10033 W VALLEY SPRING LANE 91602
Certificate Information: 10033 W VALLEY SPRING LANE 91602
- Application / Permit
- 18014-20000-03996
- Plan Check / Job No.
- B18VN11991
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL - REMOVE (E) PATIO AND ADD 7'-8" X 2'-5" ENTRY AND 1'-10" X 6'-2" TO EXTEND LAUNDRY ROOM, ADD 10'-0" X 18'-4" PATIO ON THE FIRST FLOOR TO CONNECT (E) GARAGE; ADD 6'-4" X 21'-0" TO EXTEND (E) MASTER BEDROOM AND ADD 19'-0" X 20'-6" FOR (2) NEW BEDROOMS, ADD IRREGULAR 11'-6" X 39'-10" AND 5'-0" X 18'-10" BALCONIES FOR BEDROOMS; ADD 31'-10" X 48'-0" IRREGULAR RAISED DECK; REMODEL THROUGHOUT (E) 2-STORY SFD. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 4/1/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/13/2018 | APPLICANT |
| Green Plans Picked Up | 8/8/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 8/16/2018 | JENNIFER LEE |
| Corrections Issued | 8/24/2018 | JENNIFER LEE |
| Quality Review Completed | 8/24/2018 | STEVEN KIM |
| Applicant returned to address corrections | 1/24/2019 | JENNIFER LEE |
| Applicant returned to address corrections | 2/25/2019 | JENNIFER LEE |
| Plan Check Approved | 3/12/2019 | JENNIFER LEE |
| Issued | 4/1/2019 | LADBS |
| Building Plans Picked Up | 3/23/2021 | APPLICANT |
| CofO in Progress | 6/27/2022 | THOMAS FINNILA |
| CofO Issued | 8/17/2022 | MICHAEL SMITH |
| Permit Finaled | 8/17/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 10/18/2018 | OSCAR CASTRO |
| Construction within easement | Cleared | 10/18/2018 | OSCAR CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 12/11/2018 | RUDY TERRIQUEZ. |
| Sewer availability | Cleared | 12/11/2018 | RUDY TERRIQUEZ. |
| ZA Case | Cleared | 12/11/2018 | DAISY BENICIA |
| ZI | Cleared | 12/11/2018 | DAISY BENICIA |
| Green Code | Cleared | 12/20/2018 | DAVID MATSON |
| Low Impact Development | Cleared | 2/21/2019 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 2/21/2019 | ZIXUAN CHEN |
Contact Information
| Architect | Yotnegparian, Alain Levon; Lic. No.: C26374 | 11541 DONA PEPITA PLACE STUDIO CITY, CA 91604 |
| Contractor | Mc Kernan Inspections And Construction; Lic. No.: 935880-B | 23679 CALABASAS ROAD SUITE 804 CALABASAS, CA 91302 |
| Engineer | Babayan, Raffi Samuel; Lic. No.: C72168 | 1140 N COLUMBUS AVE 112 GLENDALE, CA 91202 |
| Engineer | Koh, William Kim; Lic. No.: S3473 | 5695 STARWOOD CT WESTLAKE VILLAGE, CA 91362 |
| Geologist | Byer, John W; Lic. No.: EG883 | 1649 PUEBLA DRIVE GLENDALE, CA 91207 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 7/25/2019 | Partial Approval | JEFFREY PARD |
| Deputy Drilled-In Anchors | 8/30/2019 | Approved | JEFFREY PARD |
| Deputy Reinf. Concrete | 9/13/2019 | Approved | JEFFREY PARD |
| Footing/Foundation/Slab | 9/17/2019 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 9/20/2019 | Partial Approval | JEFFREY PARD |
| Deputy Drilled-In Anchors | 10/10/2019 | Approved | RAYMOND KEHOE |
| Deputy Reinf. Concrete | 10/10/2019 | Approved | RAYMOND KEHOE |
| Footing/Foundation/Slab | 10/11/2019 | Partial Approval | JEFFREY PARD |
| Deputy Reinf. Concrete | 11/12/2019 | Approved | JEFFREY PARD |
| Footing/Foundation/Slab | 11/14/2019 | Approved | JEFFREY PARD |
| Deputy Reinf. Concrete | 11/26/2019 | Approved | DANIEL ORRANTE |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2020 | Partial Approval | ARAM AVEDISIAN |
| Piling/Pier/Caisson | 7/28/2020 | Corrections Issued | THOMAS FINNILA |
| Rough-Elec/Plmb/HVAC | 10/2/2020 | Partial Approval | THOMAS FINNILA |
| Wood Frame | 10/2/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2020 | Partial Approval | THOMAS FINNILA |
| Rough-Elec/Plmb/HVAC | 10/6/2020 | Corrections Issued | THOMAS FINNILA |
| Rough-Elec/Plmb/HVAC | 10/13/2020 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 10/28/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Piling/Pier/Caisson | 11/4/2020 | Conditional Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 12/3/2020 | Conditional Approval | THOMAS FINNILA |
| Interior/Exterior Lathing | 12/11/2020 | Partial Approval | THOMAS FINNILA |
| Interior/Exterior Lathing | 1/8/2021 | Approved | THOMAS FINNILA |
| Wood Frame | 1/8/2021 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 1/21/2021 | Approved | THOMAS FINNILA |
| Drywall Nailing | 1/21/2021 | Approved | THOMAS FINNILA |
| Green Building Rough | 1/21/2021 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 1/21/2021 | Approved | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 2/3/2021 | Partial Approval | THOMAS FINNILA |
| Shower Pan | 2/17/2021 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 3/9/2021 | Partial Approval | ARAM AVEDISIAN |
| Deputy Steel/Welding | 8/6/2021 | Conditional Approval | MICHAEL PELHAM |
| Wood Frame | 9/30/2021 | Corrections Issued | THOMAS FINNILA |
| ELECTRICAL-Rough | 10/4/2021 | Conditional Approval | CALEB MEISTER |
| PLUMBING-Rough | 10/4/2021 | Corrections Issued | CALEB MEISTER |
| Wood Frame | 10/4/2021 | Not Ready for Inspection | CALEB MEISTER |
| Gas Test | 10/25/2021 | Approved | ARAM AVEDISIAN |
| Final | 2/15/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Green Building Final | 2/15/2022 | Not Ready for Inspection | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 2/15/2022 | SGSOV Not Ready | THOMAS FINNILA |
| Smoke Detectors | 2/15/2022 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 2/23/2022 | Not Ready for Inspection | ARAM AVEDISIAN |
| ELECTRICAL-Final | 3/1/2022 | Conditional Approval | THOMAS FINNILA |
| HVAC-Final | 3/1/2022 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 3/23/2022 | Not Ready for Inspection | DAVID MATSON |
| ELECTRICAL-Final | 3/29/2022 | Approved | THOMAS FINNILA |
| Final | 4/12/2022 | Corrections Issued | DAVID MATSON |
| Green Building Final | 4/12/2022 | Approved | DAVID MATSON |
| SGSOV-Seismic Gas S/O Valve | 4/12/2022 | SGSOV Approved | DAVID MATSON |
| Final | 4/20/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Final | 6/17/2022 | Conditional Approval | THOMAS FINNILA |
| Final | 6/24/2022 | OK to Issue CofO | THOMAS FINNILA |