11617 W VALERIO ST 91605

Certificate Information: 11617 W VALERIO ST 91605

Application / Permit
18014-20000-04101
Plan Check / Job No.
B18VN12276
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) RECREATION ROOM TO ACCESSORY DWELLING UNIT PER AB494 & SB229 AND EXPAND LIVING ROOM (3' X 21'-8") PER ENG'R DESIGN
Permit Issued
Issued on 7/9/2020
Issuing Office
Valley
Current Status
CofO Issued on 8/15/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/19/2018 APPLICANT
Assigned to Plan Check Engineer 8/30/2018 NILOOFAR MEHRAIN
Green Plans Picked Up 9/6/2018 APPLICANT
Corrections Issued 9/17/2018 NILOOFAR MEHRAIN
Quality Review Completed 9/18/2018 CHON CHIO KUO
Building Plans Picked Up 9/19/2018 APPLICANT
Applicant returned to address corrections 11/13/2019 NILOOFAR MEHRAIN
Plan Check Approved 2/3/2020 NILOOFAR MEHRAIN
Issued 7/9/2020 APPLICANT
CofO in Progress 1/13/2021 DANIEL DREW
CofO Issued 8/15/2022 DANIEL ORRANTE
Permit Finaled 8/15/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/1/2019 LEE GUILBEAUX
Green Code Cleared 11/19/2019 MICHAEL AYERS
Construction near power lines Cleared 1/4/2020 RIDWAN HARDY
Construction within easement Cleared 1/4/2020 RIDWAN HARDY
Hydrant and Access approval Cleared 1/28/2020 GEORGE SUCHAND
Eng Process Fee Ord 176,300 Cleared 2/3/2020 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 2/3/2020 LEE GUILBEAUX
Sewer availability Cleared 2/3/2020 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Papazyan,, Andranik; Lic. No.: C56824 635 W COLORADO ST STE 104      GLENDALE, CA 91204

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/17/2020 Approved RAYMOND KEHOE
Footing/Foundation/Slab 7/20/2020 Approved DANIEL DREW
PLUMBING-Rough 8/5/2020 Approved MATTHEW NELSON
BUILDING-Rough-Frame 8/20/2020 Corrections Issued DANIEL DREW
ELECTRICAL-Rough 8/20/2020 Corrections Issued DANIEL DREW
Green Building Rough 8/20/2020 Approved DANIEL DREW
HVAC-Rough 8/20/2020 Corrections Issued DANIEL DREW
BUILDING-Rough-Frame 9/1/2020 Approved DANIEL DREW
ELECTRICAL-Rough 9/1/2020 Approved DANIEL DREW
HVAC-Rough 9/1/2020 Approved DANIEL DREW
Insulation 9/24/2020 Approved DANIEL DREW
Interior/Exterior Lathing 9/24/2020 Approved DANIEL DREW
Drywall Nailing 9/30/2020 Approved DANIEL DREW
Final 12/14/2020 Corrections Issued MATTHEW NELSON
Green Building Final 12/14/2020 Corrections Issued MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 12/14/2020 SGSOV Not Ready MATTHEW NELSON
Smoke Detectors 12/14/2020 Approved MATTHEW NELSON
Final 1/5/2021 Not Ready for Inspection DANIEL DREW
Green Building Final 1/5/2021 Not Ready for Inspection DANIEL DREW
SGSOV-Seismic Gas S/O Valve 1/5/2021 SGSOV Approved DANIEL DREW
ELECTRICAL-Final 1/12/2021 Approved DANIEL DREW
Final 1/12/2021 OK to Issue CofO DANIEL DREW
Green Building Final 1/12/2021 Approved DANIEL DREW
HVAC-Final 1/12/2021 Approved DANIEL DREW
PLUMBING-Final 1/12/2021 Approved DANIEL DREW