7542 N WHITE OAK AVE 91406

Certificate Information: 7542 N WHITE OAK AVE 91406

Application / Permit
18014-20000-02850
Plan Check / Job No.
B18VN08745
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 34'-6" X 24'-0" IRR. SHAPE AND CONVERT (E) 20' X 14' DET. GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER WFPP.
Permit Issued
Issued on 6/22/2020
Issuing Office
Valley
Current Status
CofO Issued on 9/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/23/2018 APPLICANT
Green Plans Picked Up 6/21/2018 APPLICANT
Assigned to Plan Check Engineer 7/9/2018 GURUNATH NESARAJAH
Corrections Issued 7/11/2018 GURUNATH NESARAJAH
Quality Review Completed 7/20/2018 STEVEN KIM
Building Plans Picked Up 7/20/2018 APPLICANT
Plan Check Approved 8/8/2018 GURUNATH NESARAJAH
Issued 6/22/2020 LADBS
CofO in Progress 8/11/2025 JAVIER RAMOS JR
Permit Finaled 9/9/2025 RUBEN SALAS
CofO Issued 9/9/2025 RUBEN SALAS
Permit Finaled 9/9/2025 RUBEN SALAS

Permit Application Clearance Information

Low Impact Development Cleared 7/26/2018 MITESH PATEL
Stormwater Pollution Mitigatn Cleared 7/26/2018 MITESH PATEL
Address approval Cleared 7/27/2018 HOWARD COOPER
Eng Process Fee Ord 176,300 Cleared 7/27/2018 CHRISTINE REUSCH
Roof/Waste drainage to street Cleared 7/27/2018 CHRISTINE REUSCH
Address approval Cleared 7/30/2018 HOWARD COOPER
Sewer availability Cleared 7/30/2018 CHRISTINE REUSCH
Green Code Cleared 8/7/2018 DAVID MATSON

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/6/2020 Approved DANIEL DREW
Underground Mechanical 7/6/2020 Approved DANIEL DREW
Excavation/Setback/Form/Re-Bar 7/10/2020 Corrections Issued DANIEL DREW
Reinforced Concrete Frame 7/14/2020 Approved DANIEL DREW
BUILDING-Rough-Frame 10/20/2020 Not Ready for Inspection DAVID MATSON
ELECTRICAL-Rough 10/20/2020 Corrections Issued DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 10/20/2020 Not Ready for Inspection DAVID MATSON
Green Building Rough 10/20/2020 Corrections Issued DAVID MATSON
Insulation 10/20/2020 Not Ready for Inspection DAVID MATSON
PLUMBING-Rough 10/20/2020 Corrections Issued DAVID MATSON
PLUMBING-Rough 10/27/2020 Corrections Issued MICHAEL TEMPLE
Underground Mechanical 10/27/2020 Partial Approval MICHAEL TEMPLE
PLUMBING-Rough 11/25/2020 Partial Approval ARTHUR SARGSYAN
Special/Order Compliance 11/25/2020 Approved ARTHUR SARGSYAN
Underground Mechanical 11/25/2020 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 12/4/2020 Not Ready for Inspection ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 12/4/2020 Not Ready for Inspection ARTHUR SARGSYAN
Green Building Rough 12/4/2020 Not Ready for Inspection ARTHUR SARGSYAN
Insulation 2/12/2021 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 2/16/2021 Approved ARTHUR SARGSYAN
Green Building Rough 2/16/2021 Approved ARTHUR SARGSYAN
Insulation 2/18/2021 Approved ARTHUR SARGSYAN
Drywall Nailing 3/1/2021 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 3/1/2021 Partial Approval ARTHUR SARGSYAN
ELECTRICAL-Final 6/8/2023 Corrections Issued RAUL OLAGI
Final 6/8/2023 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 6/8/2023 Approved RAUL OLAGI
Green Building Final 6/8/2023 Approved RAUL OLAGI
PLUMBING-Final 6/8/2023 Corrections Issued RAUL OLAGI
ELECTRICAL-Final 12/18/2024 Corrections Issued SALVADOR MARTINEZ
Final 12/18/2024 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Final 12/18/2024 Corrections Issued SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 12/18/2024 SGSOV Not Ready SALVADOR MARTINEZ
Smoke Detectors 12/18/2024 Not Ready for Inspection SALVADOR MARTINEZ
Final 6/4/2025 Corrections Issued SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 6/4/2025 SGSOV Approved SALVADOR MARTINEZ
Smoke Detectors 6/4/2025 Approved SALVADOR MARTINEZ
ELECTRICAL-Final 8/7/2025 Approved JAVIER RAMOS JR
Final 8/7/2025 OK to Issue CofO JAVIER RAMOS JR
HVAC-Final 8/7/2025 Approved JAVIER RAMOS JR