1817 S PENMAR AVE 90291
Certificate Information: 1817 S PENMAR AVE 90291
- Application / Permit
- 18014-20000-04861
- Plan Check / Job No.
- B18VN14551
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Completly remove all interior and windows, reconfigure kitchen/living room, 1/2 bathroom and add irregular shape 19' x 22' 2nd floor bedroom. Project include reframing remaining roof and underpinning footing for current code compliant.
- Permit Issued
- Issued on 2/21/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/16/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/23/2018 | APPLICANT |
| Green Plans Picked Up | 9/7/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 9/13/2018 | ALDOUS CHIC |
| Corrections Issued | 9/17/2018 | ALDOUS CHIC |
| Quality Review Completed | 9/20/2018 | OMID HEDAYAT |
| Building Plans Picked Up | 9/24/2018 | APPLICANT |
| Applicant returned to address corrections | 10/1/2019 | ALDOUS CHIC |
| Plan Check Approved | 11/5/2019 | ALDOUS CHIC |
| Issued | 2/21/2020 | LADBS |
| CofO in Progress | 12/12/2023 | HERBERT GIRON |
| Permit Finaled | 12/16/2023 | DANIEL ORRANTE |
| CofO Issued | 12/16/2023 | DANIEL ORRANTE |
| Permit Finaled | 12/16/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| "Q" conditions | Cleared | 4/9/2019 | JOE LUCKEY |
| Eng Process Fee Ord 176,300 | Cleared | 4/9/2019 | JEANIE LAM |
| Green Code | Cleared | 4/26/2019 | MICHAEL AYERS |
| Specific Plan | Cleared | 5/29/2019 | PEDRO AYALA |
| Low Impact Development | Cleared | 9/20/2019 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 9/20/2019 | JEANETTE VONG |
| Housing rent stabilization | Cleared | 10/29/2019 | STEVEN HOFSTAD |
Contact Information
| Contractor | Jensen Const Inc; Lic. No.: 787346-B | 1409 FOOTHILL BLVD SUITE 204 LA CANADA, CA 91011 |
| Engineer | Kim, Hong Kook; Lic. No.: C64529 | 839 S MUIRFIELD RD LOS ANGELES, CA 90005 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/18/2020 | Approved | DAVID HEINE |
| PLUMBING-Rough | 12/31/2020 | Corrections Issued | DAVID HEINE |
| Wood Frame | 12/31/2020 | Corrections Issued | DAVID HEINE |
| Underground Mechanical | 1/5/2021 | Partial Approval | DAVID HEINE |
| Wood Frame | 1/5/2021 | Partial Approval | DAVID HEINE |
| Floor/Roof Diaphrgm/Shear Wall | 1/7/2021 | Partial Approval | DAVID HEINE |
| Floor/Roof Diaphrgm/Shear Wall | 1/15/2021 | Conditional Approval | DAVID HEINE |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2021 | Partial Approval | JOHNNY MIRANDA |
| Underground Mechanical | 3/26/2021 | Partial Approval | JOHNNY MIRANDA |
| Underground Mechanical | 4/21/2021 | Partial Inspection | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2021 | Partial Approval | JOHNNY MIRANDA |
| HVAC-Rough | 5/26/2021 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 5/26/2021 | Approved | JOHNNY MIRANDA |
| Shower Pan | 6/21/2021 | Approved | AMY COLIN |
| ELECTRICAL-Rough | 9/28/2021 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 10/4/2021 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 10/4/2021 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 10/4/2021 | Partial Approval | JOHNNY MIRANDA |
| Verify Sprinkler Sign Off | 10/4/2021 | Partial Approval | JOHNNY MIRANDA |
| Insulation | 10/7/2021 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 10/15/2021 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 11/4/2021 | Approved | STEPHANIE SWANSON |
| Gas Test | 5/20/2022 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 6/9/2022 | Corrections Issued | PATRICK QUALEY |
| ELECTRICAL-Final | 6/17/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 8/11/2022 | Corrections Issued | DAVID FEILER |
| HVAC-Final | 8/17/2022 | Corrections Issued | DAVID FEILER |
| PLUMBING-Final | 8/17/2022 | Approved | DAVID FEILER |
| Final | 8/29/2022 | Corrections Issued | DAVID FEILER |
| Green Building Final | 8/29/2022 | Approved | DAVID FEILER |
| HVAC-Final | 8/29/2022 | Not Ready for Inspection | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 8/29/2022 | SGSOV Approved | DAVID FEILER |
| Smoke Detectors | 8/29/2022 | Not Ready for Inspection | DAVID FEILER |
| HVAC-Final | 10/27/2022 | Approved | JESUS RODRIGUEZ |
| Final | 10/2/2023 | Corrections Issued | HERBERT GIRON |
| Smoke Detectors | 10/2/2023 | Approved | HERBERT GIRON |
| Service/Power Release | 10/6/2023 | Approved | HERBERT GIRON |
| Final | 12/11/2023 | OK to Issue CofO | HERBERT GIRON |