101 N MCCADDEN PL 90004
Certificate Information: 101 N MCCADDEN PL 90004
- Application / Permit
- 18014-20000-05419
- Plan Check / Job No.
- B18VN16368
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL, 49' 2" X 16'-1" AND 20'-3" X 4'-11" ADDITION; 46'-9" X 52'-5" (N) BASEMENT FOR (E) 2-STORY SFD.
- Permit Issued
- Issued on 3/27/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/21/2018 | APPLICANT |
| Green Plans Picked Up | 10/2/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 10/4/2018 | SELLA BENYAMIN |
| Corrections Issued | 10/10/2018 | SELLA BENYAMIN |
| Quality Review Completed | 10/17/2018 | STEVEN KIM |
| Building Plans Picked Up | 10/17/2018 | APPLICANT |
| Plan Check Approved | 3/6/2019 | SELLA BENYAMIN |
| Issued | 3/27/2019 | LADBS |
| CofO in Progress | 9/27/2022 | JOSEPH MCGARRY |
| Permit Finaled | 10/15/2022 | DEROLD HAUFF |
| CofO Issued | 10/15/2022 | DEROLD HAUFF |
| Permit Finaled | 10/15/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| HPOZ | Cleared | 10/12/2018 | SUKI GERSHENHORN |
| Eng Process Fee Ord 176,300 | Cleared | 10/17/2018 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 10/17/2018 | APEKSHYA BAJRACHARYA |
| Abandoned oil well | Cleared | 10/19/2018 | JOHN DALLAS |
| Green Code | Cleared | 11/29/2018 | MICHAEL AYERS |
| Low Impact Development | Cleared | 2/28/2019 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 3/5/2019 | JOHN LIN |
Contact Information
| Contractor | David Elliot Builders Inc; Lic. No.: 1021000-B | 8230 BEVERLY BLVD #6 LOS ANGELES, CA 90048 |
| Engineer | Mansuri,, Mehran; Lic. No.: C78614 | 14944 HESBY ST SHERMAN OAKS, CA 91403 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/1/2020 | Partial Approval | ARTHUR SARGSYAN |
| METHANE-Barrier | 4/1/2020 | Partial Inspection | ARTHUR SARGSYAN |
| METHANE-Subgrade | 4/1/2020 | Partial Inspection | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 4/15/2020 | Partial Approval | CHRIS CHRISTENSEN |
| METHANE-Barrier | 4/15/2020 | Partial Inspection | CHRIS CHRISTENSEN |
| METHANE-Subgrade | 4/15/2020 | Partial Inspection | CHRIS CHRISTENSEN |
| Deputy Reinf. Concrete | 4/17/2020 | Approved | ARTHUR SARGSYAN |
| Deputy Drilled-In Anchors | 4/24/2020 | Approved | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 4/24/2020 | Approved | ARTHUR SARGSYAN |
| METHANE-Barrier | 4/24/2020 | Approved | ARTHUR SARGSYAN |
| METHANE-Subgrade | 4/24/2020 | Approved | ARTHUR SARGSYAN |
| Deputy Reinf. Concrete | 4/28/2020 | Approved | ARTHUR SARGSYAN |
| Deputy Reinf. Concrete | 5/1/2020 | Conditional Approval | THOMAS LOGRASSO |
| PLUMBING-Rough | 5/22/2020 | Partial Approval | ARTHUR SARGSYAN |
| Underground Mechanical | 5/22/2020 | Approved | ARTHUR SARGSYAN |
| Reinforced Concrete Frame | 6/26/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 7/1/2020 | Approved | ARTHUR SARGSYAN |
| Deputy Reinf. Concrete | 7/2/2020 | Approved | ARTHUR SARGSYAN |
| Reinforced Concrete Frame | 7/23/2020 | Approved | ARTHUR SARGSYAN |
| Deputy Pre-Stress Concrete | 7/27/2020 | Approved | ARTHUR SARGSYAN |
| Deputy Shotcrete | 7/27/2020 | Approved | ARTHUR SARGSYAN |
| METHANE-Rough | 7/30/2020 | Approved | CHRIS CHRISTENSEN |
| Deputy Methane Barrier | 8/3/2020 | Approved | ARTHUR SARGSYAN |
| Deputy Methane Barrier | 8/4/2020 | Approved | ARTHUR SARGSYAN |
| METHANE-Barrier | 8/4/2020 | Approved | ARTHUR SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 8/6/2020 | Approved | ARTHUR SARGSYAN |
| Deputy Reinf. Concrete | 8/7/2020 | Approved | ARTHUR SARGSYAN |
| Reinforced Concrete Frame | 10/5/2020 | Approved | ARTHUR SARGSYAN |
| Deputy Reinf. Concrete | 10/8/2020 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Rough | 11/10/2020 | Partial Approval | JOSEPH MCGARRY |
| Wood Frame | 11/10/2020 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2021 | Partial Approval | ROBERT VORHIS |
| PLUMBING-Rough | 2/26/2021 | Conditional Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 4/9/2021 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 4/9/2021 | Approved | CHRIS CHRISTENSEN |
| Wood Frame | 4/9/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 4/29/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 4/29/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Insulation | 5/7/2021 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 5/7/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 5/11/2021 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 5/11/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Shower Pan | 5/11/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Drywall Nailing | 5/20/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 5/20/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Shower Pan | 5/20/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 6/30/2021 | Approved | THOMAS LOGRASSO |
| HVAC-Final | 3/21/2022 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Final | 3/24/2022 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Final | 3/24/2022 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 8/25/2022 | Approved | JULIAN AMAYA |
| Final | 8/25/2022 | Corrections Issued | JULIAN AMAYA |
| Green Building Final | 8/25/2022 | Partial Inspection | JULIAN AMAYA |
| SGSOV-Seismic Gas S/O Valve | 8/25/2022 | SGSOV Not Ready | JULIAN AMAYA |
| Smoke Detectors | 8/25/2022 | Approved | JULIAN AMAYA |
| Final | 9/19/2022 | Partial Approval | JOSEPH MCGARRY |
| Green Building Final | 9/19/2022 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 9/19/2022 | SGSOV Approved | JOSEPH MCGARRY |
| Final | 9/22/2022 | OK to Issue CofO | JOSEPH MCGARRY |