3565 S MAPLEWOOD AVE 90066

Certificate Information: 3565 S MAPLEWOOD AVE 90066

Application / Permit
18014-20000-03341
Plan Check / Job No.
B18VN10198
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Major remodel irregular shaped and 2nd floor addition (63'x32'-4") to existing single family dwelling. Add new open trellis (12'x33') at rear and (10'x6') trellis at front. All walls except wall at front to remain. NFPA 13 D fire sprinklers required (see comments)
Permit Issued
Issued on 9/17/2021
Issuing Office
West Los Angeles
Current Status
CofO Issued on 5/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/14/2018 APPLICANT
Green Plans Picked Up 7/27/2018 APPLICANT
Assigned to Plan Check Engineer 7/31/2018 ALYSSA N NARCISO
Corrections Issued 8/1/2018 ALYSSA N NARCISO
Quality Review Completed 8/2/2018 STEVEN KIM
Building Plans Picked Up 8/6/2018 APPLICANT
Applicant returned to address corrections 11/28/2018 ALYSSA N NARCISO
Applicant returned to address corrections 12/10/2018 ALYSSA N NARCISO
Plan Check Approved 1/8/2020 ALYSSA N NARCISO
Issued 9/17/2021 APPLICANT
CofO in Progress 4/30/2023 JESUS RODRIGUEZ
Permit Finaled 5/5/2023 DANIEL ORRANTE
CofO Issued 5/5/2023 DANIEL ORRANTE
Permit Finaled 5/5/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/25/2018 KAYLA PEJI
Hydrant and Access approval Cleared 10/25/2018 JOHN DALLAS
Permit Cleared 10/25/2018 KAYLA PEJI
Sewer availability Cleared 10/25/2018 KAYLA PEJI
Green Code Cleared 11/7/2018 PARISA ZAHABI
Low Impact Development Cleared 1/22/2019 SARAH YOUSSEF
Trees in Parkway Cleared 11/21/2019 JOHN KIM
Roof/Waste drainage to street Cleared 11/22/2019 MARKOS PEREZ-BRAN
GPI Written Notices Cleared 1/8/2020 ALYSSA N NARCISO
Grading Pre-Inspection Cleared 1/8/2020 ALYSSA N NARCISO

Contact Information

Architect Boivin,, Alan; Lic. No.: C9528 21066 COLINA DRIVE      TOPANGA, CA 90290
Contractor Carretta Construction - Development; Lic. No.: 881944-B 4133 TORRANCE BLVD #439      TORRANCE, CA 90503
Engineer Niver, Kenneth Earl; Lic. No.: S2554 10845 LINDBROOK DR STE 203      W LOS ANGELES, CA 90024

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/27/2021 Not Ready for Inspection ENRIQUE MIRELES
Pre-Inspection 10/27/2021 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 11/19/2021 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 11/19/2021 Not Ready for Inspection ENRIQUE MIRELES
Structural Steel Frame 11/19/2021 Not Ready for Inspection ENRIQUE MIRELES
Deputy Reinf. Concrete 12/7/2021 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 1/3/2022 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Rough 1/3/2022 Not Ready for Inspection JUAN VALENZUELA
Green Building Rough 1/3/2022 Not Ready for Inspection JUAN VALENZUELA
PLUMBING-Rough 1/3/2022 Corrections Issued JUAN VALENZUELA
PLUMBING-Rough 1/4/2022 Corrections Issued OGANES TARAKHCHYAN
BUILDING-Rough-Frame 1/7/2022 Partial Approval DAVID FEILER
Green Building Rough 1/7/2022 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 1/7/2022 Partial Approval DAVID FEILER
Underground Mechanical 1/7/2022 Not Ready for Inspection DAVID FEILER
BUILDING-Rough-Frame 1/11/2022 Partial Approval ENRIQUE MIRELES
Footing/Foundation/Slab 1/13/2022 Approved ENRIQUE MIRELES
Deputy Reinf. Concrete 1/14/2022 Approved ENRIQUE MIRELES
Wood Frame 1/27/2022 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 5/2/2022 Corrections Issued PATRICK QUALEY
ELECTRICAL-Rough 5/6/2022 Approved PATRICK QUALEY
Floor/Roof Diaphrgm/Shear Wall 5/18/2022 Partial Approval PATRICK QUALEY
HVAC-Rough 5/18/2022 Corrections Issued PATRICK QUALEY
PLUMBING-Rough 5/19/2022 Corrections Issued STEPHANIE SWANSON
BUILDING-Rough-Frame 6/3/2022 Partial Approval PATRICK QUALEY
Green Building Rough 6/3/2022 Not Ready for Inspection PATRICK QUALEY
HVAC-Rough 6/3/2022 Approved PATRICK QUALEY
PLUMBING-Rough 6/3/2022 Corrections Issued PATRICK QUALEY
Interior/Exterior Lathing 6/21/2022 Partial Approval EVAN COOPER
Shower Pan 6/21/2022 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 6/27/2022 Partial Inspection STEPHANIE SWANSON
Insulation 7/6/2022 Corrections Issued HERBERT GIRON
BUILDING-Rough-Frame 7/8/2022 Not Ready for Inspection PATRICK QUALEY
Green Building Rough 7/8/2022 Not Ready for Inspection PATRICK QUALEY
Insulation 7/8/2022 Not Ready for Inspection PATRICK QUALEY
PLUMBING-Rough 7/8/2022 Not Ready for Inspection PATRICK QUALEY
BUILDING-Rough-Frame 7/21/2022 Approved EVAN COOPER
Green Building Rough 7/21/2022 Approved EVAN COOPER
Insulation 7/21/2022 Approved EVAN COOPER
Drywall Nailing 8/4/2022 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 8/11/2022 Partial Approval DAVID FEILER
Interior/Exterior Lathing 8/15/2022 Partial Approval CLAYTON GRAHAM
Sewer 12/1/2022 Approved JESUS RODRIGUEZ
Underground Mechanical 12/1/2022 Partial Approval JESUS RODRIGUEZ
Gas Test 1/13/2023 Approved JESUS RODRIGUEZ
Underground Mechanical 1/13/2023 Partial Approval JESUS RODRIGUEZ
ELECTRICAL-Final 1/18/2023 Approved JESUS RODRIGUEZ
PLUMBING-Final 1/18/2023 Corrections Issued JESUS RODRIGUEZ
Service/Power Release 1/18/2023 Approved JESUS RODRIGUEZ
Smoke Detectors 1/18/2023 Corrections Issued JESUS RODRIGUEZ
Final 4/28/2023 OK to Issue CofO JESUS RODRIGUEZ
Green Building Final 4/28/2023 Approved JESUS RODRIGUEZ
HVAC-Final 4/28/2023 Approved JESUS RODRIGUEZ
PLUMBING-Final 4/28/2023 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 4/28/2023 SGSOV Approved JESUS RODRIGUEZ
Smoke Detectors 4/28/2023 Approved JESUS RODRIGUEZ