2017 S CORINTH AVE 90025
Certificate Information: 2017 S CORINTH AVE 90025
- Application / Permit
- 18014-20000-04053
- Plan Check / Job No.
- B18VN12167
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- 48' 2" x 26' 6" IRRGULAR-SHAPED ADDITION & REMODEL SINGLE FAMILY DWELLING. ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 1/15/2019
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 1/15/2019
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/17/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 7/18/2018 | MENA WASSEF |
| Corrections Issued | 7/19/2018 | MENA WASSEF |
| Building Plans Picked Up | 7/20/2018 | APPLICANT |
| Applicant returned to address corrections | 7/24/2018 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 8/31/2018 | MENA WASSEF |
| Plan Check Approved | 12/12/2018 | ARTIN ZARUKIAN |
| Issued | 1/15/2019 | LADBS |
| CofO in Progress | 8/29/2019 | ROBERT SHELLY |
| CofO Issued-Status Void | 9/5/2019 | VINCENT COTTON |
| Permit Finaled-Status Void | 9/5/2019 | VINCENT COTTON |
| Re-Activate Permit | 1/6/2020 | VINCENT COTTON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/23/2018 | MICHAEL CASTILLO |
| Roof/Waste drainage to street | Cleared | 7/23/2018 | MICHAEL CASTILLO |
| Sewer availability | Cleared | 7/23/2018 | MICHAEL CASTILLO |
| ZA Case | Cleared | 7/23/2018 | EDBER MACEDO |
| ZA Case | Cleared | 7/23/2018 | EDBER MACEDO |
Contact Information
| Contractor | Cirkic Asmir; Lic. No.: 996302-B | 26820 PAMELA DRIVE SANTA CLARITA, CA 91351 |
| Engineer | Guivatchian, Mohammad; Lic. No.: C36510 | 4720 DEGOVIA AVENUE WOODLAND HILLS, CA 91364 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/11/2019 | Partial Approval | ANTHONY MCDOWALL |
| BUILDING-Rough-Frame | 3/13/2019 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2019 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Rough | 5/3/2019 | Not Ready for Inspection | ROBERT SHELLY |
| ELECTRICAL-Rough | 5/8/2019 | Approved | EVAN COOPER |
| PLUMBING-Rough | 5/8/2019 | Approved | EVAN COOPER |
| HVAC-Rough | 5/9/2019 | Corrections Issued | EVAN COOPER |
| Interior/Exterior Lathing | 5/24/2019 | Not Ready for Inspection | ROBERT SHELLY |
| Insulation | 6/4/2019 | Approved | EVAN COOPER |
| Sewer | 6/5/2019 | Not Ready for Inspection | EVAN COOPER |
| Drywall Nailing | 6/13/2019 | Partial Approval | EVAN COOPER |
| Green Building Rough | 6/13/2019 | Not Ready for Inspection | EVAN COOPER |
| Special/Order Compliance | 7/3/2019 | Partial Approval | ROBERT SHELLY |
| Special/Order Compliance | 7/10/2019 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 7/12/2019 | Partial Approval | ROBERT SHELLY |
| BUILDING-Rough-Frame | 7/19/2019 | Partial Inspection | ROBERT SHELLY |
| Drywall Nailing | 7/19/2019 | Approved | ROBERT SHELLY |
| Final | 7/19/2019 | Not Ready for Inspection | ROBERT SHELLY |
| Footing/Foundation/Slab | 7/19/2019 | Approved | ROBERT SHELLY |
| Green Building Final | 7/19/2019 | Approved | ROBERT SHELLY |
| Green Building Rough | 7/19/2019 | Approved | ROBERT SHELLY |
| MERV13>=Final | 7/19/2019 | Not Ready for Inspection | ROBERT SHELLY |
| MERV13>=Rough | 7/19/2019 | Not Ready for Inspection | ROBERT SHELLY |
| SGSOV-Seismic Gas S/O Valve | 7/19/2019 | SGSOV Gas Company | ROBERT SHELLY |
| Smoke Detectors | 7/19/2019 | Approved | ROBERT SHELLY |
| BUILDING-Rough-Frame | 7/23/2019 | Approved | ROBERT SHELLY |
| Final | 7/23/2019 | Not Ready for Inspection | ROBERT SHELLY |
| MERV13>=Final | 7/23/2019 | Corrections Issued | ROBERT SHELLY |
| MERV13>=Rough | 7/23/2019 | Approved | ROBERT SHELLY |
| Final | 8/22/2019 | Not Ready for Inspection | ROBERT SHELLY |
| MERV13>=Final | 8/22/2019 | Approved | ROBERT SHELLY |
| Final | 8/26/2019 | Conditional Approval | ROBERT SHELLY |