4228 W LOS NIETOS DR 90027
Certificate Information: 4228 W LOS NIETOS DR 90027
- Application / Permit
- 18014-20000-02796
- Plan Check / Job No.
- B18VN08526
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD DECK (IRR 8'-11 1/2" X 11'-8") AT REAR, CONVERT (E) COVERED PATIO (11'-5" X 7'-8") TO EXTEND (E) LIVING ROOM & INTERIOR REMODEL
- Permit Issued
- Issued on 6/5/2019
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 3/16/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/21/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 5/21/2018 | NILOOFAR MEHRAIN |
| Corrections Issued | 5/21/2018 | NILOOFAR MEHRAIN |
| Building Plans Picked Up | 5/22/2018 | APPLICANT |
| Plan Check Approved | 5/25/2018 | NILOOFAR MEHRAIN |
| Issued | 6/5/2019 | LADBS |
| Permit Finaled | 3/16/2022 | JOSEPH MCGARRY |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/22/2018 | KAYLA PEJI |
| Hydrant and Access approval | Cleared | 5/22/2018 | JOHN DALLAS |
| Roof/Waste drainage to street | Cleared | 5/22/2018 | KAYLA PEJI |
| Sewer availability | Cleared | 5/22/2018 | KAYLA PEJI |
| Grading Pre-Inspection | Cleared | 5/25/2018 | NILOOFAR MEHRAIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/15/2019 | Corrections Issued | BRAD BESCOS |
| PLUMBING-Rough | 8/22/2019 | Not Ready for Inspection | BRAD BESCOS |
| Underground Mechanical | 8/27/2019 | Partial Approval | BRAD BESCOS |
| Excavation/Setback/Form/Re-Bar | 9/4/2019 | Corrections Issued | BRAD BESCOS |
| Footing/Foundation/Slab | 9/4/2019 | Not Ready for Inspection | BRAD BESCOS |
| Footing/Foundation/Slab | 9/13/2019 | Partial Approval | BRAD BESCOS |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2019 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Special/Order Compliance | 12/27/2019 | Approved | BRAD BESCOS |
| Pre-Inspection | 3/16/2021 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 4/21/2021 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 4/26/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Rough | 4/26/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 4/29/2021 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 4/29/2021 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 4/29/2021 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 4/29/2021 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 4/30/2021 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 4/30/2021 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 4/30/2021 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 5/10/2021 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 5/10/2021 | Approved | JOSEPH MCGARRY |
| Insulation | 5/10/2021 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 6/10/2021 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 6/10/2021 | Approved | THOMAS LOGRASSO |
| Shower Pan | 6/10/2021 | Approved | THOMAS LOGRASSO |
| Deck | 9/7/2021 | Approved | CHARLES BOGHOSKHAN |
| Shower Pan | 9/7/2021 | Approved | CHARLES BOGHOSKHAN |
| Footing/Foundation/Slab | 10/22/2021 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Final | 2/25/2022 | Corrections Issued | JOSEPH MCGARRY |
| Final | 2/25/2022 | Corrections Issued | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 2/25/2022 | Approved | JOSEPH MCGARRY |
| Green Building Final | 2/25/2022 | Approved | JOSEPH MCGARRY |
| HVAC-Final | 2/25/2022 | Corrections Issued | JOSEPH MCGARRY |
| PLUMBING-Final | 2/25/2022 | Corrections Issued | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 2/25/2022 | SGSOV Not Ready | JOSEPH MCGARRY |
| Smoke Detectors | 2/25/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Final | 3/10/2022 | Approved | JOSEPH MCGARRY |
| Final | 3/10/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| HVAC-Final | 3/10/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| PLUMBING-Final | 3/10/2022 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 3/10/2022 | SGSOV Approved | JOSEPH MCGARRY |
| Smoke Detectors | 3/10/2022 | Approved | JOSEPH MCGARRY |
| Special/Order Compliance | 3/10/2022 | Approved | JOSEPH MCGARRY |
| Final | 3/16/2022 | Permit Finaled | JOSEPH MCGARRY |