15094 W NURMI ST 91342

Certificate Information: 15094 W NURMI ST 91342

Application / Permit
18014-20000-02825
Plan Check / Job No.
B18VN08631
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
24' 4" X 24' 9" IRREGULAR-SHAPED ADDITION TO REAR OF (E) SINGLE FAMILY DWELLING. ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 10/9/2020
Issuing Office
Current Status
CofO Issued on 3/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/22/2018 APPLICANT
Green Plans Picked Up 6/25/2018 APPLICANT
Assigned to Plan Check Engineer 7/9/2018 GURUNATH NESARAJAH
Corrections Issued 7/12/2018 GURUNATH NESARAJAH
Quality Review Completed 7/30/2018 STEVEN KIM
Building Plans Picked Up 8/2/2018 APPLICANT
Plan Check Approved 9/4/2019 GURUNATH NESARAJAH
Issued 10/9/2020 APPLICANT
CofO in Progress 1/31/2023 ARAM AVEDISIAN
Permit Finaled 3/18/2023 DANIEL ORRANTE
CofO Issued 3/18/2023 DANIEL ORRANTE
Permit Finaled 3/18/2023 DANIEL ORRANTE

Permit Application Clearance Information

Hold Cleared 11/16/2018 CYNTHIA RYAN
Eng Process Fee Ord 176,300 Cleared 2/22/2019 JAMES MORALEZ
Roof/Waste drainage to street Cleared 2/22/2019 JAMES MORALEZ
Sewer availability Cleared 2/22/2019 JAMES MORALEZ
Green Code Cleared 8/13/2019 DAVID MATSON

Contact Information

Contractor Owner-Builder       ,
Engineer Blair, Gordon Reid; Lic. No.: C53953 10455 GAYNOR AVE      GRANADA HILLS, CA 91344

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/30/2020 Partial Inspection MISAEL ESPARZA
Pre-Inspection 10/30/2020 Partial Inspection MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 11/18/2020 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 11/18/2020 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 11/19/2020 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 11/25/2020 Partial Inspection MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 2/17/2022 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 2/17/2022 Not Ready for Inspection JOHN HAYES
Underground Mechanical 2/17/2022 Not Ready for Inspection JOHN HAYES
Deputy Drilled-In Anchors 6/13/2022 Approved JOHN HAYES
Footing/Foundation/Slab 6/13/2022 Approved JOHN HAYES
Underground Mechanical 6/13/2022 Approved JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 10/4/2022 Partial Approval CALEB MEISTER
PLUMBING-Rough 10/4/2022 Corrections Issued CALEB MEISTER
PLUMBING-Rough 10/7/2022 Approved ARAM AVEDISIAN
Shower Pan 10/7/2022 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 10/21/2022 Approved ARAM AVEDISIAN
HVAC-Rough 10/21/2022 Partial Approval ARAM AVEDISIAN
Interior/Exterior Lathing 10/21/2022 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 11/4/2022 Approved CALEB MEISTER
Green Building Rough 11/4/2022 Approved CALEB MEISTER
Wood Frame 11/4/2022 Approved CALEB MEISTER
Insulation 11/14/2022 Approved ARAM AVEDISIAN
Drywall Nailing 11/21/2022 Approved KIRK SANDERS
Gas Test 1/4/2023 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 1/24/2023 Approved ARAM AVEDISIAN
ELECTRICAL-Final 1/24/2023 Not Ready for Inspection ARAM AVEDISIAN
Final 1/24/2023 Corrections Issued ARAM AVEDISIAN
Green Building Final 1/24/2023 Approved ARAM AVEDISIAN
HVAC-Final 1/24/2023 Approved ARAM AVEDISIAN
PLUMBING-Final 1/24/2023 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 1/24/2023 SGSOV Approved ARAM AVEDISIAN
Service/Power Release 1/24/2023 Not Ready for Inspection ARAM AVEDISIAN
Smoke Detectors 1/24/2023 Approved ARAM AVEDISIAN
ELECTRICAL-Final 1/31/2023 Approved ARAM AVEDISIAN
Final 1/31/2023 OK to Issue CofO ARAM AVEDISIAN
Service/Power Release 1/31/2023 Approved ARAM AVEDISIAN