-Rough-Frame | 12/17/2019 | No Access for Inspection | SEAN WIRCH |
| Green Building Rough | 12/17/2019 | No Access for Inspection | SEAN WIRCH |
| MERV13>=Rough | 12/17/2019 | No Access for Inspection | SEAN WIRCH |
| Verify Sprinkler Sign Off | 12/17/2019 | No Access for Inspection | SEAN WIRCH |
| Wood Frame | 12/17/2019 | No Access for Inspection | SEAN WIRCH |
| BUILDING-Rough-Frame | 12/23/2019 | Not Ready for Inspection | SEAN WIRCH |
| Green Building Rough | 12/23/2019 | Not Ready for Inspection | SEAN WIRCH |
| MERV13>=Rough | 12/23/2019 | Not Ready for Inspection | SEAN WIRCH |
| Verify Sprinkler Sign Off | 12/23/2019 | Not Ready for Inspection | SEAN WIRCH |
| BUILDING-Rough-Frame | 1/8/2020 | Not Ready for Inspection | JOHN JANSON |
| Green Building Rough | 1/8/2020 | Not Ready for Inspection | JOHN JANSON |
| Insulation | 1/8/2020 | Not Ready for Inspection | JOHN JANSON |
| MERV13>=Rough | 1/8/2020 | Not Ready for Inspection | JOHN JANSON |
| Verify Sprinkler Sign Off | 1/8/2020 | Not Ready for Inspection | JOHN JANSON |
| BUILDING-Rough-Frame | 2/7/2020 | Not Ready for Inspection | DAVID SCANTLIN |
| Green Building Rough | 2/7/2020 | Not Ready for Inspection | DAVID SCANTLIN |
| HVAC-Rough | 2/7/2020 | Partial Approval | DAVID SCANTLIN |
| MERV13>=Rough | 2/7/2020 | Not Ready for Inspection | DAVID SCANTLIN |
| PLUMBING-Rough | 2/7/2020 | Partial Approval | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 2/7/2020 | Not Ready for Inspection | DAVID SCANTLIN |
| ELECTRICAL-Rough | 3/2/2020 | Not Ready for Inspection | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2020 | Partial Approval | PETER FOLLING |
| Green Building Rough | 3/2/2020 | Not Ready for Inspection | PETER FOLLING |
| Insulation | 3/2/2020 | Not Ready for Inspection | PETER FOLLING |
| MERV13>=Rough | 3/2/2020 | Not Ready for Inspection | PETER FOLLING |
| Verify Sprinkler Sign Off | 3/2/2020 | Not Ready for Inspection | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 3/11/2020 | Approved | PETER FOLLING |
| Green Building Rough | 3/11/2020 | Approved | PETER FOLLING |
| HVAC-Rough | 3/11/2020 | Not Ready for Inspection | PETER FOLLING |
| PLUMBING-Rough | 3/11/2020 | Not Ready for Inspection | PETER FOLLING |
| ELECTRICAL-Rough | 3/23/2020 | Approved | PETER FOLLING |
| HVAC-Rough | 4/20/2020 | Corrections Issued | DAVID SANDOVAL |
| PLUMBING-Rough | 4/20/2020 | Approved | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 4/27/2020 | Partial Approval | RONALD COWAN |
| HVAC-Rough | 4/27/2020 | Approved | RONALD COWAN |
| Insulation | 4/27/2020 | Partial Approval | RONALD COWAN |
| Verify Sprinkler Sign Off | 4/27/2020 | Approved | RONALD COWAN |
| Drywall Nailing | 5/8/2020 | Approved | RONALD COWAN |
| Interior/Exterior Lathing | 5/8/2020 | Approved | RONALD COWAN |
| Interior/Exterior Lathing | 6/10/2020 | Approved | RONALD COWAN |
| Shower Pan | 6/10/2020 | Approved | RONALD COWAN |
| ELECTRICAL-Final | 7/28/2020 | Not Ready for Inspection | PAUL CHOPP |
| Service/Power Release | 7/28/2020 | Not Ready for Inspection | PAUL CHOPP |
| ELECTRICAL-Final | 8/28/2020 | Corrections Issued | DAVID SANDOVAL |
| Service/Power Release | 8/28/2020 | Not Ready for Inspection | DAVID SANDOVAL |
| ELECTRICAL-Final | 9/2/2020 | Not Ready for Inspection | RONALD COWAN |
| Service/Power Release | 9/2/2020 | Approved | RONALD COWAN |
| PLUMBING-Final | 10/30/2020 | Not Ready for Inspection | TROY SANDERS |
| PLUMBING-Rough | 10/30/2020 | Partial Approval | TROY SANDERS |
| Underground Mechanical | 10/30/2020 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 11/25/2020 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Final | 11/25/2020 | Not Ready for Inspection | STEVEN BACK |
| Gas Test | 11/25/2020 | Approved | STEVEN BACK |
| HVAC-Final | 11/25/2020 | Corrections Issued | STEVEN BACK |
| PLUMBING-Final | 11/25/2020 | Approved | STEVEN BACK |
| Smoke Detectors | 11/25/2020 | Approved | STEVEN BACK |
| ELECTRICAL-Final | 1/26/2021 | Not Ready for Inspection | PAUL CHOPP |
| HVAC-Final | 1/26/2021 | Partial Approval | PAUL CHOPP |
| HVAC-Final | 3/24/2021 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Final | 4/27/2021 | Approved | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 8/2/2024 | Approved | JOHN HAYES |
| Final | 8/2/2024 | OK to Issue CofO | JOHN HAYES |
| Green Building Final | 8/2/2024 | Approved | JOHN HAYES |
| MERV13>=Final | 8/2/2024 | Approved | JOHN HAYES |
| MERV13>=Rough | 8/2/2024 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 8/2/2024 | SGSOV Approved | JOHN HAYES |
| Special/Order Compliance | 12/2/2024 | Corrections Issued | JOHN HAYES |
| Special/Order Compliance | 12/5/2024 | Corrections Issued | JOHN HAYES |