7768 N SHADYSPRING PL 91504

Certificate Information: 7768 N SHADYSPRING PL 91504

Application / Permit
18014-20000-05108
Plan Check / Job No.
B18VN15366
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE.(E) ATTACHED GARAGE. 18'-3''X 59'-0''. 18'-3''x 40'-0'' ADDITION OF 2 BEDROOMS, 1 FULL BATH, AND 18'3''x 19'-0'' GARAGE TO (E) SINGLE FAMILY DWELLING.
Permit Issued
Issued on 9/19/2018
Issuing Office
Valley
Current Status
CofO Issued on 3/14/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/6/2018 APPLICANT
Assigned to Plan Check Engineer 9/6/2018 DANNY MORALES
Corrections Issued 9/6/2018 DANNY MORALES
Building Plans Picked Up 9/11/2018 APPLICANT
Plan Check Approved 9/19/2018 DANNY MORALES
Issued 9/19/2018 LADBS
CofO in Progress 10/18/2019 BEAU COLLINS
Permit Finaled 3/14/2020 MICHAEL SMITH
CofO Issued 3/14/2020 MICHAEL SMITH
Permit Finaled 3/14/2020 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/13/2018 JOHN LIN
Hydrant and Access approval Cleared 9/13/2018 JOHN DALLAS
Low Impact Development Cleared 9/13/2018 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 9/13/2018 EDUARDO PEDROZA
Sewer availability Cleared 9/13/2018 JOHN LIN
GPI Written Notices Cleared 9/19/2018 DANNY MORALES
Grading Pre-Inspection Cleared 9/19/2018 DANNY MORALES

Contact Information

Contractor Owner-Builder       ,
Engineer Morales, Carlos A; Lic. No.: C69972 38100 SAN MATEO AVE      PALMDALE, CA 93551

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/2/2019 Partial Approval BEAU COLLINS
Footing/Foundation/Slab 1/3/2019 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 1/8/2019 Conditional Approval BEAU COLLINS
Footing/Foundation/Slab 1/23/2019 Approved COREY HUPP
Floor/Roof Diaphrgm/Shear Wall 3/12/2019 Partial Approval COREY HUPP
Rough-Elec/Plmb/HVAC 4/4/2019 Corrections Issued BEAU COLLINS
BUILDING-Rough-Frame 4/19/2019 Corrections Issued BEAU COLLINS
Rough-Elec/Plmb/HVAC 4/26/2019 Approved BEAU COLLINS
BUILDING-Rough-Frame 5/10/2019 Corrections Issued BEAU COLLINS
Green Building Rough 5/10/2019 Approved BEAU COLLINS
Interior/Exterior Lathing 5/10/2019 Not Ready for Inspection BEAU COLLINS
MERV13>=Rough 5/10/2019 Approved BEAU COLLINS
Interior/Exterior Lathing 5/20/2019 Approved BEAU COLLINS
Insulation 6/3/2019 Approved BEAU COLLINS
Drywall Nailing 6/20/2019 Partial Approval BEAU COLLINS
Shower Pan 8/13/2019 Approved BEAU COLLINS
BUILDING-Rough-Frame 9/19/2019 Corrections Issued BEAU COLLINS
Green Building Final 9/19/2019 Partial Approval BEAU COLLINS
MERV13>=Final 9/19/2019 Approved BEAU COLLINS
SGSOV-Seismic Gas S/O Valve 9/19/2019 SGSOV Not Ready BEAU COLLINS
Smoke Detectors 9/19/2019 Not Ready for Inspection BEAU COLLINS
BUILDING-Rough-Frame 10/11/2019 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 10/11/2019 Approved JENNIFER RABUCHIN
Final 10/11/2019 Partial Approval JENNIFER RABUCHIN
Green Building Final 10/11/2019 Approved JENNIFER RABUCHIN
HVAC-Final 10/11/2019 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 10/11/2019 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 10/11/2019 Approved JENNIFER RABUCHIN
Final 10/17/2019 OK to Issue CofO BEAU COLLINS
Special/Order Compliance 1/2/2020 Corrections Issued BEAU COLLINS