2261 N HERCULES DR 90046
Certificate Information: 2261 N HERCULES DR 90046
- Application / Permit
- 18014-20000-03443
- Plan Check / Job No.
- B18VN10507
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 22'9" X 22'3" BEDROOM ON TOP OF ATTACHED GARAGE PER ENGINEERING
- Permit Issued
- Issued on 9/27/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/19/2018 | APPLICANT |
| Green Plans Picked Up | 7/6/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 7/19/2018 | ALDOUS CHIC |
| Corrections Issued | 7/23/2018 | ALDOUS CHIC |
| Quality Review Completed | 7/23/2018 | CHON CHIO KUO |
| Building Plans Picked Up | 7/25/2018 | APPLICANT |
| Plan Check Approved | 9/27/2018 | KAREN HYDE |
| Issued | 9/27/2018 | LADBS |
| CofO in Progress | 3/13/2024 | RAUL BARAJAS |
| CofO Issued | 3/14/2024 | RONALD MYRICK |
| Permit Finaled | 3/14/2024 | RONALD MYRICK |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/7/2018 | ALDOUS CHIC |
| Eng Process Fee Ord 176,300 | Cleared | 7/25/2018 | MARKOS PEREZ-BRAN |
| Roof/Waste drainage to street | Cleared | 7/25/2018 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 7/25/2018 | MARKOS PEREZ-BRAN |
| Green Code | Cleared | 8/1/2018 | PARISA ZAHABI |
Contact Information
| Engineer | Javadi-Koma, Shahram; Lic. No.: C69497 | 10349 MONTGOMERY AVE GRANADA HILLS, CA 91403 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/12/2019 | Partial Inspection | RAUL BARAJAS |
| Deputy Drilled-In Anchors | 11/20/2020 | No Access for Inspection | ELMER BLAND |
| Footing/Foundation/Slab | 5/12/2021 | Corrections Issued | RAUL BARAJAS |
| Footing/Foundation/Slab | 5/20/2021 | Partial Approval | BRIAN SULLIVAN |
| Deputy Steel/Welding | 6/24/2021 | Conditional Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2021 | Partial Approval | RAUL BARAJAS |
| Green Building Rough | 7/27/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2022 | Approved | RAUL BARAJAS |
| ELECTRICAL-Rough | 4/29/2022 | Corrections Issued | RAUL BARAJAS |
| PLUMBING-Rough | 4/29/2022 | Corrections Issued | RAUL BARAJAS |
| BUILDING-Rough-Frame | 6/14/2022 | Conditional Approval | RAUL BARAJAS |
| ELECTRICAL-Rough | 6/14/2022 | Approved | RAUL BARAJAS |
| Green Building Rough | 6/14/2022 | Approved | RAUL BARAJAS |
| PLUMBING-Rough | 6/14/2022 | Approved | RAUL BARAJAS |
| Insulation | 9/29/2022 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 9/29/2022 | Approved | RAUL BARAJAS |
| Shower Pan | 9/29/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Drywall Nailing | 6/23/2023 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 6/23/2023 | Partial Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 12/26/2023 | Approved | RAUL BARAJAS |
| Final | 12/26/2023 | No Access for Inspection | RAUL BARAJAS |
| Footing/Foundation/Slab | 12/26/2023 | Approved | RAUL BARAJAS |
| Green Building Final | 12/26/2023 | No Access for Inspection | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 12/26/2023 | SGSOV Not Ready | RAUL BARAJAS |
| Smoke Detectors | 12/26/2023 | No Access for Inspection | RAUL BARAJAS |
| Final | 1/3/2024 | Corrections Issued | RAUL BARAJAS |
| Green Building Final | 1/3/2024 | Not Ready for Inspection | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 1/3/2024 | SGSOV Approved | RAUL BARAJAS |
| Smoke Detectors | 1/3/2024 | Approved | RAUL BARAJAS |
| Final | 1/29/2024 | Corrections Issued | RAUL BARAJAS |
| Green Building Final | 1/29/2024 | Not Ready for Inspection | RAUL BARAJAS |
| Final | 3/12/2024 | OK to Issue CofO | RAUL BARAJAS |
| Green Building Final | 3/12/2024 | Approved | RAUL BARAJAS |