8345 S COLEGIO DR 90045

Certificate Information: 8345 S COLEGIO DR 90045

Application / Permit
18014-20000-04686
Plan Check / Job No.
B18VN14021
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
79 SF FIRST FLOOR ADDITION TO (E) SINGLE FAMILY DWELLING WITH 5'-0" X 16'-6" PORCH AND 35'-0" X 29'-4" IRREGULAR SHAPED SECOND STORY ADDTION TO (E) SINGLE FAMILY DWELLING.
Permit Issued
Issued on 12/17/2018
Issuing Office
Valley
Current Status
CofO Issued on 4/19/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/16/2018 APPLICANT
Assigned to Plan Check Engineer 9/20/2018 SARKIS HARABEDIAN
Corrections Issued 9/26/2018 SARKIS HARABEDIAN
Quality Review Completed 10/1/2018 OMID HEDAYAT
Building Plans Picked Up 10/1/2018 APPLICANT
Green Plans Picked Up 10/12/2018 APPLICANT
Applicant returned to address corrections 11/29/2018 SARKIS HARABEDIAN
Plan Check Approved 12/12/2018 SARKIS HARABEDIAN
Issued 12/17/2018 LADBS
CofO in Progress 4/15/2022 RICHARD STEINBACH
Permit Finaled 4/19/2022 DANIEL ORRANTE
CofO Issued 4/19/2022 DANIEL ORRANTE
Permit Finaled 4/19/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/15/2018 MARKOS PEREZ-BRAN
Green Code Cleared 11/15/2018 MICHAEL AYERS
Low Impact Development Cleared 11/15/2018 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 11/15/2018 APEKSHYA BAJRACHARYA
Sewer availability Cleared 11/15/2018 MARKOS PEREZ-BRAN
GPI Written Notices Cleared 11/29/2018 SARKIS HARABEDIAN
Grading Pre-Inspection Cleared 11/29/2018 SARKIS HARABEDIAN

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor M F Construction & Design Inc; Lic. No.: 762001-B 2413 S 3RD AVENUE      ARCADIA, CA 91006
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/4/2019 Approved JUAN VALENZUELA
METHANE-Barrier 3/4/2019 Approved JUAN VALENZUELA
METHANE-Subgrade 3/4/2019 Approved JUAN VALENZUELA
PLUMBING-Rough 4/9/2019 Not Ready for Inspection JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 6/28/2019 Conditional Approval JUAN VALENZUELA
Deputy Drilled-In Anchors 7/25/2019 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 8/9/2019 Partial Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 8/9/2019 Approved JUAN VALENZUELA
Green Building Rough 8/9/2019 Not Ready for Inspection JUAN VALENZUELA
METHANE-Rough 8/9/2019 Approved JUAN VALENZUELA
PLUMBING-Rough 8/9/2019 Partial Approval JUAN VALENZUELA
Deputy Wood Construction 8/12/2019 Conditional Approval JUAN VALENZUELA
Deputy Drilled-In Anchors 8/14/2019 Approved JUAN VALENZUELA
Footing/Foundation/Slab 9/27/2019 Approved JUAN VALENZUELA
Deputy Wood Construction 10/1/2019 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 10/16/2019 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 10/24/2019 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 12/9/2019 Conditional Approval JUAN VALENZUELA
Interior/Exterior Lathing 1/14/2020 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 1/28/2020 Conditional Approval JUAN VALENZUELA
ELECTRICAL-Rough 1/28/2020 Approved JUAN VALENZUELA
Green Building Rough 1/28/2020 Not Ready for Inspection JUAN VALENZUELA
HVAC-Rough 1/28/2020 Conditional Approval JUAN VALENZUELA
PLUMBING-Rough 1/28/2020 Approved JUAN VALENZUELA
Insulation 2/5/2020 Conditional Approval JUAN VALENZUELA
Drywall Nailing 2/7/2020 Approved JUAN VALENZUELA
Green Building Rough 2/7/2020 Approved JUAN VALENZUELA
HVAC-Rough 2/7/2020 Approved JUAN VALENZUELA
Interior/Exterior Lathing 2/19/2020 Approved JUAN VALENZUELA
Shower Pan 2/19/2020 Approved JUAN VALENZUELA
HVAC-Final 4/24/2020 Corrections Issued JUAN VALENZUELA
PLUMBING-Final 4/24/2020 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Final 4/28/2020 Corrections Issued JUAN VALENZUELA
Smoke Detectors 4/28/2020 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 5/8/2020 Approved JUAN VALENZUELA
ELECTRICAL-Final 5/8/2020 Approved JUAN VALENZUELA
Final 5/8/2020 Corrections Issued JUAN VALENZUELA
Green Building Final 5/8/2020 Not Ready for Inspection JUAN VALENZUELA
HVAC-Final 5/8/2020 Not Ready for Inspection JUAN VALENZUELA
PLUMBING-Final 5/8/2020 Approved JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 5/8/2020 SGSOV Approved JUAN VALENZUELA
Final 7/29/2020 Corrections Issued JUAN VALENZUELA
Green Building Final 7/29/2020 Approved JUAN VALENZUELA
HVAC-Final 7/29/2020 Approved JUAN VALENZUELA
PLUMBING-Final 7/29/2020 Approved JUAN VALENZUELA
Service/Power Release 7/29/2020 Approved JUAN VALENZUELA
Final 10/23/2020 Corrections Issued JUAN VALENZUELA
Verify Sprinkler Sign Off 2/2/2022 Approved BOBBY KEY
Final 4/8/2022 OK to Issue CofO BOBBY KEY