12300-12302 W SHELDON ST 91352
Certificate Information: 12300-12302 W SHELDON ST 91352
- Application / Permit
- 18014-20000-05027
- Plan Check / Job No.
- B18VN15097
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT ATTACHED GARAGE (20' X 18'-3") TO ACCESSORY DWELLING UNIT PER AB494 & SB229; ADD (2) BEDROOMS, FULL BATHROOM & FAMILY ROOM (43'-8" X 13'-3") TO REAR OF (E) SFD W/ ATTACHED GARAGE PER WFPP **** COMPLY WITH DEPARTMENT ORDER EFFECTIVE DATE 07/20/2018. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE ****
- Permit Issued
- Issued on 11/16/2018
- Issuing Office
- Valley
- Current Status
- Issued on 11/16/2018
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/4/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 9/27/2018 | NILOOFAR MEHRAIN |
| Corrections Issued | 10/1/2018 | NILOOFAR MEHRAIN |
| Quality Review Completed | 10/2/2018 | CHON CHIO KUO |
| Green Plans Picked Up | 10/4/2018 | APPLICANT |
| Building Plans Picked Up | 10/12/2018 | APPLICANT |
| Plan Check Approved | 11/8/2018 | NILOOFAR MEHRAIN |
| Issued | 11/16/2018 | LADBS |
Permit Application Clearance Information
| Address approval | Cleared | 10/22/2018 | ADOLFO GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/22/2018 | ADOLFO GUTIERREZ |
| Low Impact Development | Cleared | 10/22/2018 | MITESH PATEL |
| Permit | Cleared | 10/22/2018 | ADOLFO GUTIERREZ |
| Roof/Waste drainage to street | Cleared | 10/22/2018 | STEVE MELGAR |
| Sewer availability | Cleared | 10/22/2018 | ADOLFO GUTIERREZ |
| Hydrant and Access approval | Cleared | 10/24/2018 | ROBERT DUFF |
| Green Code | Cleared | 10/31/2018 | MICHAEL AYERS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RICHARD ROBLES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HAGOP BADOSSIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| FELIPE PENICHE, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/10/2019 | No Access for Inspection | MICKEY YAMASHITA |
| Pre-Inspection | 4/11/2019 | Corrections Issued | MICKEY YAMASHITA |
| Deputy Drilled-In Anchors | 4/30/2019 | Conditional Approval | MICKEY YAMASHITA |
| Footing/Foundation/Slab | 5/1/2019 | Partial Approval | MICKEY YAMASHITA |
| BUILDING-Rough-Frame | 5/15/2019 | Corrections Issued | MICKEY YAMASHITA |
| PLUMBING-Rough | 5/15/2019 | Corrections Issued | MICKEY YAMASHITA |
| Gas Test | 5/21/2019 | Partial Approval | MICKEY YAMASHITA |
| PLUMBING-Rough | 5/21/2019 | Approved | MICKEY YAMASHITA |
| BUILDING-Rough-Frame | 5/24/2019 | Partial Inspection | DAVID JAMES |
| ELECTRICAL-Rough | 5/24/2019 | Approved | DAVID JAMES |
| Green Building Rough | 5/24/2019 | Not Ready for Inspection | DAVID JAMES |
| MERV13>=Rough | 5/24/2019 | Not Ready for Inspection | DAVID JAMES |
| Wood Frame | 5/24/2019 | Not Ready for Inspection | DAVID JAMES |
| Gas Test | 5/30/2019 | Partial Approval | MICKEY YAMASHITA |
| Green Building Rough | 5/30/2019 | Approved | MICKEY YAMASHITA |
| HVAC-Rough | 5/30/2019 | Conditional Approval | MICKEY YAMASHITA |
| Insulation | 5/30/2019 | Approved | MICKEY YAMASHITA |
| Interior/Exterior Lathing | 5/30/2019 | Partial Approval | MICKEY YAMASHITA |
| PLUMBING-Rough | 5/30/2019 | Approved | MICKEY YAMASHITA |
| Underground Mechanical | 5/30/2019 | Approved | MICKEY YAMASHITA |
| Drywall Nailing | 6/3/2019 | Approved | MICKEY YAMASHITA |
| BUILDING-Rough-Frame | 6/17/2019 | Approved | MICKEY YAMASHITA |
| Final | 6/17/2019 | Not Ready for Inspection | MICKEY YAMASHITA |
| Footing/Foundation/Slab | 6/17/2019 | Approved | MICKEY YAMASHITA |
| Green Building Final | 6/17/2019 | Approved | MICKEY YAMASHITA |
| MERV13>=Final | 6/17/2019 | Approved | MICKEY YAMASHITA |
| MERV13>=Rough | 6/17/2019 | Approved | MICKEY YAMASHITA |
| SGSOV-Seismic Gas S/O Valve | 6/17/2019 | SGSOV Not Ready | MICKEY YAMASHITA |
| Smoke Detectors | 6/17/2019 | Approved | MICKEY YAMASHITA |
| Final | 6/20/2019 | Not Ready for Inspection | MICKEY YAMASHITA |
| SGSOV-Seismic Gas S/O Valve | 6/20/2019 | SGSOV Not Ready | MICKEY YAMASHITA |
| Special/Order Compliance | 6/3/2022 | Approved | THOMAS WOODS |
| Final | 10/6/2023 | Corrections Issued | LEO MILBAUER |
| SGSOV-Seismic Gas S/O Valve | 10/6/2023 | SGSOV Not Ready | LEO MILBAUER |
| Final | 6/10/2026 | Partial Inspection | JOEL GUARDADO |
| SGSOV-Seismic Gas S/O Valve | 6/10/2026 | SGSOV Not Ready | JOEL GUARDADO |
| Final | 6/18/2026 | Partial Approval | JOEL GUARDADO |
| SGSOV-Seismic Gas S/O Valve | 6/18/2026 | SGSOV Approved | JOEL GUARDADO |