12035 N BROMONT AVE 91340
Certificate Information: 12035 N BROMONT AVE 91340
- Application / Permit
- 18014-20000-03424
- Plan Check / Job No.
- B18VN10442
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD TO & CONVERT GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 & SB 229
- Permit Issued
- Issued on 6/12/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/3/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/18/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 8/8/2018 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 8/8/2018 | VLADIMIR ARUTYUNYAN |
| Quality Review Completed | 8/10/2018 | STEVEN KIM |
| Building Plans Picked Up | 8/13/2018 | APPLICANT |
| Green Plans Picked Up | 8/13/2018 | APPLICANT |
| Plan Check Approved | 6/6/2019 | VLADIMIR ARUTYUNYAN |
| Issued | 6/12/2019 | LADBS |
| CofO in Progress | 5/26/2020 | MICHEL ABAJAN |
| Permit Finaled | 4/3/2021 | MICHAEL SMITH |
| CofO Issued | 4/3/2021 | MICHAEL SMITH |
| Permit Finaled | 4/3/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 8/30/2018 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 8/30/2018 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 8/30/2018 | MARKOS PEREZ-BRAN |
| Green Code | Cleared | 11/6/2018 | VLADIMIR ARUTYUNYAN |
| Low Impact Development | Cleared | 11/6/2018 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 2/7/2019 | CHRISTINE REUSCH |
| Construction near power lines | Cleared | 5/7/2019 | RIDWAN HARDY |
| Construction within easement | Cleared | 5/7/2019 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/13/2019 | Partial Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 9/25/2019 | Not Ready for Inspection | MICHEL ABAJAN |
| Footing/Foundation/Slab | 9/30/2019 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 9/30/2019 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2019 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 10/16/2019 | Not Ready for Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 11/26/2019 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 11/26/2019 | Approved | MICHEL ABAJAN |
| Green Building Rough | 11/26/2019 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 11/26/2019 | Not Ready for Inspection | MICHEL ABAJAN |
| Insulation | 12/18/2019 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 12/18/2019 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 1/10/2020 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 3/25/2020 | Corrections Issued | MICHEL ABAJAN |
| PLUMBING-Rough | 3/27/2020 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 5/21/2020 | Approved | MICHEL ABAJAN |
| Final | 5/21/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| Green Building Final | 5/21/2020 | Approved | MICHEL ABAJAN |
| HVAC-Final | 5/21/2020 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 5/21/2020 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 5/21/2020 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 5/21/2020 | Approved | MICHEL ABAJAN |
| Final | 5/26/2020 | OK to Issue CofO | MICHEL ABAJAN |