1927 N WILTON PL 90068

Certificate Information: 1927 N WILTON PL 90068

Application / Permit
18014-20000-05355
Plan Check / Job No.
B18VN16180
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
14'-10" X 30'-11" AND 28'-2" X 30'-11" FIRST AND SECOND STORY ADDITIONS TO EXPAND AND REMODEL DWELLING.
Permit Issued
Issued on 12/18/2018
Issuing Office
Valley
Current Status
CofO Issued on 12/15/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/19/2018 APPLICANT
Green Plans Picked Up 10/2/2018 APPLICANT
Assigned to Plan Check Engineer 10/4/2018 SARAH YOUSSEF
Corrections Issued 10/9/2018 SARAH YOUSSEF
Quality Review Completed 10/11/2018 CHON CHIO KUO
Building Plans Picked Up 10/11/2018 APPLICANT
Applicant returned to address corrections 11/15/2018 SARAH YOUSSEF
Plan Check Approved 12/18/2018 CHON CHIO KUO
Issued 12/18/2018 LADBS
CofO in Progress 12/13/2022 RUBEN SALAS
CofO in Progress 12/13/2022 RUBEN SALAS
Permit Finaled 12/15/2022 DEROLD HAUFF
CofO Issued 12/15/2022 DEROLD HAUFF
Permit Finaled 12/15/2022 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 11/9/2018 MICHAEL AYERS
Eng Process Fee Ord 176,300 Cleared 11/13/2018 APEKSHYA BAJRACHARYA
Sewer availability Cleared 11/13/2018 APEKSHYA BAJRACHARYA
GPI Written Notices Cleared 11/15/2018 VASIL MIHALEV
Grading Pre-Inspection Cleared 11/15/2018 VASIL MIHALEV
Low Impact Development Cleared 11/20/2018 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 11/20/2018 STEVE MELGAR
HPOZ Cleared 11/26/2018 AMANDA KAINER
Miscellaneous Cleared 11/26/2018 AMANDA KAINER
Hold Cleared 1/8/2019 CYNTHIA RYAN

Contact Information

Contractor Owner-Builder       ,
Engineer Loayza,, Miguel Antonio; Lic. No.: C26290 20062 MERRIDY STREET      CHATSWORTH, CA 91311
Engineer Yuzon,, Benigno S; Lic. No.: C38991 25531 PRADO DELASBELLOTAS      CALABASAS, CA 91302

