4166 N KRAFT AVE 91604

Certificate Information: 4166 N KRAFT AVE 91604

Application / Permit
18014-20000-04290
Plan Check / Job No.
B18VN12824
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18'-1" x 18'-2" DET. GARAGE AND 13'-8" x 18'-5" ADDITION FOR (N) ACCESSORY DWELLING UNIT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 10/1/2020
Issuing Office
Valley
Current Status
CofO Issued on 6/5/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/30/2018 APPLICANT
Assigned to Plan Check Engineer 7/30/2018 MENA WASSEF
Corrections Issued 7/30/2018 MENA WASSEF
Plan Check Approved 1/17/2019 JENNIFER LEE
Issued 10/1/2020 APPLICANT
CofO in Progress 4/12/2021 THOMAS FINNILA
CofO Issued 6/5/2021 MICHAEL SMITH
Permit Finaled 6/5/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 7/31/2018 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 7/31/2018 MARKOS PEREZ-BRAN
Roof/Waste drainage to street Cleared 7/31/2018 MARKOS PEREZ-BRAN
Sewer availability Cleared 7/31/2018 MARKOS PEREZ-BRAN
ZI Cleared 7/31/2018 ANNA VIDAL
Construction near power lines Cleared 1/8/2019 RIDWAN HARDY

Contact Information

Contractor J I L Construction Services Inc; Lic. No.: 938786-B 1400 EAST 61 STREET      LOS ANGELES, CA 90001
Engineer Melendrez, Edgar P; Lic. No.: C64146 11251 PIONEER BLVD APT A-8      NORWALK, CA 90650

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/13/2020 Not Ready for Inspection THOMAS FINNILA
Footing/Foundation/Slab 10/13/2020 Corrections Issued THOMAS FINNILA
Underground Mechanical 10/13/2020 Partial Approval THOMAS FINNILA
Footing/Foundation/Slab 10/28/2020 Conditional Approval THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 11/2/2020 Conditional Approval THOMAS FINNILA
ELECTRICAL-Rough 11/25/2020 Conditional Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 11/25/2020 Partial Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 12/2/2020 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 12/2/2020 Conditional Approval THOMAS FINNILA
BUILDING-Rough-Frame 12/8/2020 Partial Approval THOMAS FINNILA
Green Building Rough 12/8/2020 Approved THOMAS FINNILA
Interior/Exterior Lathing 12/14/2020 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 12/18/2020 Approved BEAU COLLINS
Insulation 12/18/2020 Approved BEAU COLLINS
Drywall Nailing 12/28/2020 Approved THOMAS FINNILA
Shower Pan 12/28/2020 Approved THOMAS FINNILA
Final 3/23/2021 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 3/23/2021 Approved THOMAS FINNILA
Green Building Final 3/23/2021 Corrections Issued THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 3/23/2021 SGSOV Not Ready THOMAS FINNILA
Final 4/12/2021 Conditional Approval THOMAS FINNILA
Green Building Final 4/12/2021 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 4/12/2021 SGSOV Approved THOMAS FINNILA
Smoke Detectors 4/12/2021 Approved THOMAS FINNILA