4447 W RUSSELL AVE 90027

Certificate Information: 4447 W RUSSELL AVE 90027

Application / Permit
18014-20000-05694
Plan Check / Job No.
B18VN17180
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 2ND FLOOR & MAJOR REMODEL OF 1ST FLOOR TO (E) 1-STORY SFD; ADD (N) 1-CAR CARPORT; REMOVE PORTION AT REAR (IRR 14' X 5') & SIDE (8'-6" X 2') OF SFD (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 1/17/2020
Issuing Office
Valley
Current Status
CofO Issued on 7/28/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/4/2018 APPLICANT
Green Plans Picked Up 10/30/2018 APPLICANT
Assigned to Plan Check Engineer 11/1/2018 JOSE MENDOZA
Corrections Issued 11/9/2018 JOSE MENDOZA
Quality Review Completed 11/16/2018 STEVEN KIM
Building Plans Picked Up 11/20/2018 APPLICANT
Plan Check Approved 1/13/2020 NILOOFAR MEHRAIN
Issued 1/17/2020 LADBS
CofO in Progress 7/19/2021 JOSEPH MCGARRY
CofO Issued 7/28/2021 DEROLD HAUFF
Permit Finaled 7/28/2021 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 1/29/2019 DAVID MATSON
Sewer availability Cleared 2/5/2019 APEKSHYA BAJRACHARYA
Low Impact Development Cleared 2/6/2019 MARTIN FRAGOSO
Eng Process Fee Ord 176,300 Cleared 2/7/2019 CHRISTINE REUSCH
Permit Cleared 2/7/2019 CHRISTINE REUSCH
Roof/Waste drainage to street Cleared 2/7/2019 CHRISTINE REUSCH
Grading Pre-Inspection Cleared 11/21/2019 TIMOTHY POWELL
Trees in Parkway Cleared 12/24/2019 STEPHEN DUPREY
"D" conditions Cleared 1/9/2020 DAISY BENICIA
GPI Written Notices Cleared 1/13/2020 JOSE MENDOZA
Miscellaneous Cleared 1/16/2020 DAISY BENICIA
Specific Plan Cleared 1/16/2020 DAISY BENICIA
ZI Cleared 1/16/2020 DAISY BENICIA

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/10/2020 Partial Approval JOSEPH MCGARRY
Pre-Inspection 4/30/2020 Approved JOSEPH MCGARRY
Deputy Drilled-In Anchors 5/13/2020 Partial Approval JOSEPH MCGARRY
Deputy Reinf. Concrete 5/20/2020 Partial Approval JOSEPH MCGARRY
Footing/Foundation/Slab 5/20/2020 Corrections Issued JOSEPH MCGARRY
Footing/Foundation/Slab 5/28/2020 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 6/5/2020 Partial Approval JOSEPH MCGARRY
Gas Test 6/5/2020 Partial Inspection JOSEPH MCGARRY
PLUMBING-Rough 6/5/2020 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 6/9/2020 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 6/9/2020 Not Ready for Inspection CHRIS CHRISTENSEN
Wood Frame 6/15/2020 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 6/30/2020 Corrections Issued JOSEPH MCGARRY
ELECTRICAL-Rough 7/20/2020 Approved ARTHUR SARGSYAN
Sewer 7/20/2020 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 7/29/2020 Approved ARTHUR SARGSYAN
HVAC-Rough 7/29/2020 Approved ARTHUR SARGSYAN
PLUMBING-Rough 7/29/2020 Approved ARTHUR SARGSYAN
Wood Frame 7/29/2020 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 7/30/2020 Approved JOSEPH MCGARRY
HVAC-Rough 7/30/2020 Approved JOSEPH MCGARRY
PLUMBING-Rough 7/30/2020 Approved JOSEPH MCGARRY
Wood Frame 7/30/2020 Partial Approval JOSEPH MCGARRY
Insulation 8/18/2020 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 8/18/2020 Approved CHRIS CHRISTENSEN
Shower Pan 8/18/2020 Approved CHRIS CHRISTENSEN
Verify Sprinkler Sign Off 8/18/2020 Approved CHRIS CHRISTENSEN
Wood Frame 8/18/2020 Approved CHRIS CHRISTENSEN
Drywall Nailing 8/24/2020 Approved THOMAS LOGRASSO
Green Building Rough 8/24/2020 Approved THOMAS LOGRASSO
ELECTRICAL-Final 1/19/2021 Approved JOSEPH MCGARRY
HVAC-Final 1/19/2021 Approved JOSEPH MCGARRY
PLUMBING-Final 1/19/2021 Approved JOSEPH MCGARRY
Service/Power Release 1/19/2021 Approved JOSEPH MCGARRY
Gas Test 1/28/2021 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 7/9/2021 Approved JOSEPH MCGARRY
Final 7/9/2021 OK to Issue CofO JOSEPH MCGARRY
Green Building Final 7/9/2021 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 7/9/2021 SGSOV Approved JOSEPH MCGARRY
Smoke Detectors 7/9/2021 Approved JOSEPH MCGARRY