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/28/2018 Corrections Issued LUIS BARRALES
Footing/Foundation/Slab 1/2/2019 Approved LUIS BARRALES
Footing/Foundation/Slab 1/7/2019 Not Ready for Inspection LUIS BARRALES
Floor/Roof Diaphrgm/Shear Wall 1/25/2019 Corrections Issued RAUL BARAJAS
Insulation 1/25/2019 Not Ready for Inspection RAUL BARAJAS
BUILDING-Rough-Frame 1/29/2019 Partial Approval RONALD COWAN
Green Building Rough 1/29/2019 Not Ready for Inspection RONALD COWAN
Insulation 1/29/2019 Partial Approval RONALD COWAN
Gas Test 2/14/2019 Approved RONALD COWAN
BUILDING-Rough-Frame 4/9/2019 Corrections Issued RONALD COWAN
Green Building Rough 4/9/2019 Corrections Issued RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 4/12/2019 Not Ready for Inspection RONALD COWAN
BUILDING-Rough-Frame 5/21/2019 Not Ready for Inspection BRIAN SULLIVAN
Green Building Rough 5/21/2019 Not Ready for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 6/10/2019 Corrections Issued RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 6/10/2019 Corrections Issued RAUL BARAJAS
Green Building Rough 6/10/2019 Not Ready for Inspection RAUL BARAJAS
BUILDING-Rough-Frame 9/20/2019 Partial Inspection ROBERT CORNELL
Green Building Rough 9/20/2019 Not Ready for Inspection ROBERT CORNELL
Floor/Roof Diaphrgm/Shear Wall 1/30/2020 Approved ROBERT CORNELL
ELECTRICAL-Rough 2/12/2020 Approved ROBERT CORNELL
Footing/Foundation/Slab 2/12/2020 Approved ROBERT CORNELL
PLUMBING-Rough 2/12/2020 Approved ROBERT CORNELL
BUILDING-Rough-Frame 2/25/2020 Not Ready for Inspection ROBERT CORNELL
Green Building Rough 2/25/2020 Corrections Issued ROBERT CORNELL
Insulation 2/25/2020 Corrections Issued ROBERT CORNELL
BUILDING-Rough-Frame 3/2/2020 Corrections Issued RAUL BARAJAS
Green Building Rough 3/2/2020 Not Ready for Inspection RAUL BARAJAS
Insulation 3/2/2020 Not Ready for Inspection RAUL BARAJAS
BUILDING-Rough-Frame 3/6/2020 No Access for Inspection RAUL BARAJAS
Green Building Rough 3/6/2020 No Access for Inspection RAUL BARAJAS
Insulation 3/6/2020 No Access for Inspection RAUL BARAJAS
Insulation 3/11/2020 Approved ROBERT CORNELL
Drywall Nailing 4/2/2020 Approved STUART CHAPMAN
Interior/Exterior Lathing 4/8/2020 Corrections Issued ROBERT CORNELL
Interior/Exterior Lathing 4/15/2020 Not Ready for Inspection BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 4/29/2020 Partial Inspection BRIAN SULLIVAN
Interior/Exterior Lathing 4/29/2020 Not Ready for Inspection BRIAN SULLIVAN
Interior/Exterior Lathing 5/1/2020 No Access for Inspection BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 5/4/2020 No Access for Inspection BRIAN SULLIVAN
Interior/Exterior Lathing 5/4/2020 No Access for Inspection BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 5/6/2020 Not Ready for Inspection BRIAN SULLIVAN
Interior/Exterior Lathing 5/6/2020 Corrections Issued BRIAN SULLIVAN
Interior/Exterior Lathing 5/21/2020 Partial Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 5/27/2020 Conditional Approval JOSEPH MCGARRY
Green Building Rough 5/27/2020 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 5/27/2020 Corrections Issued JOSEPH MCGARRY
Interior/Exterior Lathing 6/5/2020 Conditional Approval CHRISTOPHER DELLEFIELD
HVAC-Rough 12/14/2020 Corrections Issued BRIAN SULLIVAN
Shower Pan 12/14/2020 Approved BRIAN SULLIVAN
Pool Piping 3/9/2021 Not Ready for Inspection BRIAN SULLIVAN
Wood Frame 3/9/2021 Not Ready for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 4/1/2021 Not Ready for Inspection BRIAN SULLIVAN
Rough-Elec/Plmb/HVAC 4/1/2021 Corrections Issued BRIAN SULLIVAN
BUILDING-Rough-Frame 9/8/2021 Partial Inspection RAUL BARAJAS
Wood Frame 9/8/2021 Partial Inspection RAUL BARAJAS
BUILDING-Rough-Frame 11/1/2021 Not Ready for Inspection BRIAN SULLIVAN
HVAC-Final 11/1/2021 Not Ready for Inspection BRIAN SULLIVAN
HVAC-Rough 11/1/2021 Corrections Issued BRIAN SULLIVAN
BUILDING-Rough-Frame 11/16/2021 Corrections Issued JOSEPH MCGARRY
HVAC-Final 11/16/2021 Not Ready for Inspection JOSEPH MCGARRY
HVAC-Rough 11/16/2021 Not Ready for Inspection JOSEPH MCGARRY
HVAC-Final 11/19/2021 Not Ready for Inspection BRIAN SULLIVAN
HVAC-Rough 11/19/2021 Not Ready for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 11/29/2021 Approved JOSEPH MCGARRY
Drywall Nailing 11/29/2021 Approved JOSEPH MCGARRY
HVAC-Rough 11/29/2021 Approved JOSEPH MCGARRY
Insulation 11/29/2021 Approved JOSEPH MCGARRY
PLUMBING-Final 12/21/2021 Not Ready for Inspection BRIAN SULLIVAN
ELECTRICAL-Final 5/5/2022 Corrections Issued BRIAN SULLIVAN
PLUMBING-Final 5/5/2022 Corrections Issued BRIAN SULLIVAN
ELECTRICAL-Final 5/10/2022 Approved BRIAN SULLIVAN
PLUMBING-Final 5/10/2022 Approved BRIAN SULLIVAN
Final 6/30/2022 Not Ready for Inspection BRIAN SULLIVAN
Green Building Final 6/30/2022 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 6/30/2022 SGSOV Approved BRIAN SULLIVAN
Smoke Detectors 6/30/2022 Approved BRIAN SULLIVAN
Final 8/17/2022 Corrections Issued STUART CHAPMAN
Final 9/12/2022 Not Ready for Inspection STUART CHAPMAN
Final 10/6/2022 Corrections Issued STUART CHAPMAN
Final 12/13/2022 OK to Issue CofO RUBEN SALAS