1813 S PENMAR AVE 90291

Certificate Information: 1813 S PENMAR AVE 90291

Application / Permit
18014-20000-04860
Plan Check / Job No.
B18VN14551
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Completly remove all interior and windows, reconfigure kitchen/living room, 1/2 bathroom and add irregular shape 24' x 23.5' new 2nd floor for bedroom. Project include reframing remaining roof and underpinning footing for current code compliant.
Permit Issued
Issued on 2/21/2020
Issuing Office
Valley
Current Status
CofO Issued on 12/16/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/23/2018 APPLICANT
Green Plans Picked Up 9/7/2018 APPLICANT
Assigned to Plan Check Engineer 9/13/2018 ALDOUS CHIC
Corrections Issued 9/17/2018 ALDOUS CHIC
Quality Review Completed 9/20/2018 OMID HEDAYAT
Building Plans Picked Up 9/24/2018 APPLICANT
Applicant returned to address corrections 10/1/2019 ALDOUS CHIC
Plan Check Approved 11/5/2019 ALDOUS CHIC
Issued 2/21/2020 LADBS
CofO in Progress 12/12/2023 HERBERT GIRON
Permit Finaled 12/16/2023 DANIEL ORRANTE
CofO Issued 12/16/2023 DANIEL ORRANTE
Permit Finaled 12/16/2023 DANIEL ORRANTE

Permit Application Clearance Information

"Q" conditions Cleared 4/9/2019 JOE LUCKEY
Eng Process Fee Ord 176,300 Cleared 4/9/2019 JEANIE LAM
Green Code Cleared 4/26/2019 MICHAEL AYERS
Specific Plan Cleared 5/29/2019 PEDRO AYALA
Low Impact Development Cleared 9/20/2019 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 9/20/2019 JEANETTE VONG
Housing rent stabilization Cleared 10/18/2019 STEVEN HOFSTAD

Contact Information

Contractor Jensen Const Inc; Lic. No.: 787346-B 1409 FOOTHILL BLVD SUITE 204      LA CANADA, CA 91011
Engineer Kim, Hong Kook; Lic. No.: C64529 839 S MUIRFIELD RD      LOS ANGELES, CA 90005

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/21/2020 Partial Approval DAVID HEINE
Footing/Foundation/Slab 12/18/2020 Partial Approval DAVID HEINE
PLUMBING-Rough 12/31/2020 Corrections Issued DAVID HEINE
Wood Frame 12/31/2020 Corrections Issued DAVID HEINE
Underground Mechanical 1/5/2021 Partial Approval DAVID HEINE
Wood Frame 1/5/2021 Partial Approval DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 1/7/2021 Partial Approval DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 1/15/2021 Conditional Approval DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 3/4/2021 Partial Approval JOHNNY MIRANDA
Underground Mechanical 3/26/2021 Partial Approval JOHNNY MIRANDA
Underground Mechanical 4/21/2021 Partial Inspection KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 5/7/2021 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 6/4/2021 Approved JOHNNY MIRANDA
Shower Pan 6/21/2021 Approved AMY COLIN
ELECTRICAL-Rough 10/7/2021 Approved JOHNNY MIRANDA
HVAC-Rough 10/7/2021 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 10/13/2021 Approved DAVID FEILER
Green Building Final 10/13/2021 Not Ready for Inspection DAVID FEILER
Green Building Rough 10/13/2021 Approved DAVID FEILER
Interior/Exterior Lathing 10/13/2021 Partial Approval DAVID FEILER
Insulation 10/19/2021 Approved DAVID FEILER
Drywall Nailing 10/25/2021 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 11/4/2021 Approved STEPHANIE SWANSON
Gas Test 5/23/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 6/10/2022 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Final 6/17/2022 Approved JESUS RODRIGUEZ
HVAC-Rough 8/18/2022 Corrections Issued DAVID FEILER
PLUMBING-Final 8/18/2022 Approved DAVID FEILER
Final 8/29/2022 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 8/29/2022 Approved DAVID FEILER
Green Building Final 8/29/2022 Approved DAVID FEILER
HVAC-Final 8/29/2022 Not Ready for Inspection DAVID FEILER
SGSOV-Seismic Gas S/O Valve 8/29/2022 SGSOV Approved DAVID FEILER
Smoke Detectors 8/29/2022 Not Ready for Inspection DAVID FEILER
HVAC-Final 10/27/2022 Approved JESUS RODRIGUEZ
Service/Power Release 10/6/2023 Approved HERBERT GIRON
Smoke Detectors 10/6/2023 Approved HERBERT GIRON
Final 12/11/2023 OK to Issue CofO HERBERT GIRON