9302 N STANWIN AVE 91331

Certificate Information: 9302 N STANWIN AVE 91331

Application / Permit
18014-20000-05363
Plan Check / Job No.
B18VN16196
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
17'-0"X4'-6" ADDITION TO AND CONVERT THE (E) 20'-0"X19'-4" GARAGE INTO A (N) ADU PER AB 494 AND SB 229 FOR ACCESSORY DWELLING UNITS. WORK PER WFPP.
Permit Issued
Issued on 3/5/2019
Issuing Office
Valley
Current Status
CofO Issued on 3/21/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/20/2018 APPLICANT
Assigned to Plan Check Engineer 9/20/2018 MARVEL DELACRUZ
Corrections Issued 9/20/2018 MARVEL DELACRUZ
Applicant returned to address corrections 2/25/2019 JOHNNY WU
Plan Check Approved 3/1/2019 JOHNNY WU
Issued 3/5/2019 LADBS
CofO in Progress 2/6/2020 MICHEL ABAJAN
CofO Issued 3/21/2020 MICHAEL SMITH
Permit Finaled 3/21/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 9/20/2018 EDUARDO PEDROZA
Roof/Waste drainage to street Cleared 9/20/2018 EDUARDO PEDROZA
Construction near power lines Cleared 1/11/2019 RIDWAN HARDY
Construction within easement Cleared 1/11/2019 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 2/25/2019 LEE GUILBEAUX
Sewer availability Cleared 3/1/2019 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/29/2019 Corrections Issued MICHEL ABAJAN
PLUMBING-Rough 5/29/2019 Not Ready for Inspection MICHEL ABAJAN
Footing/Foundation/Slab 6/4/2019 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Rough 6/4/2019 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 6/20/2019 Approved MICHEL ABAJAN
ELECTRICAL-Rough 8/8/2019 Corrections Issued MICHEL ABAJAN
PLUMBING-Rough 8/8/2019 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 8/15/2019 Approved MICHEL ABAJAN
ELECTRICAL-Rough 8/15/2019 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 8/15/2019 Approved MICHEL ABAJAN
Green Building Rough 8/15/2019 Approved MICHEL ABAJAN
PLUMBING-Rough 8/15/2019 Approved MICHEL ABAJAN
Gas Test 10/9/2019 Partial Approval MICHEL ABAJAN
Insulation 10/9/2019 Approved MICHEL ABAJAN
Interior/Exterior Lathing 10/9/2019 Approved MICHEL ABAJAN
Shower Pan 10/9/2019 Partial Approval MICHEL ABAJAN
Drywall Nailing 10/31/2019 Approved MICHEL ABAJAN
Interior/Exterior Lathing 11/25/2019 Not Ready for Inspection MICHEL ABAJAN
Interior/Exterior Lathing 12/19/2019 Approved MICHEL ABAJAN
ELECTRICAL-Final 1/3/2020 Not Ready for Inspection MICHEL ABAJAN
Final 1/3/2020 Not Ready for Inspection MICHEL ABAJAN
Green Building Final 1/3/2020 Not Ready for Inspection MICHEL ABAJAN
HVAC-Final 1/3/2020 Approved MICHEL ABAJAN
PLUMBING-Final 1/3/2020 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 1/3/2020 SGSOV Not Ready MICHEL ABAJAN
Smoke Detectors 1/3/2020 Not Ready for Inspection MICHEL ABAJAN
ELECTRICAL-Final 1/14/2020 Corrections Issued MICHEL ABAJAN
Final 1/14/2020 Corrections Issued MICHEL ABAJAN
Green Building Final 1/14/2020 Not Ready for Inspection MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 1/14/2020 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 1/14/2020 Approved MICHEL ABAJAN
ELECTRICAL-Final 2/5/2020 Approved MICHEL ABAJAN
Final 2/5/2020 OK to Issue CofO MICHEL ABAJAN
Green Building Final 2/5/2020 Approved MICHEL ABAJAN