1754 N CLEAR VIEW DR 90210

Certificate Information: 1754 N CLEAR VIEW DR 90210

Application / Permit
18014-20000-03646
Plan Check / Job No.
B18VN11086
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
91' x 50' SECOND STORY ADDITION AND REMODEL TO EXISTING DWELLING. REMODEL AND REARRANGE ROOMS ON FIRST FLOOR.
Permit Issued
Issued on 9/18/2018
Issuing Office
Valley
Current Status
CofO Issued on 5/18/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/27/2018 APPLICANT
Green Plans Picked Up 7/10/2018 APPLICANT
Assigned to Plan Check Engineer 8/2/2018 SARAH YOUSSEF
Corrections Issued 8/7/2018 SARAH YOUSSEF
Quality Review Completed 8/7/2018 STEVEN KIM
Building Plans Picked Up 8/8/2018 APPLICANT
Plan Check Approved 8/31/2018 SARAH YOUSSEF
Issued 9/18/2018 LADBS
CofO in Progress 2/9/2021 ANTHONY MCDOWALL
CofO Issued 5/18/2021 VINCENT COTTON
Permit Finaled 5/18/2021 VINCENT COTTON

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 8/10/2018 MARKOS PEREZ-BRAN
BHO/Hillside ordinance Cleared 8/10/2018 MARKOS PEREZ-BRAN
BHO/Hillside ordinance Cleared 8/10/2018 MARKOS PEREZ-BRAN
Distance to fire station Cleared 8/10/2018 GILBERT URREA
Eng Process Fee Ord 176,300 Cleared 8/10/2018 MARKOS PEREZ-BRAN
Sewer availability Cleared 8/10/2018 MARKOS PEREZ-BRAN
ZA Case Cleared 8/10/2018 DAISY BENICIA
ZA Case Cleared 8/10/2018 DAISY BENICIA
ZA Case Cleared 8/10/2018 DAISY BENICIA
ZA Case Cleared 8/10/2018 DAISY BENICIA
ZA Case Cleared 8/10/2018 DAISY BENICIA
GPI Written Notices Cleared 8/27/2018 SARAH YOUSSEF
Grading Pre-Inspection Cleared 8/27/2018 SARAH YOUSSEF
Green Code Cleared 8/27/2018 DAVID MATSON
Low Impact Development Cleared 8/27/2018 SAM NAVID
Roof/Waste drainage to street Cleared 8/27/2018 MARKOS PEREZ-BRAN

Contact Information

Contractor Yaghoubi M Corp; Lic. No.: 972773-B 6459 LUBAO AVENUE      WOODLAND HILLS, CA 91367
Engineer Alexander,, Andy Joseph; Lic. No.: C84086       ,

