5152 N ETIWANDA AVE 91356
Certificate Information: 5152 N ETIWANDA AVE 91356
- Application / Permit
- 18014-20000-03548
- Plan Check / Job No.
- B18VN10805
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY DWELLING WITH ATTACHED GARAGE. TO BE FULLY SPRINKLERED THOUGH OUT.
- Permit Issued
- Issued on 8/8/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/22/2018 | APPLICANT |
| Green Plans Picked Up | 7/16/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 7/26/2018 | SARAH YOUSSEF |
| Corrections Issued | 7/30/2018 | SARAH YOUSSEF |
| Quality Review Completed | 8/1/2018 | STEVEN KIM |
| Building Plans Picked Up | 8/1/2018 | APPLICANT |
| Application Withdrawn-Void | 3/14/2019 | STEVEN KIM |
| Re-Activate Application | 3/18/2019 | TAMERA SVETICH |
| Plan Check Approved | 8/8/2019 | SELLA BENYAMIN |
| Issued | 8/8/2019 | LADBS |
| CofO in Progress | 5/7/2025 | JOHN KIDWELL |
| Permit Finaled | 6/17/2025 | JOHN JANSON |
| CofO Issued | 6/17/2025 | JOHN JANSON |
| Permit Finaled | 6/17/2025 | JOHN JANSON |
Permit Application Clearance Information
| Disturb/Remove Protected Trees | Cleared | 9/17/2018 | ADRIAN SANCHEZ |
| Trees in Parkway | Cleared | 9/17/2018 | ADRIAN SANCHEZ |
| Low Impact Development | Cleared | 10/18/2018 | MITESH PATEL |
| Green Code | Cleared | 10/25/2018 | MICHAEL AYERS |
| Hydrant and Access approval | Cleared | 7/18/2019 | GEORGE SUCHAND |
| Hydrant and Access approval | Cleared | 7/18/2019 | GEORGE SUCHAND |
| Eng Process Fee Ord 176,300 | Cleared | 7/19/2019 | GUILLERMO PETRA |
| Permit | Cleared | 7/19/2019 | GUILLERMO PETRA |
| Permit | Cleared | 7/19/2019 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 7/19/2019 | GUILLERMO PETRA |
| Sewer availability | Cleared | 7/19/2019 | GUILLERMO PETRA |
| GPI Written Notices | Cleared | 8/8/2019 | SARAH YOUSSEF |
| Grading Pre-Inspection | Cleared | 8/8/2019 | SARAH YOUSSEF |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Askarian,, Soroosh Namaghi; Lic. No.: C83413 | 22287 MULHOLLAND HWY 163 CALABASAS, CA 91302 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grading Pre-Inspection | 9/3/2020 | Not Ready for Inspection | DAVID SANDOVAL |
| Sewer | 12/10/2020 | Corrections Issued | SEAN WIRCH |
| Underground Mechanical | 12/10/2020 | Not Ready for Inspection | SEAN WIRCH |
| Underground Mechanical | 12/16/2020 | Partial Approval | DAVID SANDOVAL |
| Footing/Foundation/Slab | 12/23/2020 | Corrections Issued | DAVID SANDOVAL |
| Footing/Foundation/Slab | 12/30/2020 | Corrections Issued | DAVID SANDOVAL |
| Footing/Foundation/Slab | 1/5/2021 | Approved | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 2/8/2021 | Corrections Issued | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2021 | Partial Approval | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2021 | Corrections Issued | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 3/30/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 7/13/2021 | Not Ready for Inspection | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2021 | Partial Approval | RONALD COWAN |
| Pre-Inspection | 8/2/2021 | Approved | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| ELECTRICAL-Rough | 9/29/2021 | No Access for Inspection | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2021 | Partial Inspection | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2021 | Partial Approval | DAVID SANDOVAL |
| Interior/Exterior Lathing | 1/11/2022 | Partial Approval | PETER FOLLING |
| Insulation | 2/24/2022 | Corrections Issued | PETER FOLLING |
| Insulation | 3/4/2022 | No Access for Inspection | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 3/14/2022 | Approved | DAVID SANDOVAL |
| Green Building Rough | 3/14/2022 | Approved | DAVID SANDOVAL |
| Interior/Exterior Lathing | 3/14/2022 | Partial Approval | DAVID SANDOVAL |
| Rough-Elec/Plmb/HVAC | 3/14/2022 | Approved | DAVID SANDOVAL |
| Shower Pan | 3/14/2022 | Approved | DAVID SANDOVAL |
| Verify Sprinkler Sign Off | 3/14/2022 | Approved | DAVID SANDOVAL |
| Drywall Nailing | 4/27/2022 | Approved | DAVID SANDOVAL |
| Sewer | 6/27/2023 | Not Ready for Inspection | SEAN HAUPT |
| Underground Mechanical | 6/27/2023 | No Access for Inspection | SEAN HAUPT |
| Sewer | 7/21/2023 | Corrections Issued | SEAN HAUPT |
| Sewer | 7/28/2023 | Approved | SEAN HAUPT |
| Final | 9/6/2024 | Not Ready for Inspection | JOHN KIDWELL |
| Green Building Final | 9/6/2024 | Not Ready for Inspection | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 9/6/2024 | SGSOV Not Ready | JOHN KIDWELL |
| Service/Power Release | 9/6/2024 | Not Ready for Inspection | JOHN KIDWELL |
| Smoke Detectors | 9/6/2024 | Approved | JOHN KIDWELL |
| Green Building Final | 9/27/2024 | Not Ready for Inspection | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 9/27/2024 | SGSOV Approved | JOHN KIDWELL |
| Final | 10/7/2024 | Not Ready for Inspection | JOHN KIDWELL |
| Green Building Final | 10/7/2024 | Not Ready for Inspection | JOHN KIDWELL |
| Service/Power Release | 10/7/2024 | Not Ready for Inspection | JOHN KIDWELL |
| Final | 1/7/2025 | Corrections Issued | JOHN KIDWELL |
| Green Building Final | 1/7/2025 | Not Ready for Inspection | JOHN KIDWELL |
| Service/Power Release | 1/7/2025 | Not Ready for Inspection | JOHN KIDWELL |
| Final | 1/24/2025 | Not Ready for Inspection | JOHN KIDWELL |
| Green Building Final | 1/24/2025 | Approved | JOHN KIDWELL |
| Service/Power Release | 1/24/2025 | Approved | JOHN KIDWELL |
| Final | 4/8/2025 | OK to Issue CofO | JOHN KIDWELL |