4368 N IRVINE AVE 91604
Certificate Information: 4368 N IRVINE AVE 91604
- Application / Permit
- 18014-20000-03735
- Plan Check / Job No.
- B18VN11333
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 9' X 19'11" ADDITION AND CONVERT (E) 20' X 19' 11" DET. GARAGE TO ADU PER AB 494 AND SB 229. ADD 2' X 19'11" STORAGE. ALL WORK PER ENGINEER.
- Permit Issued
- Issued on 1/6/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/4/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/2/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 7/2/2018 | MENA WASSEF |
| Corrections Issued | 7/3/2018 | MENA WASSEF |
| Building Plans Picked Up | 7/5/2018 | APPLICANT |
| Applicant returned to address corrections | 8/26/2019 | YAQUB MIRZA |
| Plan Check Approved | 9/4/2019 | PINANK PATEL |
| Issued | 1/6/2020 | LADBS |
| CofO in Progress | 11/13/2020 | THOMAS FINNILA |
| Permit Finaled | 9/4/2021 | MICHAEL SMITH |
| CofO Issued | 9/4/2021 | MICHAEL SMITH |
| Permit Finaled | 9/4/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| ZA Case | Cleared | 7/5/2018 | ANNA VIDAL |
| Address approval | Cleared | 8/16/2018 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 8/16/2018 | JOHN LIN |
| Sewer availability | Cleared | 8/16/2018 | JOHN LIN |
| Hydrant and Access approval | Cleared | 8/26/2019 | GILBERT URREA |
| Low Impact Development | Cleared | 8/29/2019 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 8/29/2019 | ERIK BEASLEY |
Contact Information
| Contractor | T L B Construction Corp; Lic. No.: 967633-B | 2029 VERDUGO ROAD SUITE 260 MONTROSE, CA 91020 |
| Engineer | Loayza,, Miguel Antonio; Lic. No.: C26290 | 20062 MERRIDY STREET CHATSWORTH, CA 91311 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/14/2020 | Corrections Issued | JEFFREY PARD |
| Footing/Foundation/Slab | 2/21/2020 | Approved | JEFFREY PARD |
| Underground Mechanical | 2/21/2020 | Partial Approval | JEFFREY PARD |
| BUILDING-Rough-Frame | 5/20/2020 | Approved | JEFFREY PARD |
| ELECTRICAL-Rough | 5/20/2020 | Approved | JEFFREY PARD |
| Green Building Rough | 5/20/2020 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 5/20/2020 | Approved | JEFFREY PARD |
| HVAC-Rough | 6/16/2020 | Conditional Approval | THOMAS FINNILA |
| Insulation | 6/16/2020 | Approved | THOMAS FINNILA |
| Drywall Nailing | 6/24/2020 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 8/12/2020 | Partial Inspection | THOMAS FINNILA |
| Service/Power Release | 8/12/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Shower Pan | 8/12/2020 | Corrections Issued | THOMAS FINNILA |
| Interior/Exterior Lathing | 8/24/2020 | Approved | THOMAS FINNILA |
| Shower Pan | 8/24/2020 | Approved | THOMAS FINNILA |
| Sewer | 8/31/2020 | Approved | THOMAS FINNILA |
| Final | 10/7/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Green Building Final | 10/7/2020 | Not Ready for Inspection | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 10/7/2020 | SGSOV Not Ready | THOMAS FINNILA |
| Service/Power Release | 10/7/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Smoke Detectors | 10/7/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Service/Power Release | 10/9/2020 | Not Ready for Inspection | DAVID MATSON |
| Service/Power Release | 10/13/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Final | 10/23/2020 | Partial Inspection | THOMAS FINNILA |
| Green Building Final | 10/23/2020 | Partial Approval | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 10/23/2020 | SGSOV Not Ready | THOMAS FINNILA |
| Service/Power Release | 10/23/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Smoke Detectors | 10/23/2020 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 11/6/2020 | SGSOV Approved | THOMAS FINNILA |
| Service/Power Release | 11/6/2020 | Approved | THOMAS FINNILA |
| Final | 11/13/2020 | OK to Issue CofO | THOMAS FINNILA |
| Green Building Final | 11/13/2020 | Approved | THOMAS FINNILA |