2558 N HUTTON DR 90210

Certificate Information: 2558 N HUTTON DR 90210

Application / Permit
18014-20000-05466
Plan Check / Job No.
B18VN16511
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED (7'-5" x 30'-3") & (3'-6" x 7') ADDITION & REMODEL TO (E) SFD PER ENGINEERING
Permit Issued
Issued on 12/4/2018
Issuing Office
Valley
Current Status
CofO Issued on 5/19/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/25/2018 APPLICANT
Assigned to Plan Check Engineer 9/25/2018 RAPHAEL ROSAS
Corrections Issued 9/25/2018 RAPHAEL ROSAS
Building Plans Picked Up 10/4/2018 APPLICANT
Plan Check Approved 11/29/2018 RAPHAEL ROSAS
Issued 12/4/2018 LADBS
CofO in Progress 5/28/2025 SEAN HAUPT
Permit Finaled 5/19/2026 RICHARD STEINBACH
CofO Issued 5/19/2026 RICHARD STEINBACH
Permit Finaled 5/19/2026 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/28/2018 LEE GUILBEAUX
Grading Pre-Inspection Cleared 11/29/2018 RAPHAEL ROSAS
Roof/Waste drainage to street Cleared 11/29/2018 MARKOS PEREZ-BRAN
Sewer availability Cleared 11/29/2018 CHRISTINE REUSCH

Contact Information

Contractor Concept Renovations Inc; Lic. No.: 1016942-B 4335 VAN NUYS BLVD UNIT 255      SHERMAN OAKS, CA 91403
Engineer Burnazyan, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/10/2019 Partial Approval CARLOS MATAMOROS
Special/Order Compliance 6/22/2019 Partial Inspection CHRISTOPHER WILSON
Special/Order Compliance 6/29/2019 Partial Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 1/10/2020 Partial Approval ANTHONY MCDOWALL
Green Building Rough 1/10/2020 Not Ready for Inspection ANTHONY MCDOWALL
PLUMBING-Rough 6/18/2020 Not Ready for Inspection ANTHONY MCDOWALL
Underground Mechanical 6/18/2020 Corrections Issued ANTHONY MCDOWALL
BUILDING-Rough-Frame 7/7/2020 Partial Approval ANTHONY MCDOWALL
Underground Mechanical 7/7/2020 Partial Approval ANTHONY MCDOWALL
Floor/Roof Diaphrgm/Shear Wall 11/9/2020 Corrections Issued ANTHONY MCDOWALL
Green Building Rough 11/9/2020 Not Ready for Inspection ANTHONY MCDOWALL
HVAC-Rough 11/13/2020 Not Ready for Inspection ANTHONY MCDOWALL
PLUMBING-Rough 11/13/2020 Approved ANTHONY MCDOWALL
ELECTRICAL-Rough 11/19/2020 Approved ANTHONY MCDOWALL
Floor/Roof Diaphrgm/Shear Wall 11/19/2020 Partial Approval ANTHONY MCDOWALL
Green Building Rough 11/19/2020 Not Ready for Inspection ANTHONY MCDOWALL
HVAC-Rough 11/19/2020 Partial Approval ANTHONY MCDOWALL
BUILDING-Rough-Frame 12/3/2020 Corrections Issued ANTHONY MCDOWALL
Green Building Rough 12/3/2020 Approved ANTHONY MCDOWALL
Shower Pan 12/3/2020 Approved ANTHONY MCDOWALL
Wood Frame 12/3/2020 Not Ready for Inspection ANTHONY MCDOWALL
BUILDING-Rough-Frame 12/15/2020 Approved GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 12/15/2020 Approved GERMAN RODRIGUEZ MENDOZA
Insulation 12/18/2020 Not Ready for Inspection CARLOS MATAMOROS
Insulation 12/23/2020 Not Ready for Inspection CARLOS MATAMOROS
Insulation 12/24/2020 Approved CARLOS MATAMOROS
Wood Frame 12/24/2020 Approved CARLOS MATAMOROS
Drywall Nailing 1/14/2021 Corrections Issued ANTHONY MCDOWALL
Drywall Nailing 1/19/2021 Approved ANTHONY MCDOWALL
Pre-Inspection 3/16/2022 Approved GERMAN RODRIGUEZ MENDOZA
Gas Test 5/31/2023 Not Ready for Inspection STEPHANIE SWANSON
Gas Test 6/5/2023 Approved STEPHANIE SWANSON
PLUMBING-Final 6/7/2023 Corrections Issued BRENDAN LOONEY
ELECTRICAL-Final 6/27/2023 Not Ready for Inspection BRENDAN LOONEY
HVAC-Final 6/27/2023 Not Ready for Inspection BRENDAN LOONEY
Interior/Exterior Lathing 6/27/2023 Partial Approval BRENDAN LOONEY
PLUMBING-Final 6/27/2023 Not Ready for Inspection BRENDAN LOONEY
Final 3/21/2025 Not Ready for Inspection DANIEL VERA
Footing/Foundation/Slab 3/21/2025 Not Ready for Inspection DANIEL VERA
Green Building Final 3/21/2025 Not Ready for Inspection DANIEL VERA
SGSOV-Seismic Gas S/O Valve 3/21/2025 SGSOV Not Ready DANIEL VERA
Smoke Detectors 3/21/2025 Not Ready for Inspection DANIEL VERA
Final 4/14/2025 Corrections Issued SEAN HAUPT
Footing/Foundation/Slab 4/14/2025 Approved SEAN HAUPT
Green Building Final 4/14/2025 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 4/14/2025 SGSOV Approved SEAN HAUPT
Smoke Detectors 4/14/2025 Not Ready for Inspection SEAN HAUPT
Service/Power Release 4/15/2025 Approved SEAN HAUPT
Final 5/5/2025 Corrections Issued SEAN HAUPT
Smoke Detectors 5/5/2025 Approved SEAN HAUPT
Final 5/27/2025 OK to Issue CofO SEAN HAUPT