4368 N IRVINE AVE 91604

Certificate Information: 4368 N IRVINE AVE 91604

Application / Permit
18014-20000-03735
Plan Check / Job No.
B18VN11333
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
9' X 19'11" ADDITION AND CONVERT (E) 20' X 19' 11" DET. GARAGE TO ADU PER AB 494 AND SB 229. ADD 2' X 19'11" STORAGE. ALL WORK PER ENGINEER.
Permit Issued
Issued on 1/6/2020
Issuing Office
Metro
Current Status
CofO Issued on 9/4/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/2/2018 APPLICANT
Assigned to Plan Check Engineer 7/2/2018 MENA WASSEF
Corrections Issued 7/3/2018 MENA WASSEF
Building Plans Picked Up 7/5/2018 APPLICANT
Applicant returned to address corrections 8/26/2019 YAQUB MIRZA
Plan Check Approved 9/4/2019 PINANK PATEL
Issued 1/6/2020 LADBS
CofO in Progress 11/13/2020 THOMAS FINNILA
Permit Finaled 9/4/2021 MICHAEL SMITH
CofO Issued 9/4/2021 MICHAEL SMITH
Permit Finaled 9/4/2021 MICHAEL SMITH

Permit Application Clearance Information

ZA Case Cleared 7/5/2018 ANNA VIDAL
Address approval Cleared 8/16/2018 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 8/16/2018 JOHN LIN
Sewer availability Cleared 8/16/2018 JOHN LIN
Hydrant and Access approval Cleared 8/26/2019 GILBERT URREA
Low Impact Development Cleared 8/29/2019 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 8/29/2019 ERIK BEASLEY

Contact Information

Contractor T L B Construction Corp; Lic. No.: 967633-B 2029 VERDUGO ROAD SUITE 260      MONTROSE, CA 91020
Engineer Loayza,, Miguel Antonio; Lic. No.: C26290 20062 MERRIDY STREET      CHATSWORTH, CA 91311

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/14/2020 Corrections Issued JEFFREY PARD
Footing/Foundation/Slab 2/21/2020 Approved JEFFREY PARD
Underground Mechanical 2/21/2020 Partial Approval JEFFREY PARD
BUILDING-Rough-Frame 5/20/2020 Approved JEFFREY PARD
ELECTRICAL-Rough 5/20/2020 Approved JEFFREY PARD
Green Building Rough 5/20/2020 Approved JEFFREY PARD
PLUMBING-Rough 5/20/2020 Approved JEFFREY PARD
HVAC-Rough 6/16/2020 Conditional Approval THOMAS FINNILA
Insulation 6/16/2020 Approved THOMAS FINNILA
Drywall Nailing 6/24/2020 Approved THOMAS FINNILA
Interior/Exterior Lathing 8/12/2020 Partial Inspection THOMAS FINNILA
Service/Power Release 8/12/2020 Not Ready for Inspection THOMAS FINNILA
Shower Pan 8/12/2020 Corrections Issued THOMAS FINNILA
Interior/Exterior Lathing 8/24/2020 Approved THOMAS FINNILA
Shower Pan 8/24/2020 Approved THOMAS FINNILA
Sewer 8/31/2020 Approved THOMAS FINNILA
Final 10/7/2020 Not Ready for Inspection THOMAS FINNILA
Green Building Final 10/7/2020 Not Ready for Inspection THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 10/7/2020 SGSOV Not Ready THOMAS FINNILA
Service/Power Release 10/7/2020 Not Ready for Inspection THOMAS FINNILA
Smoke Detectors 10/7/2020 Not Ready for Inspection THOMAS FINNILA
Service/Power Release 10/9/2020 Not Ready for Inspection DAVID MATSON
Service/Power Release 10/13/2020 Not Ready for Inspection THOMAS FINNILA
Final 10/23/2020 Partial Inspection THOMAS FINNILA
Green Building Final 10/23/2020 Partial Approval THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 10/23/2020 SGSOV Not Ready THOMAS FINNILA
Service/Power Release 10/23/2020 Not Ready for Inspection THOMAS FINNILA
Smoke Detectors 10/23/2020 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 11/6/2020 SGSOV Approved THOMAS FINNILA
Service/Power Release 11/6/2020 Approved THOMAS FINNILA
Final 11/13/2020 OK to Issue CofO THOMAS FINNILA
Green Building Final 11/13/2020 Approved THOMAS FINNILA