14311 W WEDDINGTON ST 91401

Certificate Information: 14311 W WEDDINGTON ST 91401

Application / Permit
18014-20000-03769
Plan Check / Job No.
B18VN11419
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 2ND FLOOR TO (E) 21'6" HIGH GARAGE AND RECROOM TO CREATE AN ADU UNIT AT 2ND FLOOR PER AB 494 AND SB 229. SEE COMMENT. (Convert recroom to ADU as well, Garage to remain)
Permit Issued
Issued on 12/5/2019
Issuing Office
Valley
Current Status
CofO Issued on 3/21/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/3/2018 APPLICANT
Assigned to Plan Check Engineer 8/15/2018 MENA WASSEF
Corrections Issued 8/28/2018 MENA WASSEF
Quality Review Completed 8/29/2018 CHON CHIO KUO
Building Plans Picked Up 8/29/2018 APPLICANT
Green Plans Picked Up 3/29/2019 APPLICANT
Applicant returned to address corrections 6/26/2019 RODNEY SAMIIAN
Plan Check Approved 10/16/2019 RODNEY SAMIIAN
Issued 12/5/2019 LADBS
CofO in Progress 2/27/2024 RYAN SALAZAR
Permit Finaled 3/21/2024 RUBEN SALAS
CofO Issued 3/21/2024 RUBEN SALAS
Permit Finaled 3/21/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/1/2019 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 4/1/2019 ELAINE LEI
Sewer availability Cleared 4/1/2019 ELAINE LEI
Hydrant and Access approval Cleared 6/11/2019 GEORGE SUCHAND
Low Impact Development Cleared 6/12/2019 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 6/12/2019 GUILLERMO PETRA
Green Code Cleared 8/20/2019 PARISA ZAHABI

Contact Information

Contractor Owner-Builder       ,
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/28/2020 Approved MISAEL ESPARZA
PLUMBING-Rough 7/13/2020 No Access for Inspection MISAEL ESPARZA
PLUMBING-Rough 11/16/2023 Partial Approval RYAN SALAZAR
BUILDING-Rough-Frame 12/7/2023 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 12/7/2023 Approved RYAN SALAZAR
Green Building Rough 12/7/2023 Not Ready for Inspection RYAN SALAZAR
BUILDING-Rough-Frame 12/18/2023 Corrections Issued RYAN SALAZAR
ELECTRICAL-Rough 12/18/2023 Approved RYAN SALAZAR
Green Building Rough 12/18/2023 Approved RYAN SALAZAR
HVAC-Rough 12/18/2023 Approved RYAN SALAZAR
PLUMBING-Rough 12/18/2023 Not Ready for Inspection RYAN SALAZAR
BUILDING-Rough-Frame 12/21/2023 Approved RYAN SALAZAR
Gas Test 12/21/2023 Approved RYAN SALAZAR
PLUMBING-Rough 12/21/2023 Approved RYAN SALAZAR
Insulation 12/27/2023 Corrections Issued JOHN COLEMAN
Interior/Exterior Lathing 12/27/2023 Partial Approval JOHN COLEMAN
Shower Pan 12/27/2023 Approved JOHN COLEMAN
Insulation 12/29/2023 Approved RYAN SALAZAR
Drywall Nailing 1/3/2024 Approved RYAN SALAZAR
Final 2/8/2024 Partial Inspection RYAN SALAZAR
Footing/Foundation/Slab 2/8/2024 Approved RYAN SALAZAR
Green Building Final 2/8/2024 Not Ready for Inspection RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 2/8/2024 SGSOV Approved RYAN SALAZAR
Service/Power Release 2/8/2024 Approved RYAN SALAZAR
Smoke Detectors 2/8/2024 Approved RYAN SALAZAR
Final 2/21/2024 Not Ready for Inspection RYAN SALAZAR
Green Building Final 2/21/2024 Approved RYAN SALAZAR
Final 2/23/2024 OK to Issue CofO RYAN SALAZAR