8345 S COLEGIO DR 90045
Certificate Information: 8345 S COLEGIO DR 90045
- Application / Permit
- 18014-20000-04686
- Plan Check / Job No.
- B18VN14021
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 79 SF FIRST FLOOR ADDITION TO (E) SINGLE FAMILY DWELLING WITH 5'-0" X 16'-6" PORCH AND 35'-0" X 29'-4" IRREGULAR SHAPED SECOND STORY ADDTION TO (E) SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 12/17/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/16/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 9/20/2018 | SARKIS HARABEDIAN |
| Corrections Issued | 9/26/2018 | SARKIS HARABEDIAN |
| Quality Review Completed | 10/1/2018 | OMID HEDAYAT |
| Building Plans Picked Up | 10/1/2018 | APPLICANT |
| Green Plans Picked Up | 10/12/2018 | APPLICANT |
| Applicant returned to address corrections | 11/29/2018 | SARKIS HARABEDIAN |
| Plan Check Approved | 12/12/2018 | SARKIS HARABEDIAN |
| Issued | 12/17/2018 | LADBS |
| CofO in Progress | 4/15/2022 | RICHARD STEINBACH |
| Permit Finaled | 4/19/2022 | DANIEL ORRANTE |
| CofO Issued | 4/19/2022 | DANIEL ORRANTE |
| Permit Finaled | 4/19/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/15/2018 | MARKOS PEREZ-BRAN |
| Green Code | Cleared | 11/15/2018 | MICHAEL AYERS |
| Low Impact Development | Cleared | 11/15/2018 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 11/15/2018 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 11/15/2018 | MARKOS PEREZ-BRAN |
| GPI Written Notices | Cleared | 11/29/2018 | SARKIS HARABEDIAN |
| Grading Pre-Inspection | Cleared | 11/29/2018 | SARKIS HARABEDIAN |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: C30383 | 5739 KANAN ROAD # 133 AGOURA HILLS, CA 91301 |
| Contractor | M F Construction & Design Inc; Lic. No.: 762001-B | 2413 S 3RD AVENUE ARCADIA, CA 91006 |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/4/2019 | Approved | JUAN VALENZUELA |
| METHANE-Barrier | 3/4/2019 | Approved | JUAN VALENZUELA |
| METHANE-Subgrade | 3/4/2019 | Approved | JUAN VALENZUELA |
| PLUMBING-Rough | 4/9/2019 | Not Ready for Inspection | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 6/28/2019 | Conditional Approval | JUAN VALENZUELA |
| Deputy Drilled-In Anchors | 7/25/2019 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 8/9/2019 | Partial Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 8/9/2019 | Approved | JUAN VALENZUELA |
| Green Building Rough | 8/9/2019 | Not Ready for Inspection | JUAN VALENZUELA |
| METHANE-Rough | 8/9/2019 | Approved | JUAN VALENZUELA |
| PLUMBING-Rough | 8/9/2019 | Partial Approval | JUAN VALENZUELA |
| Deputy Wood Construction | 8/12/2019 | Conditional Approval | JUAN VALENZUELA |
| Deputy Drilled-In Anchors | 8/14/2019 | Approved | JUAN VALENZUELA |
| Footing/Foundation/Slab | 9/27/2019 | Approved | JUAN VALENZUELA |
| Deputy Wood Construction | 10/1/2019 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2019 | Partial Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2019 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2019 | Conditional Approval | JUAN VALENZUELA |
| Interior/Exterior Lathing | 1/14/2020 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 1/28/2020 | Conditional Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 1/28/2020 | Approved | JUAN VALENZUELA |
| Green Building Rough | 1/28/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| HVAC-Rough | 1/28/2020 | Conditional Approval | JUAN VALENZUELA |
| PLUMBING-Rough | 1/28/2020 | Approved | JUAN VALENZUELA |
| Insulation | 2/5/2020 | Conditional Approval | JUAN VALENZUELA |
| Drywall Nailing | 2/7/2020 | Approved | JUAN VALENZUELA |
| Green Building Rough | 2/7/2020 | Approved | JUAN VALENZUELA |
| HVAC-Rough | 2/7/2020 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 2/19/2020 | Approved | JUAN VALENZUELA |
| Shower Pan | 2/19/2020 | Approved | JUAN VALENZUELA |
| HVAC-Final | 4/24/2020 | Corrections Issued | JUAN VALENZUELA |
| PLUMBING-Final | 4/24/2020 | Corrections Issued | JUAN VALENZUELA |
| ELECTRICAL-Final | 4/28/2020 | Corrections Issued | JUAN VALENZUELA |
| Smoke Detectors | 4/28/2020 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 5/8/2020 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 5/8/2020 | Approved | JUAN VALENZUELA |
| Final | 5/8/2020 | Corrections Issued | JUAN VALENZUELA |
| Green Building Final | 5/8/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| HVAC-Final | 5/8/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| PLUMBING-Final | 5/8/2020 | Approved | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 5/8/2020 | SGSOV Approved | JUAN VALENZUELA |
| Final | 7/29/2020 | Corrections Issued | JUAN VALENZUELA |
| Green Building Final | 7/29/2020 | Approved | JUAN VALENZUELA |
| HVAC-Final | 7/29/2020 | Approved | JUAN VALENZUELA |
| PLUMBING-Final | 7/29/2020 | Approved | JUAN VALENZUELA |
| Service/Power Release | 7/29/2020 | Approved | JUAN VALENZUELA |
| Final | 10/23/2020 | Corrections Issued | JUAN VALENZUELA |
| Verify Sprinkler Sign Off | 2/2/2022 | Approved | BOBBY KEY |
| Final | 4/8/2022 | OK to Issue CofO | BOBBY KEY |