5624 N BEVIS AVE 91411
Certificate Information: 5624 N BEVIS AVE 91411
- Application / Permit
- 18014-20000-02998
- Plan Check / Job No.
- B18VN09165
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 15'-6'' X 27'-0''ADDITION TO (E) SFD TO CREATE A NEW MASTER BEDROOM AND NEW MASTER BATHROOM. ALL WORK PER WFPP
- Permit Issued
- Issued on 6/20/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/17/2018
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/31/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 5/31/2018 | DANNY MORALES |
| Corrections Issued | 5/31/2018 | DANNY MORALES |
| Applicant returned to address corrections | 6/14/2018 | JOHNNY WU |
| Plan Check Approved | 6/20/2018 | RARES BODEA |
| Issued | 6/20/2018 | LADBS |
| CofO in Progress | 9/13/2018 | ARAM AVEDISIAN |
| CofO Issued | 9/17/2018 | ANTHONY GIANNINI |
| Permit Finaled | 9/17/2018 | ANTHONY GIANNINI |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/31/2018 | KAYLA PEJI |
| Roof/Waste drainage to street | Cleared | 5/31/2018 | KAYLA PEJI |
| Sewer availability | Cleared | 5/31/2018 | KAYLA PEJI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/11/2018 | Approved | GREG ALLTON |
| BUILDING-Rough-Frame | 7/17/2018 | Partial Approval | GREG ALLTON |
| Insulation | 7/17/2018 | Partial Approval | GREG ALLTON |
| PLUMBING-Rough | 7/17/2018 | Partial Approval | GREG ALLTON |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2018 | Partial Approval | GREG ALLTON |
| Floor/Roof Diaphrgm/Shear Wall | 7/23/2018 | Approved | GREG ALLTON |
| ELECTRICAL-Rough | 7/31/2018 | Approved | GREG ALLTON |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2018 | Approved | GREG ALLTON |
| Interior/Exterior Lathing | 8/2/2018 | Partial Approval | GREG ALLTON |
| Drywall Nailing | 8/7/2018 | Approved | GREG ALLTON |
| BUILDING-Rough-Frame | 9/10/2018 | Approved | ARAM AVEDISIAN |
| Final | 9/10/2018 | Corrections Issued | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 9/10/2018 | Approved | ARAM AVEDISIAN |
| Green Building Final | 9/10/2018 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 9/10/2018 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 9/10/2018 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 9/10/2018 | Approved | ARAM AVEDISIAN |
| Final | 9/12/2018 | Conditional Approval | ARAM AVEDISIAN |