16451 W SHADOW MOUNTAIN DR 90272

Certificate Information: 16451 W SHADOW MOUNTAIN DR 90272

Application / Permit
18014-20000-04847
Plan Check / Job No.
B18VN14601
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL AND ADD OPEN BALCONY TO (E) SFD.
Permit Issued
Issued on 6/16/2020
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 5/11/2021

Permit Application Status History

Submitted 8/24/2018 APPLICANT
Green Plans Picked Up 9/18/2018 APPLICANT
Assigned to Plan Check Engineer 9/27/2018 DANNY MORALES
Corrections Issued 10/18/2018 DANNY MORALES
Quality Review Completed 10/22/2018 OMID HEDAYAT
Building Plans Picked Up 10/30/2018 APPLICANT
Plan Check Approved 11/18/2019 ARTIN ZARUKIAN
Issued 6/16/2020 LADBS
Permit Finaled 5/11/2021 ANDREW NAVE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/29/2019 ANTHONY MAINEZ
Watercourse Cleared 10/29/2019 ANTHONY MAINEZ
Green Code Cleared 10/31/2019 DAVID MATSON
Grading Pre-Inspection Cleared 11/5/2019 MANUEL TEJADA
ZI Cleared 12/9/2019 SARAH GOLDMAN
Coastal Zone Cleared 2/18/2020 DENZEL HENDERSON

Contact Information

Architect Borukhim, Behdad; Lic. No.: C33202 2102 VETERAN AVENUE      LOS ANGELES, CA 900255724
Contractor Stevens Mark Construction Co Inc; Lic. No.: 681686-B 19420 SANTA RITA STREET      TARZANA, CA 91356
Engineer , ; Lic. No.: S2504       ,

Inspector Information

DANIEL VERA, (213) 577-9924 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/10/2020 Approved KENNETH NAGLE
BUILDING-Rough-Frame 10/2/2020 Approved ANDREW NAVE
PLUMBING-Rough 10/2/2020 Not Ready for Inspection ANDREW NAVE
ELECTRICAL-Rough 10/13/2020 Partial Inspection ANDREW NAVE
HVAC-Rough 10/13/2020 Not Ready for Inspection ANDREW NAVE
PLUMBING-Rough 10/13/2020 Approved ANDREW NAVE
ELECTRICAL-Rough 10/15/2020 Approved ANDREW NAVE
HVAC-Rough 10/15/2020 Approved ANDREW NAVE
Wood Frame 10/20/2020 Partial Approval ANDREW NAVE
Shower Pan 10/26/2020 Approved ANDREW NAVE
Insulation 11/4/2020 Approved ANDREW NAVE
Drywall Nailing 11/9/2020 Approved ANDREW NAVE
Interior/Exterior Lathing 11/23/2020 Partial Approval ANDREW NAVE
Interior/Exterior Lathing 11/25/2020 Approved ANDREW NAVE
Final 4/13/2021 Partial Inspection ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 4/13/2021 SGSOV Not Ready ANDREW NAVE
Smoke Detectors 4/13/2021 Corrections Issued ANDREW NAVE
Final 5/11/2021 Permit Finaled ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 5/11/2021 SGSOV Approved ANDREW NAVE
Smoke Detectors 5/11/2021 Approved ANDREW NAVE