5624 N BEVIS AVE 91411

Certificate Information: 5624 N BEVIS AVE 91411

Application / Permit
18014-20000-02998
Plan Check / Job No.
B18VN09165
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 15'-6'' X 27'-0''ADDITION TO (E) SFD TO CREATE A NEW MASTER BEDROOM AND NEW MASTER BATHROOM. ALL WORK PER WFPP
Permit Issued
Issued on 6/20/2018
Issuing Office
Valley
Current Status
CofO Issued on 9/17/2018
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/31/2018 APPLICANT
Assigned to Plan Check Engineer 5/31/2018 DANNY MORALES
Corrections Issued 5/31/2018 DANNY MORALES
Applicant returned to address corrections 6/14/2018 JOHNNY WU
Plan Check Approved 6/20/2018 RARES BODEA
Issued 6/20/2018 LADBS
CofO in Progress 9/13/2018 ARAM AVEDISIAN
CofO Issued 9/17/2018 ANTHONY GIANNINI
Permit Finaled 9/17/2018 ANTHONY GIANNINI

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/31/2018 KAYLA PEJI
Roof/Waste drainage to street Cleared 5/31/2018 KAYLA PEJI
Sewer availability Cleared 5/31/2018 KAYLA PEJI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/11/2018 Approved GREG ALLTON
BUILDING-Rough-Frame 7/17/2018 Partial Approval GREG ALLTON
Insulation 7/17/2018 Partial Approval GREG ALLTON
PLUMBING-Rough 7/17/2018 Partial Approval GREG ALLTON
Floor/Roof Diaphrgm/Shear Wall 7/18/2018 Partial Approval GREG ALLTON
Floor/Roof Diaphrgm/Shear Wall 7/23/2018 Approved GREG ALLTON
ELECTRICAL-Rough 7/31/2018 Approved GREG ALLTON
Floor/Roof Diaphrgm/Shear Wall 7/31/2018 Approved GREG ALLTON
Interior/Exterior Lathing 8/2/2018 Partial Approval GREG ALLTON
Drywall Nailing 8/7/2018 Approved GREG ALLTON
BUILDING-Rough-Frame 9/10/2018 Approved ARAM AVEDISIAN
Final 9/10/2018 Corrections Issued ARAM AVEDISIAN
Footing/Foundation/Slab 9/10/2018 Approved ARAM AVEDISIAN
Green Building Final 9/10/2018 Approved ARAM AVEDISIAN
Green Building Rough 9/10/2018 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 9/10/2018 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 9/10/2018 Approved ARAM AVEDISIAN
Final 9/12/2018 Conditional Approval ARAM AVEDISIAN