14960 W HAMLIN ST 91411

Certificate Information: 14960 W HAMLIN ST 91411

Application / Permit
18014-20000-04416
Plan Check / Job No.
B18VN13195
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
18'3" X 29'2" EXPAND FAMILY ROOM, 4'10' X 9' 5" EXPAND OF LAUNDRY ROOM AND ENCLOSED 15'4" X 5' 10" (E) PORCH AND ADD 12' 4" X 4' NEW PORCH AT FRANT OF (E) SFD.
Permit Issued
Issued on 7/9/2019
Issuing Office
Valley
Current Status
CofO Issued on 10/12/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/3/2018 APPLICANT
Green Plans Picked Up 9/4/2018 APPLICANT
Assigned to Plan Check Engineer 9/6/2018 PINANK PATEL
Corrections Issued 9/8/2018 PINANK PATEL
Quality Review Completed 9/13/2018 OMID HEDAYAT
Building Plans Picked Up 9/18/2018 APPLICANT
Plan Check Approved 3/19/2019 PINANK PATEL
Issued 7/9/2019 LADBS
CofO in Progress 10/1/2021 MICHAEL TEMPLE
Permit Finaled 10/12/2021 MICHAEL SMITH
CofO Issued 10/12/2021 MICHAEL SMITH
Permit Finaled 10/12/2021 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/16/2018 MARKOS PEREZ-BRAN
Sewer availability Cleared 11/16/2018 MARKOS PEREZ-BRAN
Green Code Cleared 11/30/2018 MICHAEL AYERS
Low Impact Development Cleared 2/12/2019 RYAN HUDSON
Roof/Waste drainage to street Cleared 3/12/2019 JEANETTE VONG

Contact Information

Contractor Owner-Builder       ,
Engineer Chavez, Eduardo; Lic. No.: C76372 437 ARCADIA WAY      WALNUT, CA 91789

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/26/2019 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 1/16/2020 Partial Approval ARAM AVEDISIAN
Deputy Wood Construction 1/24/2020 Conditional Approval WILLIAM KUEHN
ELECTRICAL-Rough 2/24/2020 Corrections Issued MISAEL ESPARZA
HVAC-Rough 2/24/2020 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 2/24/2020 Approved MISAEL ESPARZA
Wood Frame 2/24/2020 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 4/13/2020 Approved MISAEL ESPARZA
HVAC-Rough 4/13/2020 Conditional Approval MISAEL ESPARZA
Wood Frame 4/13/2020 Approved MISAEL ESPARZA
Interior/Exterior Lathing 4/23/2020 Partial Approval MISAEL ESPARZA
Insulation 5/12/2020 Approved MISAEL ESPARZA
Drywall Nailing 5/19/2020 Partial Approval MISAEL ESPARZA
Green Building Rough 5/19/2020 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 5/21/2020 Corrections Issued JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 5/22/2020 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 5/27/2020 Approved MISAEL ESPARZA
Special/Order Compliance 5/27/2020 Approved MISAEL ESPARZA
Interior/Exterior Lathing 6/5/2020 Approved MISAEL ESPARZA
Shower Pan 6/5/2020 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 7/22/2020 Approved WILLIAM KUEHN
Drywall Nailing 7/22/2020 Approved WILLIAM KUEHN
Final 7/22/2020 Not Ready for Inspection WILLIAM KUEHN
Green Building Final 7/22/2020 Not Ready for Inspection WILLIAM KUEHN
SGSOV-Seismic Gas S/O Valve 7/22/2020 SGSOV Approved WILLIAM KUEHN
Smoke Detectors 7/22/2020 Not Ready for Inspection WILLIAM KUEHN
Final 1/5/2021 Corrections Issued JENNIFER RABUCHIN
Green Building Final 1/5/2021 Corrections Issued JENNIFER RABUCHIN
Smoke Detectors 1/5/2021 Approved JENNIFER RABUCHIN
Final 1/15/2021 Corrections Issued MATTHEW NELSON
Green Building Final 1/15/2021 Approved MATTHEW NELSON
Final 9/30/2021 OK to Issue CofO MICHAEL TEMPLE