9291 W FLICKER WAY 90069
Certificate Information: 9291 W FLICKER WAY 90069
- Application / Permit
- 18014-20000-05546
- Plan Check / Job No.
- B18VN16755
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 28'6" X 48' IRREGULAR SHAPED 2ND FLOOR ADDITION TO (E) SFD TO CREATE NEW MASTER BEDROOM , MASTER BATHROOM , W.I.C, STAIRWAY AND ELEVATOR , INTERIOR REMODEL TO (E) GARAGE TO ADD A STAIRCASE , INTERIOR REMODEL TO 1ST FLOOR TO KITCHEN , FAMILY ROOM , DINING ROOM , (2) BATHROOM , (2) BEDROOMS , REMOVE ONE BEDROOM , RE-MOVE EXISTING ROOF, FIRE SPRINKLERS REQUIRED NFPA -13D THROUGHOUT . ALL WORK PER ENGINEERING - SEE COMMENTS
- Permit Issued
- Issued on 1/10/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/17/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/27/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 10/11/2018 | RARES BODEA |
| Green Plans Picked Up | 10/11/2018 | APPLICANT |
| Corrections Issued | 10/14/2018 | RARES BODEA |
| Quality Review Completed | 10/16/2018 | OMID HEDAYAT |
| Building Plans Picked Up | 10/17/2018 | APPLICANT |
| Applicant returned to address corrections | 12/13/2019 | RARES BODEA |
| Plan Check Approved | 12/23/2019 | RARES BODEA |
| Issued | 1/10/2020 | LADBS |
| CofO in Progress | 10/13/2020 | RAUL BARAJAS |
| Permit Finaled | 11/17/2020 | DEROLD HAUFF |
| CofO Issued | 11/17/2020 | DEROLD HAUFF |
| Permit Finaled | 11/17/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 10/31/2018 | MARKOS PEREZ-BRAN |
| BHO/Hillside ordinance | Cleared | 10/31/2018 | MARKOS PEREZ-BRAN |
| Green Code | Cleared | 10/31/2018 | MICHAEL AYERS |
| Sewer availability | Cleared | 10/31/2018 | MARKOS PEREZ-BRAN |
| Distance to fire station | Cleared | 11/1/2019 | GEORGE SUCHAND |
| Eng Process Fee Ord 176,300 | Cleared | 11/1/2019 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 11/1/2019 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 12/12/2019 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 12/12/2019 | MARKOS PEREZ-BRAN |
| GPI Written Notices | Cleared | 12/13/2019 | RARES BODEA |
| Grading Pre-Inspection | Cleared | 12/13/2019 | RARES BODEA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/17/2020 | Partial Inspection | RICHARD STEINBACH |
| Footing/Foundation/Slab | 1/30/2020 | Conditional Approval | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2020 | Conditional Approval | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2020 | Corrections Issued | ROBERT CORNELL |
| ELECTRICAL-Rough | 4/22/2020 | Approved | RAUL BARAJAS |
| PLUMBING-Rough | 4/22/2020 | Approved | RAUL BARAJAS |
| HVAC-Rough | 4/28/2020 | Partial Approval | RAUL BARAJAS |
| Wood Frame | 4/28/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Shower Pan | 5/5/2020 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 5/7/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Green Building Rough | 5/7/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 5/7/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Interior/Exterior Lathing | 5/8/2020 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 5/12/2020 | Conditional Approval | RAUL BARAJAS |
| Green Building Rough | 5/12/2020 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 5/12/2020 | Approved | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 5/12/2020 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 5/14/2020 | Approved | RAUL BARAJAS |
| Drywall Nailing | 5/26/2020 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 9/11/2020 | Approved | RAUL BARAJAS |
| ELECTRICAL-Final | 9/11/2020 | Approved | RAUL BARAJAS |
| Final | 9/11/2020 | Corrections Issued | RAUL BARAJAS |
| Footing/Foundation/Slab | 9/11/2020 | Approved | RAUL BARAJAS |
| Green Building Final | 9/11/2020 | Not Ready for Inspection | RAUL BARAJAS |
| HVAC-Final | 9/11/2020 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Final | 9/11/2020 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 9/11/2020 | SGSOV Approved | RAUL BARAJAS |
| Service/Power Release | 9/11/2020 | Approved | RAUL BARAJAS |
| Smoke Detectors | 9/11/2020 | Approved | RAUL BARAJAS |
| ELECTRICAL-Final | 10/13/2020 | Approved | RAUL BARAJAS |
| Final | 10/13/2020 | OK to Issue CofO | RAUL BARAJAS |
| Green Building Final | 10/13/2020 | Approved | RAUL BARAJAS |
| HVAC-Final | 10/13/2020 | Approved | RAUL BARAJAS |
| PLUMBING-Final | 10/13/2020 | Approved | RAUL BARAJAS |
| Underground Mechanical | 10/22/2020 | No Access for Inspection | RAUL BARAJAS |
| HVAC-Final | 11/9/2020 | Approved | RAUL BARAJAS |
| PLUMBING-Final | 11/9/2020 | Approved | RAUL BARAJAS |