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/20/2018 Not Ready for Inspection CARLOS MATAMOROS
Pre-Inspection 9/20/2018 Not Ready for Inspection CARLOS MATAMOROS
Footing/Foundation/Slab 10/23/2018 Approved CARLOS MATAMOROS
Piling/Pier/Caisson 10/25/2018 Corrections Issued CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 11/7/2018 Corrections Issued CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 11/28/2018 Approved CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 12/21/2018 Not Ready for Inspection CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 1/10/2019 Partial Approval CARLOS MATAMOROS
Piling/Pier/Caisson 1/10/2019 Partial Approval CARLOS MATAMOROS
Structural Steel Frame 1/10/2019 Approved CARLOS MATAMOROS
Piling/Pier/Caisson 2/7/2019 Approved CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 2/13/2019 Conditional Approval CARLOS MATAMOROS
Underground Mechanical 3/21/2019 Approved CARLOS MATAMOROS
Wood Frame 3/21/2019 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 3/28/2019 Approved CARLOS MATAMOROS
Deputy Steel/Welding 4/9/2019 Conditional Approval CARLOS MATAMOROS
Deputy Steel/Welding 4/11/2019 Conditional Approval CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 4/22/2019 Approved CARLOS MATAMOROS
Special/Order Compliance 5/11/2019 Partial Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 5/24/2019 Conditional Approval CARLOS MATAMOROS
ELECTRICAL-Rough 9/4/2019 Partial Approval CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 9/4/2019 Not Ready for Inspection CARLOS MATAMOROS
Gas Test 9/19/2019 Approved CARLOS MATAMOROS
PLUMBING-Rough 9/19/2019 Partial Approval CARLOS MATAMOROS
BUILDING-Rough-Frame 9/26/2019 Not Ready for Inspection CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 9/26/2019 Conditional Approval CARLOS MATAMOROS
HVAC-Rough 9/26/2019 Partial Approval CARLOS MATAMOROS
Verify Sprinkler Sign Off 9/26/2019 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 10/8/2019 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 10/8/2019 Approved CARLOS MATAMOROS
Green Building Rough 10/8/2019 Approved CARLOS MATAMOROS
HVAC-Rough 10/8/2019 Approved CARLOS MATAMOROS
PLUMBING-Rough 10/8/2019 Approved CARLOS MATAMOROS
Insulation 10/25/2019 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 10/25/2019 Not Ready for Inspection CARLOS MATAMOROS
Shower Pan 10/25/2019 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 10/31/2019 Approved CARLOS MATAMOROS
Drywall Nailing 11/15/2019 Approved CARLOS MATAMOROS
Rough-Elec/Plmb/HVAC 11/15/2019 Not Ready for Inspection CARLOS MATAMOROS
BUILDING-Rough-Frame 12/23/2019 Corrections Issued CARLOS MATAMOROS
Interior/Exterior Lathing 12/23/2019 Approved CARLOS MATAMOROS
Sewer 12/23/2019 Not Ready for Inspection CARLOS MATAMOROS
Interior/Exterior Lathing 1/6/2020 Conditional Approval ANTHONY MCDOWALL
Interior/Exterior Lathing 7/7/2020 Partial Approval ANTHONY MCDOWALL
Excavation/Setback/Form/Re-Bar 9/10/2020 Corrections Issued ANTHONY MCDOWALL
Pre-Inspection 9/11/2020 Approved ANTHONY MCDOWALL
ELECTRICAL-Final 9/14/2020 Not Ready for Inspection ANTHONY MCDOWALL
PLUMBING-Final 9/14/2020 Not Ready for Inspection ANTHONY MCDOWALL
Excavation/Setback/Form/Re-Bar 9/15/2020 Partial Approval ANTHONY MCDOWALL
ELECTRICAL-Final 11/17/2020 Corrections Issued ANTHONY MCDOWALL
HVAC-Final 11/17/2020 Not Ready for Inspection ANTHONY MCDOWALL
PLUMBING-Final 11/17/2020 Not Ready for Inspection ANTHONY MCDOWALL
Service/Power Release 11/17/2020 Not Ready for Inspection ANTHONY MCDOWALL
ELECTRICAL-Final 11/23/2020 Approved ANTHONY MCDOWALL
HVAC-Final 12/1/2020 Not Ready for Inspection ANTHONY MCDOWALL
PLUMBING-Final 12/1/2020 Approved ANTHONY MCDOWALL
Pre-Inspection 12/7/2020 Partial Approval ANTHONY MCDOWALL
Service/Power Release 12/15/2020 Approved CARLOS MATAMOROS
HVAC-Final 12/18/2020 Not Ready for Inspection CARLOS MATAMOROS
BUILDING-Rough-Frame 12/21/2020 Not Ready for Inspection CARLOS MATAMOROS
Final 12/21/2020 Not Ready for Inspection CARLOS MATAMOROS
Green Building Final 12/21/2020 Not Ready for Inspection CARLOS MATAMOROS
Grounding or Bonding 12/21/2020 Approved CARLOS MATAMOROS
Pool Piping 12/21/2020 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 12/21/2020 SGSOV Not Ready CARLOS MATAMOROS
Smoke Detectors 12/21/2020 Approved CARLOS MATAMOROS
HVAC-Final 12/23/2020 Conditional Approval CARLOS MATAMOROS
BUILDING-Rough-Frame 2/2/2021 Approved ANTHONY MCDOWALL
Final 2/2/2021 Not Ready for Inspection ANTHONY MCDOWALL
Green Building Final 2/2/2021 Approved ANTHONY MCDOWALL
SGSOV-Seismic Gas S/O Valve 2/2/2021 SGSOV Approved ANTHONY MCDOWALL
Final 2/9/2021 OK to Issue CofO ANTHONY MCDOWALL
Gas Test 2/12/2021 Not Ready for Inspection ANTHONY MCDOWALL
Gas Test 2/17/2021 Corrections Issued ANTHONY MCDOWALL
Gas Test 2/19/2021 Approved ANTHONY MCDOWALL