11250 N MONOGRAM AVE 91344

Certificate Information: 11250 N MONOGRAM AVE 91344

Application / Permit
18014-20000-05638
Plan Check / Job No.
B18VN16995
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (18'x20') garage to accessory dwelling unit and add (18'x27') for new 2nd floor for accessory dwelling unit per AB 494 and SB 229
Permit Issued
Issued on 12/3/2019
Issuing Office
Valley
Current Status
CofO Issued on 3/31/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/2/2018 APPLICANT
Green Plans Picked Up 10/31/2018 APPLICANT
Assigned to Plan Check Engineer 11/1/2018 ALYSSA N NARCISO
Corrections Issued 11/9/2018 ALYSSA N NARCISO
Quality Review Completed 11/9/2018 OMID HEDAYAT
Building Plans Picked Up 11/21/2018 APPLICANT
Applicant returned to address corrections 10/3/2019 ALYSSA N NARCISO
Applicant returned to address corrections 11/12/2019 ALYSSA N NARCISO
Plan Check Approved 12/3/2019 ALYSSA N NARCISO
Issued 12/3/2019 LADBS
CofO in Progress 3/31/2022 MICHAEL TEMPLE
Permit Finaled 3/31/2022 MICHAEL SMITH
CofO Issued 3/31/2022 MICHAEL SMITH
Permit Finaled 3/31/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 3/7/2019 APEKSHYA BAJRACHARYA
Eng Process Fee Ord 176,300 Cleared 3/7/2019 APEKSHYA BAJRACHARYA
Sewer availability Cleared 3/7/2019 APEKSHYA BAJRACHARYA
Construction near power lines Cleared 8/17/2019 RIDWAN HARDY
Green Code Cleared 9/3/2019 PARISA ZAHABI
Hydrant and Access approval Cleared 10/22/2019 GEORGE SUCHAND
Low Impact Development Cleared 10/28/2019 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 10/29/2019 LEE GUILBEAUX
Grading Pre-Inspection Cleared 11/8/2019 BARTON HOLMES
GPI Written Notices Cleared 11/12/2019 ALYSSA N NARCISO

Contact Information

Contractor Owner-Builder       ,
Engineer Carrillo,, Jesus Eduardo; Lic. No.: C77737 8207 BROOKGREEN RD      DOWNEY, CA 90240

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/24/2020 Not Ready for Inspection MARK JOHNSON
Pre-Inspection 2/24/2020 Approved MARK JOHNSON
Footing/Foundation/Slab 3/2/2020 Not Ready for Inspection MARK JOHNSON
Footing/Foundation/Slab 3/6/2020 Partial Approval MARK JOHNSON
Footing/Foundation/Slab 4/3/2020 Partial Approval MARK JOHNSON
PLUMBING-Rough 4/8/2020 Partial Approval MARK JOHNSON
Deputy Drilled-In Anchors 4/21/2020 Partial Approval MARK JOHNSON
Footing/Foundation/Slab 4/22/2020 Approved MARK JOHNSON
Special/Order Compliance 5/13/2020 Approved GREGG CUMMINGS
Wood Frame 5/13/2020 Corrections Issued MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 5/22/2020 Partial Approval CHARLES POWELL
ELECTRICAL-Rough 6/26/2020 Not Ready for Inspection WILLIAM KUEHN
Floor/Roof Diaphrgm/Shear Wall 6/26/2020 Partial Inspection WILLIAM KUEHN
HVAC-Rough 6/26/2020 Not Ready for Inspection WILLIAM KUEHN
PLUMBING-Rough 6/26/2020 Not Ready for Inspection WILLIAM KUEHN
ELECTRICAL-Rough 7/1/2020 Approved MARK JOHNSON
HVAC-Rough 7/1/2020 Approved MARK JOHNSON
PLUMBING-Rough 7/1/2020 Approved MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 8/3/2020 Not Ready for Inspection MARK JOHNSON
BUILDING-Rough-Frame 9/9/2020 Approved MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 9/9/2020 Approved MARK JOHNSON
Green Building Rough 9/9/2020 Approved MARK JOHNSON
MERV13>=Rough 9/9/2020 Approved MARK JOHNSON
Wood Frame 9/9/2020 Approved MARK JOHNSON
Insulation 9/15/2020 Approved MARK JOHNSON
Drywall Nailing 9/21/2020 Approved MARK JOHNSON
Interior/Exterior Lathing 9/21/2020 Approved MARK JOHNSON
Shower Pan 9/28/2020 Approved MARK JOHNSON
Shower Pan 9/30/2020 Approved MARK JOHNSON
Final 11/18/2020 Corrections Issued MARK JOHNSON
Green Building Final 11/18/2020 Not Ready for Inspection MARK JOHNSON
MERV13>=Final 11/18/2020 Approved MARK JOHNSON
SGSOV-Seismic Gas S/O Valve 11/18/2020 SGSOV Not Ready MARK JOHNSON
Smoke Detectors 11/18/2020 Approved MARK JOHNSON
Final 10/6/2021 Not Ready for Inspection MARK JOHNSON
Green Building Final 10/6/2021 Approved MARK JOHNSON
SGSOV-Seismic Gas S/O Valve 10/6/2021 SGSOV Approved MARK JOHNSON
Final 11/17/2021 Conditional Approval MICHAEL TEMPLE
Final 3/31/2022 OK to Issue CofO MICHAEL TEMPLE