16907 W BOLLINGER DR 90272
Certificate Information: 16907 W BOLLINGER DR 90272
- Application / Permit
- 18014-20000-04218
- Plan Check / Job No.
- B18VN12606
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ENCLOSE (E) (2'-8" X 12') CONVERED PORCH & (22' X 35'-6") IRREGULAR SHAPED 2ND STORY ADDITION TO (E) 2 STORY SFD. REMODEL (E) SFD FOR (N) FIXTURES AND FINISHES AT KITCHEN, LIVING ROOM, AND BATHROOMS.
- Permit Issued
- Issued on 12/28/2018
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 8/25/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/25/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 8/23/2018 | RAPHAEL ROSAS |
| Corrections Issued | 8/25/2018 | RAPHAEL ROSAS |
| Quality Review Completed | 8/27/2018 | OMID HEDAYAT |
| Building Plans Picked Up | 8/31/2018 | APPLICANT |
| Green Plans Picked Up | 8/31/2018 | APPLICANT |
| Applicant returned to address corrections | 12/3/2018 | RAPHAEL ROSAS |
| Plan Check Approved | 12/11/2018 | RAPHAEL ROSAS |
| Issued | 12/28/2018 | LADBS |
| CofO in Progress | 8/18/2021 | JOHN MATTILLO |
| Permit Finaled | 8/25/2021 | BRUCE TODD |
| CofO Issued | 8/25/2021 | BRUCE TODD |
| Permit Finaled | 8/25/2021 | BRUCE TODD |
Permit Application Clearance Information
| Coastal Zone | Cleared | 10/1/2018 | MARITZA PRZEKOP |
| Miscellaneous | Cleared | 10/1/2018 | MARITZA PRZEKOP |
| Low Impact Development | Cleared | 12/7/2018 | MITESH PATEL |
| Eng Process Fee Ord 176,300 | Cleared | 12/10/2018 | RUDY TERRIQUEZ. |
| Green Code | Cleared | 12/10/2018 | DAVID MATSON |
| Roof/Waste drainage to street | Cleared | 12/10/2018 | RUDY TERRIQUEZ. |
| Sewer availability | Cleared | 12/10/2018 | RUDY TERRIQUEZ. |
| GPI Written Notices | Cleared | 12/11/2018 | RAPHAEL ROSAS |
| Grading Pre-Inspection | Cleared | 12/11/2018 | RAPHAEL ROSAS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rhee, Kyle; Lic. No.: C78215 | 3855 W 7TH ST #304 LOS ANGELES, CA 90005 |
Inspector Information
| ROBERT GARTH, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN MATTILLO, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO RIVERA, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| EUSEBIO GUZMAN, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL REECE, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDREW BEELI, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/8/2019 | Conditional Approval | JOHN MATTILLO |
| Excavation/Setback/Form/Re-Bar | 8/13/2019 | Approved | BRENDAN LOONEY |
| Footing/Foundation/Slab | 8/13/2019 | Approved | BRENDAN LOONEY |
| Deputy Reinf. Concrete | 8/14/2019 | Approved | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2019 | Partial Approval | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/6/2019 | Corrections Issued | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2019 | Approved | BRENDAN LOONEY |
| PLUMBING-Rough | 10/9/2019 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 11/19/2019 | Conditional Approval | BRENDAN LOONEY |
| ELECTRICAL-Rough | 11/19/2019 | Approved | BRENDAN LOONEY |
| Green Building Rough | 11/19/2019 | Approved | BRENDAN LOONEY |
| HVAC-Rough | 11/19/2019 | Corrections Issued | BRENDAN LOONEY |
| Insulation | 11/27/2019 | Not Ready for Inspection | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2019 | Corrections Issued | BRENDAN LOONEY |
| Insulation | 12/3/2019 | Conditional Approval | BRENDAN LOONEY |
| Deputy Wood Construction | 12/5/2019 | Approved | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2019 | Approved | BRENDAN LOONEY |
| HVAC-Rough | 12/10/2019 | Partial Approval | BRENDAN LOONEY |
| Drywall Nailing | 12/19/2019 | Conditional Approval | BRENDAN LOONEY |
| Interior/Exterior Lathing | 12/19/2019 | Approved | BRENDAN LOONEY |
| Shower Pan | 1/14/2020 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 1/21/2020 | Approved | BRENDAN LOONEY |
| Deputy Wood Construction | 3/5/2020 | Conditional Approval | BRENDAN LOONEY |
| Interior/Exterior Lathing | 3/25/2020 | Partial Approval | MARIAN PODPORA |
| Interior/Exterior Lathing | 3/27/2020 | Partial Approval | MARIAN PODPORA |
| Interior/Exterior Lathing | 7/28/2020 | Approved | JOHN MATTILLO |
| Wood Frame | 9/9/2020 | Approved | JOHN MATTILLO |
| ELECTRICAL-Final | 11/17/2020 | Corrections Issued | JOHN MATTILLO |
| BUILDING-Rough-Frame | 7/19/2021 | Approved | JOHN MATTILLO |
| Drywall Nailing | 7/19/2021 | Approved | JOHN MATTILLO |
| Final | 7/19/2021 | Conditional Approval | JOHN MATTILLO |
| Green Building Final | 7/19/2021 | Approved | JOHN MATTILLO |
| SGSOV-Seismic Gas S/O Valve | 7/19/2021 | SGSOV Approved | JOHN MATTILLO |
| Smoke Detectors | 7/19/2021 | Approved | JOHN MATTILLO |