22014 W LEADWELL ST 91303

Certificate Information: 22014 W LEADWELL ST 91303

Application / Permit
18014-20000-05384
Plan Check / Job No.
B18VN16258
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
7'-1" X 8' ADDITION TO AND CONVERT THE (E) REC. ROOM INTO A (N) ACESSORY DWELLING UNIT PER AB 494 AND SB 229. WORK PER WFPP.
Permit Issued
Issued on 11/13/2018
Issuing Office
Valley
Current Status
CofO Issued on 11/23/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/20/2018 APPLICANT
Assigned to Plan Check Engineer 9/20/2018 MARVEL DELACRUZ
Corrections Issued 9/20/2018 MARVEL DELACRUZ
Applicant returned to address corrections 9/28/2018 MARVEL DELACRUZ
Applicant returned to address corrections 10/11/2018 NIKTA MOUSAVI
Issued 11/13/2018 LADBS
CofO in Progress 11/22/2020 DAVID STEPANYAN
Permit Finaled 11/23/2020 JOHN JANSON
CofO Issued 11/23/2020 JOHN JANSON
Permit Finaled 11/23/2020 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 9/20/2018 APEKSHYA BAJRACHARYA
Eng Process Fee Ord 176,300 Cleared 10/5/2018 RUDY TERRIQUEZ.
Roof/Waste drainage to street Cleared 10/5/2018 RUDY TERRIQUEZ.
Sewer availability Cleared 11/13/2018 KAYLA PEJI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/19/2018 Not Ready for Inspection PETER FOLLING
Footing/Foundation/Slab 12/11/2018 Corrections Issued PETER FOLLING
Footing/Foundation/Slab 1/22/2019 Not Ready for Inspection JOHN KIDWELL
ELECTRICAL-Rough 2/14/2019 Corrections Issued JOHN KIDWELL
Footing/Foundation/Slab 2/14/2019 Partial Approval JOHN KIDWELL
Underground Mechanical 3/8/2019 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 3/14/2019 Approved DONALD SUNSERI
SGSOV-Seismic Gas S/O Valve 3/14/2019 SGSOV Not Ready DONALD SUNSERI
ELECTRICAL-Rough 3/20/2019 Approved RYAN MCGILL
Floor/Roof Diaphrgm/Shear Wall 3/20/2019 Corrections Issued RYAN MCGILL
PLUMBING-Rough 12/17/2019 Corrections Issued PETER FOLLING
BUILDING-Rough-Frame 8/5/2020 Corrections Issued DAVID STEPANYAN
Footing/Foundation/Slab 8/5/2020 Approved DAVID STEPANYAN
HVAC-Rough 8/5/2020 Corrections Issued DAVID STEPANYAN
PLUMBING-Rough 8/5/2020 Corrections Issued DAVID STEPANYAN
PLUMBING-Rough 8/11/2020 Corrections Issued DAVID STEPANYAN
Special/Order Compliance 8/11/2020 Approved DONALD SUNSERI
Insulation 8/14/2020 Partial Approval DAVID STEPANYAN
Floor/Roof Diaphrgm/Shear Wall 8/19/2020 Approved DAVID STEPANYAN
HVAC-Rough 8/19/2020 Approved DAVID STEPANYAN
PLUMBING-Rough 8/19/2020 Partial Approval DAVID STEPANYAN
BUILDING-Rough-Frame 8/25/2020 Approved DAVID STEPANYAN
Green Building Rough 8/25/2020 Approved DAVID STEPANYAN
Interior/Exterior Lathing 8/25/2020 Partial Approval DAVID STEPANYAN
PLUMBING-Rough 8/25/2020 Approved DAVID STEPANYAN
Insulation 8/28/2020 Approved DAVID STEPANYAN
Drywall Nailing 9/11/2020 Approved DAVID STEPANYAN
Gas Test 11/2/2020 Approved TROY SANDERS
Final 11/20/2020 OK to Issue CofO DAVID STEPANYAN
Green Building Final 11/20/2020 Approved DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 11/20/2020 SGSOV Approved DAVID STEPANYAN
Smoke Detectors 11/20/2020 Approved DAVID STEPANYAN