559 N LAS CASAS AVE 90272
Certificate Information: 559 N LAS CASAS AVE 90272
- Application / Permit
- 18014-20000-02590
- Plan Check / Job No.
- B18VN07943
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED (15'-6" X 30') ADDITION TO (E) 1-STORY SFD PER ENGINEERING. "COMPLY WITH DEPARTMENT ORDER effective date 04/02/2018. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 8/20/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/22/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/10/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 6/21/2018 | RAPHAEL ROSAS |
| Green Plans Picked Up | 6/22/2018 | APPLICANT |
| Corrections Issued | 6/25/2018 | RAPHAEL ROSAS |
| Quality Review Completed | 7/3/2018 | STEVEN KIM |
| Building Plans Picked Up | 7/9/2018 | APPLICANT |
| Applicant returned to address corrections | 8/16/2018 | RAPHAEL ROSAS |
| Plan Check Approved | 8/20/2018 | RAPHAEL ROSAS |
| Issued | 8/20/2018 | LADBS |
| CofO in Progress | 5/27/2021 | RYAN BARNES |
| Permit Finaled | 6/22/2021 | BRUCE TODD |
| CofO Issued | 6/22/2021 | BRUCE TODD |
| Permit Finaled | 6/22/2021 | BRUCE TODD |
Permit Application Clearance Information
| Green Code | Cleared | 8/1/2018 | DAVID MATSON |
| Eng Process Fee Ord 176,300 | Cleared | 8/7/2018 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 8/7/2018 | LEE GUILBEAUX |
| Sewer availability | Cleared | 8/7/2018 | LEE GUILBEAUX |
| Coastal Zone | Cleared | 8/10/2018 | ANNA VIDAL |
| Miscellaneous | Cleared | 8/10/2018 | ANNA VIDAL |
| ZI | Cleared | 8/10/2018 | ANNA VIDAL |
| Grading Pre-Inspection | Cleared | 8/16/2018 | RAPHAEL ROSAS |
| Miscellaneous | Cleared | 8/16/2018 | DAISY BENICIA |
| ZA Case | Cleared | 8/16/2018 | DAISY BENICIA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Haro, Ruben Jr; Lic. No.: C72213 | 1554 CIPRES CT CAMARILLO, CA 93010 |
| Engineer | Richman, Arthur Scott; Lic. No.: C66766 | PO BOX 994 PASADENA, CA 91031 |
| Geologist | Bovenizer, Ernest; Lic. No.: EG2515 | 7622 GODDARD AVENUE LOS ANGELES, CA 90045 |
Inspector Information
| ROBERT GARTH, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN MATTILLO, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO RIVERA, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| EUSEBIO GUZMAN, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL REECE, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDREW BEELI, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 8/28/2018 | Not Ready for Inspection | BRENDAN LOONEY |
| ELECTRICAL-Rough | 8/28/2018 | Not Ready for Inspection | BRENDAN LOONEY |
| Green Building Rough | 8/28/2018 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Rough | 8/28/2018 | Not Ready for Inspection | BRENDAN LOONEY |
| Footing/Foundation/Slab | 9/14/2018 | Partial Approval | BRENDAN LOONEY |
| PLUMBING-Rough | 9/14/2018 | Partial Approval | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 10/5/2018 | Not Ready for Inspection | BRENDAN LOONEY |
| ELECTRICAL-Rough | 10/5/2018 | Not Ready for Inspection | BRENDAN LOONEY |
| Green Building Rough | 10/5/2018 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Rough | 10/5/2018 | Not Ready for Inspection | BRENDAN LOONEY |
| Drywall Nailing | 10/10/2018 | Not Ready for Inspection | BRENDAN LOONEY |
| Green Building Rough | 10/10/2018 | Not Ready for Inspection | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 10/11/2018 | Corrections Issued | BRENDAN LOONEY |
| Drywall Nailing | 10/16/2018 | Not Ready for Inspection | BRENDAN LOONEY |
| Green Building Rough | 10/16/2018 | Not Ready for Inspection | BRENDAN LOONEY |
| Drywall Nailing | 10/19/2018 | Not Ready for Inspection | BRENDAN LOONEY |
| Green Building Rough | 10/19/2018 | Not Ready for Inspection | BRENDAN LOONEY |
| Drywall Nailing | 10/29/2018 | Not Ready for Inspection | BRENDAN LOONEY |
| Green Building Rough | 10/29/2018 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Rough | 11/1/2018 | Partial Approval | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 4/18/2019 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Rough | 4/18/2019 | Not Ready for Inspection | BRENDAN LOONEY |
| Green Building Rough | 4/18/2019 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Rough | 4/18/2019 | Not Ready for Inspection | BRENDAN LOONEY |
| Pre-Inspection | 4/18/2019 | Partial Approval | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 7/24/2019 | Corrections Issued | BRENDAN LOONEY |
| Green Building Rough | 7/24/2019 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Rough | 7/24/2019 | Corrections Issued | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2019 | Partial Approval | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 8/2/2019 | Not Ready for Inspection | BRENDAN LOONEY |
| Green Building Rough | 8/2/2019 | Not Ready for Inspection | BRENDAN LOONEY |
| Shower Pan | 8/2/2019 | Approved | BRENDAN LOONEY |
| Drywall Nailing | 8/6/2019 | Not Ready for Inspection | JOHN MATTILLO |
| Green Building Rough | 8/6/2019 | Not Ready for Inspection | JOHN MATTILLO |
| Interior/Exterior Lathing | 8/6/2019 | Not Ready for Inspection | JOHN MATTILLO |
| Footing/Foundation/Slab | 9/25/2019 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 10/9/2019 | Approved | BRENDAN LOONEY |
| ELECTRICAL-Rough | 10/9/2019 | Approved | BRENDAN LOONEY |
| Green Building Rough | 10/9/2019 | Approved | BRENDAN LOONEY |
| PLUMBING-Rough | 10/9/2019 | Approved | BRENDAN LOONEY |
| Insulation | 10/17/2019 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 10/17/2019 | Approved | BRENDAN LOONEY |
| Drywall Nailing | 10/23/2019 | Approved | BRENDAN LOONEY |
| Final | 12/18/2019 | Not Ready for Inspection | BRENDAN LOONEY |
| Green Building Final | 12/18/2019 | Not Ready for Inspection | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 12/18/2019 | SGSOV Not Ready | BRENDAN LOONEY |
| Smoke Detectors | 12/18/2019 | Not Ready for Inspection | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/14/2020 | Approved | BRENDAN LOONEY |
| Final | 1/24/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| Green Building Final | 1/24/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 1/24/2020 | SGSOV Approved | BRENDAN LOONEY |
| Smoke Detectors | 1/24/2020 | Approved | BRENDAN LOONEY |
| Final | 2/3/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| Green Building Final | 2/3/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| Final | 4/15/2021 | Corrections Issued | RYAN BARNES |
| Green Building Final | 4/15/2021 | Not Ready for Inspection | RYAN BARNES |
| Final | 5/18/2021 | Corrections Issued | RYAN BARNES |
| Green Building Final | 5/18/2021 | Approved | RYAN BARNES |
| Final | 5/27/2021 | Corrections Issued | RYAN BARNES |