14554 W GALLAUDET PL 90272
Certificate Information: 14554 W GALLAUDET PL 90272
- Application / Permit
- 18014-20000-03331
- Plan Check / Job No.
- B18VN10162
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR INTERIOR REMODEL TO (E) SFD TO REMODEL ENTIRE FLOOR PLAN LAYOUT: 1' 6" X 6' 6", & 1' 6" X 21' 4" 1ST FLOOR ADDITIONS, 7' X 24' ADDITION TO GARAGE, 41' 11" X 55' 4" IRR.-SHAPE 2ND FLOOR ADDITION AND 16' 5" X 24' 11" CARPORT TRELLIS ADDITION. ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 2/17/2022
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 2/17/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/14/2018 | APPLICANT |
| Green Plans Picked Up | 7/24/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 8/9/2018 | GURUNATH NESARAJAH |
| Corrections Issued | 8/15/2018 | GURUNATH NESARAJAH |
| Quality Review Completed | 8/22/2018 | STEVEN KIM |
| Plan Check Approved | 2/10/2022 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 2/10/2022 | APPLICANT |
| Issued | 2/17/2022 | APPLICANT |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 4/5/2019 | JOHN DALLAS |
| BHO/Hillside ordinance | Cleared | 1/12/2021 | RAYMOND MUGAMBWA |
| BHO/Hillside ordinance | Cleared | 1/12/2021 | RAYMOND MUGAMBWA |
| Eng Process Fee Ord 176,300 | Cleared | 1/25/2021 | RAYMOND MUGAMBWA |
| Sewer availability | Cleared | 3/25/2021 | RAYMOND MUGAMBWA |
| BHO/Hillside ordinance | Cleared | 7/30/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 7/30/2021 | DINAH GARIN |
| Low Impact Development | Cleared | 10/5/2021 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 11/3/2021 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 11/3/2021 | DINAH GARIN |
| Private street | Cleared | 11/17/2021 | MIGUEL GAMBOA |
| ZA Case | Cleared | 11/17/2021 | MIGUEL GAMBOA |
| ZA Case | Cleared | 11/17/2021 | MIGUEL GAMBOA |
| Distance to fire station | Cleared | 1/12/2022 | KURT CORRAL |
| GPI Written Notices | Cleared | 2/7/2022 | GURUNATH NESARAJAH |
| Grading Pre-Inspection | Cleared | 2/7/2022 | GURUNATH NESARAJAH |
| Green Code | Cleared | 2/7/2022 | PARISA ZAHABI |
Contact Information
| Engineer | Adams,, Robert Charles; Lic. No.: C21234 | 22129 BRYANT STREET CANOGA PARK, CA 91304 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/12/2022 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 7/20/2022 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 8/3/2022 | Corrections Issued | ANDREW NAVE |
| Footing/Foundation/Slab | 8/8/2022 | Approved | ANDREW NAVE |
| Underground Mechanical | 8/25/2022 | Partial Approval | MICHAEL PELHAM |
| Deputy Drilled-In Anchors | 1/3/2023 | Conditional Approval | KEVIN SARGSYAN |
| Deputy Drilled-In Anchors | 2/21/2023 | No Access for Inspection | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 3/1/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/13/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Wood Frame | 3/24/2023 | Approved | OGANES TARAKHCHYAN |
| Wood Frame | 3/28/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Underground Mechanical | 4/4/2023 | Corrections Issued | STEPHANIE SWANSON |
| Underground Mechanical | 4/14/2023 | Not Ready for Inspection | JESUS PINEDA |
| Underground Mechanical | 4/18/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| HVAC-Rough | 4/25/2023 | Approved | OGANES TARAKHCHYAN |
| Underground Mechanical | 4/25/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 5/2/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Underground Mechanical | 5/4/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 5/18/2023 | Conditional Approval | MICHAEL PELHAM |
| Deputy Drilled-In Anchors | 5/19/2023 | Conditional Approval | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 5/23/2023 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 5/31/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 5/31/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 6/1/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 6/1/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 6/14/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 6/22/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 6/22/2023 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 6/27/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Rough | 6/27/2023 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 6/28/2023 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 6/30/2023 | Approved | OGANES TARAKHCHYAN |
| Insulation | 7/10/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Drywall Nailing | 7/26/2023 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 8/15/2023 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 8/24/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 8/29/2023 | Partial Approval | ARAM AVEDISIAN |
| Underground Mechanical | 10/26/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Underground Mechanical | 11/1/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Gas Test | 11/9/2023 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 2/29/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| HVAC-Rough | 2/29/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 3/4/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 5/1/2024 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 5/1/2024 | Approved | EVAN COOPER |
| Final | 5/1/2024 | Corrections Issued | EVAN COOPER |
| Green Building Final | 5/1/2024 | Approved | EVAN COOPER |
| HVAC-Final | 5/1/2024 | Approved | EVAN COOPER |
| PLUMBING-Final | 5/1/2024 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 5/1/2024 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 5/1/2024 | Approved | EVAN COOPER |