10033 W VALLEY SPRING LANE 91602

Certificate Information: 10033 W VALLEY SPRING LANE 91602

Application / Permit
18014-20000-03996
Plan Check / Job No.
B18VN11991
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL - REMOVE (E) PATIO AND ADD 7'-8" X 2'-5" ENTRY AND 1'-10" X 6'-2" TO EXTEND LAUNDRY ROOM, ADD 10'-0" X 18'-4" PATIO ON THE FIRST FLOOR TO CONNECT (E) GARAGE; ADD 6'-4" X 21'-0" TO EXTEND (E) MASTER BEDROOM AND ADD 19'-0" X 20'-6" FOR (2) NEW BEDROOMS, ADD IRREGULAR 11'-6" X 39'-10" AND 5'-0" X 18'-10" BALCONIES FOR BEDROOMS; ADD 31'-10" X 48'-0" IRREGULAR RAISED DECK; REMODEL THROUGHOUT (E) 2-STORY SFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 4/1/2019
Issuing Office
Valley
Current Status
CofO Issued on 8/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/13/2018 APPLICANT
Green Plans Picked Up 8/8/2018 APPLICANT
Assigned to Plan Check Engineer 8/16/2018 JENNIFER LEE
Corrections Issued 8/24/2018 JENNIFER LEE
Quality Review Completed 8/24/2018 STEVEN KIM
Applicant returned to address corrections 1/24/2019 JENNIFER LEE
Applicant returned to address corrections 2/25/2019 JENNIFER LEE
Plan Check Approved 3/12/2019 JENNIFER LEE
Issued 4/1/2019 LADBS
Building Plans Picked Up 3/23/2021 APPLICANT
CofO in Progress 6/27/2022 THOMAS FINNILA
CofO Issued 8/17/2022 MICHAEL SMITH
Permit Finaled 8/17/2022 MICHAEL SMITH

Permit Application Clearance Information

Construction near power lines Cleared 10/18/2018 OSCAR CASTRO
Construction within easement Cleared 10/18/2018 OSCAR CASTRO
Eng Process Fee Ord 176,300 Cleared 12/11/2018 RUDY TERRIQUEZ.
Sewer availability Cleared 12/11/2018 RUDY TERRIQUEZ.
ZA Case Cleared 12/11/2018 DAISY BENICIA
ZI Cleared 12/11/2018 DAISY BENICIA
Green Code Cleared 12/20/2018 DAVID MATSON
Low Impact Development Cleared 2/21/2019 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 2/21/2019 ZIXUAN CHEN

Contact Information

Architect Yotnegparian, Alain Levon; Lic. No.: C26374 11541 DONA PEPITA PLACE      STUDIO CITY, CA 91604
Contractor Mc Kernan Inspections And Construction; Lic. No.: 935880-B 23679 CALABASAS ROAD SUITE 804      CALABASAS, CA 91302
Engineer Babayan, Raffi Samuel; Lic. No.: C72168 1140 N COLUMBUS AVE 112      GLENDALE, CA 91202
Engineer Koh, William Kim; Lic. No.: S3473 5695 STARWOOD CT      WESTLAKE VILLAGE, CA 91362
Geologist Byer, John W; Lic. No.: EG883 1649 PUEBLA DRIVE      GLENDALE, CA 91207

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/25/2019 Partial Approval JEFFREY PARD
Deputy Drilled-In Anchors 8/30/2019 Approved JEFFREY PARD
Deputy Reinf. Concrete 9/13/2019 Approved JEFFREY PARD
Footing/Foundation/Slab 9/17/2019 Not Ready for Inspection CHRISTOPHE COCHRAN
Footing/Foundation/Slab 9/20/2019 Partial Approval JEFFREY PARD
Deputy Drilled-In Anchors 10/10/2019 Approved RAYMOND KEHOE
Deputy Reinf. Concrete 10/10/2019 Approved RAYMOND KEHOE
Footing/Foundation/Slab 10/11/2019 Partial Approval JEFFREY PARD
Deputy Reinf. Concrete 11/12/2019 Approved JEFFREY PARD
Footing/Foundation/Slab 11/14/2019 Approved JEFFREY PARD
Deputy Reinf. Concrete 11/26/2019 Approved DANIEL ORRANTE
Floor/Roof Diaphrgm/Shear Wall 3/19/2020 Partial Approval ARAM AVEDISIAN
Piling/Pier/Caisson 7/28/2020 Corrections Issued THOMAS FINNILA
Rough-Elec/Plmb/HVAC 10/2/2020 Partial Approval THOMAS FINNILA
Wood Frame 10/2/2020 Not Ready for Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/6/2020 Partial Approval THOMAS FINNILA
Rough-Elec/Plmb/HVAC 10/6/2020 Corrections Issued THOMAS FINNILA
Rough-Elec/Plmb/HVAC 10/13/2020 Approved THOMAS FINNILA
Interior/Exterior Lathing 10/28/2020 Not Ready for Inspection THOMAS FINNILA
Piling/Pier/Caisson 11/4/2020 Conditional Approval THOMAS FINNILA
BUILDING-Rough-Frame 12/3/2020 Conditional Approval THOMAS FINNILA
Interior/Exterior Lathing 12/11/2020 Partial Approval THOMAS FINNILA
Interior/Exterior Lathing 1/8/2021 Approved THOMAS FINNILA
Wood Frame 1/8/2021 Approved THOMAS FINNILA
BUILDING-Rough-Frame 1/21/2021 Approved THOMAS FINNILA
Drywall Nailing 1/21/2021 Approved THOMAS FINNILA
Green Building Rough 1/21/2021 Approved THOMAS FINNILA
Interior/Exterior Lathing 1/21/2021 Approved THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 2/3/2021 Partial Approval THOMAS FINNILA
Shower Pan 2/17/2021 Approved THOMAS FINNILA
Interior/Exterior Lathing 3/9/2021 Partial Approval ARAM AVEDISIAN
Deputy Steel/Welding 8/6/2021 Conditional Approval MICHAEL PELHAM
Wood Frame 9/30/2021 Corrections Issued THOMAS FINNILA
ELECTRICAL-Rough 10/4/2021 Conditional Approval CALEB MEISTER
PLUMBING-Rough 10/4/2021 Corrections Issued CALEB MEISTER
Wood Frame 10/4/2021 Not Ready for Inspection CALEB MEISTER
Gas Test 10/25/2021 Approved ARAM AVEDISIAN
Final 2/15/2022 Not Ready for Inspection THOMAS FINNILA
Green Building Final 2/15/2022 Not Ready for Inspection THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 2/15/2022 SGSOV Not Ready THOMAS FINNILA
Smoke Detectors 2/15/2022 Approved THOMAS FINNILA
ELECTRICAL-Final 2/23/2022 Not Ready for Inspection ARAM AVEDISIAN
ELECTRICAL-Final 3/1/2022 Conditional Approval THOMAS FINNILA
HVAC-Final 3/1/2022 Approved THOMAS FINNILA
ELECTRICAL-Final 3/23/2022 Not Ready for Inspection DAVID MATSON
ELECTRICAL-Final 3/29/2022 Approved THOMAS FINNILA
Final 4/12/2022 Corrections Issued DAVID MATSON
Green Building Final 4/12/2022 Approved DAVID MATSON
SGSOV-Seismic Gas S/O Valve 4/12/2022 SGSOV Approved DAVID MATSON
Final 4/20/2022 Not Ready for Inspection THOMAS FINNILA
Final 6/17/2022 Conditional Approval THOMAS FINNILA
Final 6/24/2022 OK to Issue CofO THOMAS FINNILA