218 S LARCHMONT BLVD 90004

Certificate Information: 218 S LARCHMONT BLVD 90004

Application / Permit
18014-20000-05049
Plan Check / Job No.
B18VN15174
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
REMOVE (E) 5'-0" X 24'-6" PORTION OF (E) STORAGE, CONVERT PORTION OF GARAGE AND STORAGE ON FIRST FLOOR AND ADD IRREGULAR 19'-4" X 27'-3" SECOND FLOOR FOR (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229, 11'-5" X 18'-7" PORTION OF (E) GARAGE TO REMAIN. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 10/9/2019
Issuing Office
Valley
Current Status
Issued on 10/9/2019
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/4/2018 APPLICANT
Assigned to Plan Check Engineer 9/20/2018 JENNIFER LEE
Corrections Issued 9/26/2018 JENNIFER LEE
Quality Review Completed 9/27/2018 STEVEN KIM
Building Plans Picked Up 9/28/2018 APPLICANT
Green Plans Picked Up 9/28/2018 APPLICANT
Plan Check Approved 6/27/2019 JENNIFER LEE
Issued 10/9/2019 LADBS

Permit Application Clearance Information

CPC Cleared 10/16/2018 RICK TORRES
CPC Cleared 10/30/2018 MAX LODER
HPOZ Cleared 10/30/2018 MAX LODER
ZI Cleared 10/30/2018 MAX LODER
Construction near power lines Cleared 4/24/2019 RIDWAN HARDY
Construction within easement Cleared 4/24/2019 RIDWAN HARDY
Address approval Cleared 6/20/2019 JULIUS GARCIA
Eng Process Fee Ord 176,300 Cleared 6/20/2019 JULIUS GARCIA
ZI Cleared 6/20/2019 MAX LODER
Green Code Cleared 6/25/2019 PARISA ZAHABI
Roof/Waste drainage to street Cleared 6/25/2019 APEKSHYA BAJRACHARYA
Sewer availability Cleared 6/25/2019 APEKSHYA BAJRACHARYA

Contact Information

Contractor O'Connor - Mackey Inc; Lic. No.: 761277-B 5739 KANAN ROAD #373      AGOURA HILLS, CA 91301
Engineer Tan, Henreik Steven; Lic. No.: C65723 5100 LLANO DRIVE      WOODLAND HILLS, CA 91364

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 11/13/2019 Partial Approval DANIEL GONZALEZ
Excavation/Setback/Form/Re-Bar 12/9/2019 Approved DANIEL GONZALEZ
Special/Order Compliance 12/13/2019 Partial Inspection DANIEL GONZALEZ
Special/Order Compliance 1/27/2020 Approved BRAD BESCOS
Floor/Roof Diaphrgm/Shear Wall 2/5/2020 Approved ARTHUR SARGSYAN
HVAC-Rough 3/3/2020 Not Ready for Inspection ARTHUR SARGSYAN
ELECTRICAL-Rough 4/10/2020 Approved ARTHUR SARGSYAN
HVAC-Rough 4/10/2020 Approved ARTHUR SARGSYAN
PLUMBING-Rough 4/10/2020 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 5/5/2020 Approved ARTHUR SARGSYAN
Special/Order Compliance 5/18/2020 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 7/12/2021 Approved JOSEPH MCGARRY
Drywall Nailing 7/12/2021 Approved JOSEPH MCGARRY
Final 7/12/2021 Corrections Issued JOSEPH MCGARRY
Footing/Foundation/Slab 7/12/2021 Approved JOSEPH MCGARRY
Green Building Final 7/12/2021 Approved JOSEPH MCGARRY
Green Building Rough 7/12/2021 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 7/12/2021 SGSOV Approved JOSEPH MCGARRY
Smoke Detectors 7/12/2021 Approved JOSEPH MCGARRY
Special/Order Compliance 5/30/2025 Corrections Issued RAUL BARAJAS
Final 7/21/2025 Corrections Issued RONNIE MINDANAO
ELECTRICAL-Final 12/10/2025 Corrections Issued JEFFREY MEAD
HVAC-Final 12/10/2025 Approved JEFFREY MEAD