2558 N HUTTON DR 90210
Certificate Information: 2558 N HUTTON DR 90210
- Application / Permit
- 18014-20000-05466
- Plan Check / Job No.
- B18VN16511
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED (7'-5" x 30'-3") & (3'-6" x 7') ADDITION & REMODEL TO (E) SFD PER ENGINEERING
- Permit Issued
- Issued on 12/4/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/19/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/25/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 9/25/2018 | RAPHAEL ROSAS |
| Corrections Issued | 9/25/2018 | RAPHAEL ROSAS |
| Building Plans Picked Up | 10/4/2018 | APPLICANT |
| Plan Check Approved | 11/29/2018 | RAPHAEL ROSAS |
| Issued | 12/4/2018 | LADBS |
| CofO in Progress | 5/28/2025 | SEAN HAUPT |
| Permit Finaled | 5/19/2026 | RICHARD STEINBACH |
| CofO Issued | 5/19/2026 | RICHARD STEINBACH |
| Permit Finaled | 5/19/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/28/2018 | LEE GUILBEAUX |
| Grading Pre-Inspection | Cleared | 11/29/2018 | RAPHAEL ROSAS |
| Roof/Waste drainage to street | Cleared | 11/29/2018 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 11/29/2018 | CHRISTINE REUSCH |
Contact Information
| Contractor | Concept Renovations Inc; Lic. No.: 1016942-B | 4335 VAN NUYS BLVD UNIT 255 SHERMAN OAKS, CA 91403 |
| Engineer | Burnazyan, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/10/2019 | Partial Approval | CARLOS MATAMOROS |
| Special/Order Compliance | 6/22/2019 | Partial Inspection | CHRISTOPHER WILSON |
| Special/Order Compliance | 6/29/2019 | Partial Inspection | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/10/2020 | Partial Approval | ANTHONY MCDOWALL |
| Green Building Rough | 1/10/2020 | Not Ready for Inspection | ANTHONY MCDOWALL |
| PLUMBING-Rough | 6/18/2020 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Underground Mechanical | 6/18/2020 | Corrections Issued | ANTHONY MCDOWALL |
| BUILDING-Rough-Frame | 7/7/2020 | Partial Approval | ANTHONY MCDOWALL |
| Underground Mechanical | 7/7/2020 | Partial Approval | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2020 | Corrections Issued | ANTHONY MCDOWALL |
| Green Building Rough | 11/9/2020 | Not Ready for Inspection | ANTHONY MCDOWALL |
| HVAC-Rough | 11/13/2020 | Not Ready for Inspection | ANTHONY MCDOWALL |
| PLUMBING-Rough | 11/13/2020 | Approved | ANTHONY MCDOWALL |
| ELECTRICAL-Rough | 11/19/2020 | Approved | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2020 | Partial Approval | ANTHONY MCDOWALL |
| Green Building Rough | 11/19/2020 | Not Ready for Inspection | ANTHONY MCDOWALL |
| HVAC-Rough | 11/19/2020 | Partial Approval | ANTHONY MCDOWALL |
| BUILDING-Rough-Frame | 12/3/2020 | Corrections Issued | ANTHONY MCDOWALL |
| Green Building Rough | 12/3/2020 | Approved | ANTHONY MCDOWALL |
| Shower Pan | 12/3/2020 | Approved | ANTHONY MCDOWALL |
| Wood Frame | 12/3/2020 | Not Ready for Inspection | ANTHONY MCDOWALL |
| BUILDING-Rough-Frame | 12/15/2020 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Interior/Exterior Lathing | 12/15/2020 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Insulation | 12/18/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| Insulation | 12/23/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| Insulation | 12/24/2020 | Approved | CARLOS MATAMOROS |
| Wood Frame | 12/24/2020 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 1/14/2021 | Corrections Issued | ANTHONY MCDOWALL |
| Drywall Nailing | 1/19/2021 | Approved | ANTHONY MCDOWALL |
| Pre-Inspection | 3/16/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Gas Test | 5/31/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| Gas Test | 6/5/2023 | Approved | STEPHANIE SWANSON |
| PLUMBING-Final | 6/7/2023 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Final | 6/27/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| HVAC-Final | 6/27/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Interior/Exterior Lathing | 6/27/2023 | Partial Approval | BRENDAN LOONEY |
| PLUMBING-Final | 6/27/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Final | 3/21/2025 | Not Ready for Inspection | DANIEL VERA |
| Footing/Foundation/Slab | 3/21/2025 | Not Ready for Inspection | DANIEL VERA |
| Green Building Final | 3/21/2025 | Not Ready for Inspection | DANIEL VERA |
| SGSOV-Seismic Gas S/O Valve | 3/21/2025 | SGSOV Not Ready | DANIEL VERA |
| Smoke Detectors | 3/21/2025 | Not Ready for Inspection | DANIEL VERA |
| Final | 4/14/2025 | Corrections Issued | SEAN HAUPT |
| Footing/Foundation/Slab | 4/14/2025 | Approved | SEAN HAUPT |
| Green Building Final | 4/14/2025 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 4/14/2025 | SGSOV Approved | SEAN HAUPT |
| Smoke Detectors | 4/14/2025 | Not Ready for Inspection | SEAN HAUPT |
| Service/Power Release | 4/15/2025 | Approved | SEAN HAUPT |
| Final | 5/5/2025 | Corrections Issued | SEAN HAUPT |
| Smoke Detectors | 5/5/2025 | Approved | SEAN HAUPT |
| Final | 5/27/2025 | OK to Issue CofO | SEAN HAUPT |